Conditions and Application Process for Obtaining a Connection Certificate According to the Regulation on Connection to the
In accordance with the Regulation on Connection to
I. Who Can Obtain a Connection Certificate?
While it is mandatory to obtain a
II. Application Process and Documents:
In order for the
1. RES owners must first activate the infrastructure of the Managerial Control and Data Acquisition System ("SCADA") and the Power Quality Analyzer Device ("GKÇ") associated with the RES and measuring electrical parameters in accordance with the technical specifications specified in the RITM-IA. After the application is submitted, the power plant information form for
2. In the event that there are no deficiencies and/or errors in the power plant information form and it is determined that the SCADA and GKÇ data of the power plant reaches
III. Capacity Increase:
After the license amendment procedures are completed for WPPs that will increase power after connecting to
IV. Forecasting Service:
According to Article 9 of the Regulation, the forecasting service for WPPs with
1. TEİAŞ informs the relevant plant owner for the payment of the forecasting service fee following the storage of reliable SCADA and/or RAO data for the requested WPPs.
2. In case the document showing that the forecasting service fee has been paid is sent by e-mail, the forecast data is provided on a daily basis.
3. The forecast service fee is applied annually and published in RITM-IA in October.
4. Those who request the continuation of the forecasting service for the following year must send by e-mail a document showing that the set fee has been paid by
5.
V. Confidentiality and Data Sharing:
According to Article 10 of the Regulation, the confidentiality and security of the SCADA and GKÇ data received from WPPs by TEİAŞ is ensured. These data cannot be shared with third parties other than public institutions and organizations approved by TEİAŞ without the consent of the relevant plant owner.
VI. Obligations of the Power Plant:
According to Article 11 of the Regulation, the obligations of the power plant for which a
1. Continuous transfer of data in accordance with the format: SCADA and GKÇ data shall be in accordance with the specified format and shall be continuously transferred to RİTM in line with the power generation data and the infrastructure shall be kept in smooth operation. [Art.11/1(a) of the Regulation]
2. Notification of infrastructure changes: IP address, username, password and other infrastructure changes required for the transfer of SCADA and GKÇ data must be notified by e-mail within three business days. [Art.11/1(b) of the Regulation]
3. Notification of failures in data transfer: When malfunctions, interruptions or similar situations occurring in the transfer of SCADA and GKÇ data are detected, the relevant power plant should be notified, and the necessary interventions should be made within three business days and the situation should be notified by e-mail. [Article 11/1(c) of the Regulation]
4. Notification of changes in the power plant information form: Changes in the power plant information form submitted in the RİTM connection certificate request must be notified via electronic mail within three business days. [Art.11/1(ç) of the Regulation]
In case these obligations are not fulfilled, a written warning is given by TEİAŞ. If the obligations are still not fulfilled within seven calendar days following the date of the warning, the Ministry shall take the necessary measures.
The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.
Kesikli Law Firm
Kesikli Law Firm
Suadiye Mah. Bagdat Cad. No: 399
B Blok K: 4, D: 4,
Kadikoy
Tel: 216 348 29 24
Fax: 216 337 74 90
E-mail: omer@kesikli.com
URL: www.kesikli.com
© Mondaq Ltd, 2024 - Tel. +44 (0)20 8544 8300 - http://www.mondaq.com, source