The Cerro Dominador solar thermal project, owned by
It was placed in the highest part of the central tower of the complex, which is surrounded by 10,600 heliostats.
The maneuver was completed in recent weeks, with the positioning of the receiver (piece of high complexity weighing 2,300 tons) in the foundation octagon, at 220 meters high in the central tower of the solar thermal plant. The function of the receiver is to concentrate the solar radiation reflected from the heliostats that are located around the 250-meter tower and heat the salts that will be stored to generate electricity.
The complete raising operation lasted a week, since the moment the receiver entered a cavity located at the base of the tower. Once inside, the receiver was raised to the top of the construction with 16 hydraulic industrial jacks. The ascent rate did not exceed five meters per hour, due to safety requirements and given the technical complexity of the entire procedure.
'We are very proud to have achieved this milestone. We continue advancing without pause in the construction of this iconic project for the region,' said
'This is the first time this maneuver has been carried out worldwide in this type of project,' as explained by Abengoa's project manager on
On the other hand,
About Abengoa
Abengoa (MCE: ABG/P: SM) applies innovative technology solutions for sustainability in the infrastructure, energy and water sectors.
Contact:
Tel: +34 954 93 71 11
Email: communication@abengoa.com
(C) 2020 Electronic News Publishing, source