Delivering reliable production

Delivered quarterly production of 44.5 MMboe (489 Mboe/day), down 5% from Q1 2023 due to planned turnaround and maintenance activities. Full-year production guidance remains unchanged at 180-190 MMboe.

Delivered sales volume of 48.4 MMboe, down 4% from Q1 2023, primarily due to lower production.

Delivered revenue of $3,084 million, down 29% from Q1 2023, due to lower realised prices and lower production.

Achieved a portfolio average realised price of $63/boe.

Sold 31% of produced LNG at prices linked to gas hub indices.

Executing major projects

Mad Dog Phase 2 successfully achieved first production at the Argos platform in April 2023, increasing production in the US Gulf of Mexico.

The Scarborough development was 38% complete at the end of the period, with manufacturing of the export trunkline complete and Pluto Train 2 module fabrication ramping up.

The Sangomar project was 88% complete at the end of the period, with 12 of 23 wells drilled and completed. The floating production storage and offloading (FPSO) topsides integration and pre-commissioning works continued in Singapore.

The Sangomar project is now targeting first oil in mid-2024 and the total cost of the project is expected to be US$4.9-5.2 billion, an increase of 7-13% from the previous cost estimate of US$4.6 billion.

Investing in growth

Approved a final investment decision to develop the Trion resource in Mexico, with the development remaining subject to regulatory approval of the field development plan (FDP).

Made a final investment decision on the Julimar-Brunello Phase 3 project.

Progressed contracting activities for the plant construction scope and schedule-critical packages for H2OK.

Page 1 of 16

Woodside CEO Meg O'Neill said:

"It was an extremely difficult period for everyone at Woodside, given the tragic death in early June of a contractor employee at the North Rankin Complex.

"Western Australian Police and the National Offshore Petroleum Safety and Environmental Management Authority (NOPSEMA) are investigating the incident and Woodside is conducting an internal investigation.

"Strong underlying operational performance in the second quarter was impacted by planned turnaround and maintenance activities particularly at the onshore Pluto LNG facility and associated offshore facilities in Western Australia.

"The team delivered a successful turnaround, completing the planned activities at Pluto on schedule.

"Whilst production and sales were lower compared with the first quarter of 2023, they were higher than the corresponding period last year, reflecting Woodside's expanded operations portfolio.

"In the US Gulf of Mexico, we commenced production from the Argos offshore facility. This was a significant milestone for the Mad Dog Phase 2 project and production is expected to ramp up through the year.

"The Scarborough and Pluto Train 2 project continued to make good progress and is now 38% complete. Fabrication of both the topsides and hull of the floating production unit has ramped up. The accommodation village in Karratha, which will service the Pluto Train 2 construction workforce, is now complete. Pluto Train 2 module fabrication and foundation site works is progressing well.

"We conducted a cost and schedule review at Sangomar following the identification of remedial work required on the FPSO. We have taken the prudent decision to conduct the remedial work while the FPSO remains at the shipyard in Singapore.

"This minimises the impact to the project schedule as it is safer, more efficient and more cost effective than undertaking the work offshore Senegal. First oil is now targeted for mid-2024.

"We also achieved an important step towards value-accretive investment in future growth, taking a final investment decision to develop the Trion oil field offshore Mexico, subject to the regulator's approval of the field development plan which is expected in the fourth quarter of this year. Trion is expected to deliver shareholder returns which exceed Woodside's capital allocation framework targets following its forecast start up in 2028.

"A final investment decision was also taken for the Julimar-Brunello Phase 3 project, which will provide a new supply of gas to the non-operated Wheatstone LNG facility in Western Australia.

"We are progressing contracting activities for the plant construction scope and other schedule-critical packages for H2OK and aiming to be ready for a final investment decision in 2023."

Comparative performance at a glance

Q2 2023

Q1 2023

Change %

Q2 20221

Change %

Production2

MMboe 44.5 46.8 (5%) 33.8 32%
Mboe/day 489 520 371

Sales

MMboe 48.4 50.4 (4%) 35.8 35%

Revenue

$ million 3,084 4,330 (29%) 3,438 (10%)
1

Q2 2022 reflects the performance of the interests acquired as part of the merger with BHP's Petroleum business from 1 June 2022.

