Northern Vertex Mining Corp. announced that it has successfully completed the vendor commissioning phase of the start-up of the Moss Mine crushing plant. The initial testing phase of the crushing plant included 14 conveyors and 4 vibratory rock feeders, the jaw crusher, a K400 secondary cone crusher, two K500 tertiary cone crushers, the cement silo and cement feeder, and the agglomeration drum. The vendor representatives included Goodfellow Crushers, Kolberg-Pioneer, Johnson Crushers and WestPro Machinery. The initial commissioning phase included both the overland and grasshopper conveyors to deliver ore to the leach pad. The next phase of commissioning will focus on the implementation of the Programable Logic Control (PLC) programming and operations with the Human-Machine Interface (HMI), followed by calibration of the instrumentation. The first ore stacking on the leach pad should commence by early next week.