BlueNord ASA related to the operational occurrence with the IP compressor temporarily impacting the commissioning of the new Tyra facilities during the ramp-up and testing period. Continued efforts and investigations are ongoing, however, the export volumes from Tyra II are expected to be impacted for the month of May 2024. Currently, the duration of the testing program and commissioning plan for achieving the technical milestones and driving the ramp-up to 8,1 mcm/d Technical Capacity is expected to be prolonged by at least 1 month.

The exact duration is to be determined pending outcome of the investigation.