The offshore operations involved over three hundred workers. Before shipping to the sea the more than 3,700 tonnes heavy jackets were moved up to the cargo pontoon 'Rahman Sharifov' and floated off. The fleet navigated to the offshore installation site via the Volga-
The company plans to mount topsides of the accommodation block and the ice resistant platform on the jackets in 2021. The start of production at the field is scheduled for 2022. The field's annual planned production rate is 1.2 million metric tonnes of oil.