2

Q2 2023 includes 0.23 MMboe, Q1 2023 includes 0.31 MMboe and Q2 2022 includes 0.30 MMboe primarily from feed gas purchased from Pluto non-operating participants processed through the Pluto-KGP Interconnector.

Page 2 of 16

Operational overview

Production

Production decreased compared to the previous quarter to 44.5 MMboe, primarily due to the planned major turnarounds on Pluto LNG and Ngujima-Yin FPSO. This was partly offset by seasonal demand from Bass Strait and higher production from Mad Dog following first production from the Argos facility in April 2023.

Australian LNG

Completed significant planned turnaround and maintenance activities on the onshore and offshore facilities at Pluto LNG on schedule, with production recommencing in June 2023.

Julimar-Brunello

Made a final investment decision on Julimar-Brunello Phase 3 in April 2023. The project involves the drilling of up to four development wells in the Julimar field and the installation of subsea infrastructure to connect to the existing Julimar field production system.

Bass Strait

Commenced the commercial tender process for decommissioning a number of facilities within the Gippsland Basin and continued plug and abandonment (P&A) of wells that are no longer producing.

Progressed front-end engineering design (FEED) work on Phase 1 of the South East Australia carbon capture and storage (SEA CCS) project. Phase 1 of the SEA CCS project aims to use existing infrastructure to store CO2 in the depleted Bream field off the coast of Gippsland, Victoria.

Gulf of Mexico

A successful appraisal well, SWX4, was drilled in the southwest part of the Mad Dog field. An extension of the current development through a multi-well tie-back to Argos is being evaluated.

The second of two wells was completed on the Shenzi North project. Subsea work is ongoing with the first of three subsea installation campaigns completed, installing manifolds and high integrity pressure-protection system packages. The project was 82% complete at the end of the period.

Australia Oil

The Ngujima-Yin FPSO successfully completed a planned five-yearly maintenance turnaround in a Singapore drydock with production expected to recommence in July 2023.

The Enfield P&A campaign continued with four wells permanently plugged and three xmas trees removed. The plugging of 13 of 18 Enfield wells and removal of 16 of 18 xmas trees has been completed.

Project and development activities

Mad Dog Phase 2

First production was successfully achieved at the Argos platform in April 2023. Production is expected to continue to ramp-up through 2023.

Scarborough

Scarborough upstream pipeline manufacturing is now complete, with pipeline coating ongoing. Ramp up of the floating production unit (FPU) fabrication for both the topsides and hull continued.

Pluto Train 2 module fabrication and foundation site works progressed. The construction accommodation village was completed.

Pluto Train 1 design activities and market engagement for long-lead items continued.

Page 3 of 16

The relevant Western Australian regulator accepted the Scarborough Trunkline Installation (State Waters) Environment Plan. Engagement with NOPSEMA continued regarding Commonwealth Environment Plans.

The project was 38% complete at the end of the period and first LNG cargo is targeted for 2026.

Sangomar Field Development Phase 1

A cost and schedule review was conducted following the identification of remedial work required on the FPSO facility.

First oil is now expected in mid-2024 and the total development cost is expected to be US$4.9-5.2 billion, representing a 7-13% increase from the previous cost estimate of US$4.6 billion.

FPSO topsides integration and pre-commissioning works continued in Singapore.

The development drilling program continued with 12 of 23 wells completed.

The subsea installation campaign was 76% complete, with the overall subsea work scope 95% complete at the end of the period.

The project was 88% complete at the end of the period.

Trion

In June 2023, Woodside made a final investment decision to develop the Trion resource in Mexico. The development is expected to deliver shareholder returns which exceed Woodside's capital allocation framework targets.3

Following Woodside's approval, the joint venture approved the FDP. The FDP was submitted to the regulator and approval is expected in Q4 2023.

Long-lead orders were placed for the FPU topsides rotating equipment.

The FPU engineering, procurement and construction contract was executed with Hyundai Heavy Industries.

New energy

H2OK

Contracting activities for the plant construction scope and other schedule critical packages progressed.

Woodside purchased 94 acres of land in the Westport Industrial Park in Ardmore, Oklahoma, for the proposed H2OK facility.

Woodside is targeting final investment decision readiness for H2OK in 2023.

Hydrogen Refueller @H2Perth

Awarded the contract for the engineering and fabrication of the hydrogen production equipment and submitted Western Australian environmental approval application documents. The Commonwealth environmental approval application documents were submitted subsequent to the quarter.

Woodside Solar:

Completed the solar electrical tie-in scope at the Pluto LNG facility during the 2023 Pluto shutdown.

Woodside Solar is targeting final investment decision readiness in 2023.

3

Forecast IRR and payback period assume Woodside equity of 60% in Trion; includes capital carry of approximately US$460m of capital expenditure for PEMEX (at Woodside's final investment decision). IRR and the payback period are a look forward from June 2023 and assume US$70/bbl (real terms 2022) Brent oil price. Payback period is calculated from undiscounted cash flows, RFSU + approximately 4 years.

Page 4 of 16

Marketing

Australian domestic gas

The long-term gas sale and purchase agreement (GSPA) with Perdaman Chemicals and Fertiliser Pty Ltd (Perdaman) became unconditional following a final investment decision being made by Perdaman on its 2.3 million tonne per annum urea plant, near Karratha, Western Australia. Supply under the GSPA is for approximately 130 terajoules per day of gas over a term of 20 years, commencing upon commissioning of the plant expected in 2026 or 2027.

Woodside executed several natural gas sales agreements for the combined supply of approximately 80 petajoules of pipeline gas to Western Australian domestic customers including retailers, commercial and industrial users. Delivery is expected to take place from Q4 2023 to the end of 2025.

Following an expression of interest (EOI) process, Woodside executed several natural gas sales agreements for the supply of approximately 40 petajoules of gas to domestic customers including retailers, commercial and industrial users in the eastern Australian gas market from 2024 to 2026.

Corporate activities

Hedging

Woodside has placed oil price hedges for approximately 21.8 Mmboe of 2023 production at an average price of approximately $74.5 per barrel, of which approximately 11.2 MMboe has been delivered. As at the end of the period, Woodside hedged approximately 6.2 MMboe of 2024 production at an average price of approximately $75.2 per barrel.

Subsequent to the period, Woodside placed oil price hedges on a further 19.8 MMboe of production and has now hedged approximately 26.0 MMboe of 2024 production at an average price of approximately $75.36 per barrel.

Woodside also has a hedging program for Corpus Christi LNG volumes designed to protect against downside pricing risk. These hedges are Henry Hub and Title Transfer Facility (TTF) commodity swaps. Approximately 81% of Corpus Christi volumes for the remainder of 2023 and approximately 29% of 2024 volumes have reduced pricing risk as a result of hedging activities.

The year-to-datepre-tax expense related to hedged positions is approximately $229 million, with $103 million pre-tax expense related to oil price hedges, $99 million pre-tax expense related to Corpus Christi hedges and $27 million pre-tax expense related to other hedge positions. Hedging losses will be included in "other expenses" in the half-year financial statements.

2023 half year results and teleconference

Woodside's Half-Year Report 2023 and associated investor briefing will be released to the market on Tuesday, 22 August 2023. It will also be available on Woodside's website at www.woodside.com.

A teleconference providing an overview of the 2023 half-year results and a question-and-answer (Q&A) session will be hosted by CEO and Managing Director, Meg O'Neill, and Chief Financial Officer, Graham Tiver, on Tuesday, 22 August at 08:00 AWST / 10:00 AEST / 19:00 CDT (Monday 21 August).

We recommend participants pre-register 5 to 10 minutes prior to the event with one of the following links:

https://webcast.openbriefing.com/wds-hyr-2023/ to view the presentation and listen to a live stream of the Q&A session

https://s1.c-conf.com/diamondpass/10031114-ldyp34.html to participate in the Q&A session. Following pre-registration, participants will receive the teleconference details and a unique access passcode.

Page 5 of 16

2023 full-year guidance

Prior Current

Production

MMboe 180 -190 No change

Capital expenditure

$ billion 6.0 - 6.5 No change

Gas hub exposure

% of produced LNG 20 - 25 No change

Half-year 2023 line-item guidance

Financial reporting guidance

Woodside's net profit after tax for the first half of 2023 is expected to include the recognition of a Pluto petroleum resource rent tax (PRRT) deferred tax asset (DTA) expense of approximately $630 million due to lower realised pricing in the first half of 2023 and lower forecast short-term pricing. The reduction of the DTA is recognised as an expense in the PRRT tax line item in the consolidated income statement in the financial statements and is included in the half-year 2023 line-item guidance below. The post-tax impact of the Pluto PRRT DTA expense is approximately $430 million.

Woodside also expects to recognise a DTA of approximately $320 million for Trion, following the final investment decision in June 2023. The recognition of the deferred tax asset represents the expected future tax benefit due to the expenditure incurred on the Trion project.

The Pluto PRRT DTA expense and the Trion DTA recognition are expected to be excluded from the underlying NPAT for the purposes of calculating the 2023 half-year dividend, consistent with prior practice.

Comments

Taxes

PRRT expense

$ million 750 - 1,000 Includes Pluto PRRT DTA expense of ~$630m.

Income tax expense

$ million 150 - 400 Includes Trion DTA recognition on final investment decision of ~$320m benefit; and the effect of the Pluto PRRT DTA expense of ~$200m.
Contacts:
INVESTORS MEDIA
Matthew Turnbull (Group) Christine Forster
M: +61 410 471 079 M: +61 484 112 469
E: christine.forster@woodside.com
Sarah Peyman (Australia)
M: +61 457 513 249
Rohan Goudge (US)
M: +1 (713) 679-1550
E: investor@woodside.com

This announcement was approved and authorised for release by Woodside's Disclosure Committee.

Page 6 of 16

Production summary

Three months ended Year to date
June
2023
Mar
2023
June
20224
June
2023
June
20224

AUSTRALIA

LNG

North West Shelf

Mboe 8,746 9,673 5,826 18,419 10,438

Pluto5

Mboe 8,765 12,154 12,328 20,919 21,654

Wheatstone

Mboe 2,588 2,456 1,645 5,044 4,053

Total

Mboe 20,099 24,283 19,799 44,382 36,145

Pipeline gas

Bass Strait

Mboe 4,170 3,133 2,353 7,303 2,353

Other6

Mboe 3,080 3,037 1,692 6,117 2,445

Total

Mboe 7,250 6,170 4,045 13,420 4,798

Crude oil and condensate

North West Shelf

Mbbl 1,546 1,684 1,104 3,230 1,910

Pluto5

Mbbl 699 961 967 1,660 1,712

Wheatstone

Mbbl 425 408 277 833 698

Bass Strait

Mbbl 904 777 441 1,681 441

Macedon & Pyrenees

Mbbl 759 631 223 1,390 223

Ngujima-Yin

Mbbl - 869 2,275 869 3,673

Okha

Mbbl 421 431 444 852 869

Total

Mboe 4,754 5,761 5,731 10,515 9,526

NGL

North West Shelf

Mbbl 339 292 228 631 409

Pluto5

Mbbl 45 50 60 95 66

Bass Strait

Mbbl 1,191 723 503 1,914 503

Total

Mboe 1,575 1,065 791 2,640 978

Total Australia7

Mboe 33,678 37,279 30,366 70,957 51,447
4

June 2022 reflects the performance of the interests acquired as part of the merger with BHP's Petroleum business from 1 June 2022.

5

Q2 2023 includes 1.96 MMboe of LNG, 0.08 MMboe of condensate and 0.04 MMboe of NGL, Q1 2023 includes 2.70 MMboe of LNG, 0.11 MMboe of condensate and 0.05 MMboe of NGL and Q2 2022 includes 2.51 MMboe of LNG and 0.10 MMboe of condensate and 0.06 MMboe of NGL processed at the Karratha Gas Plant (KGP) through the Pluto-KGP Interconnector.

6

Includes the aggregate Woodside equity domestic gas production from all Western Australian projects.

7

Q2 2023 includes 0.23 MMboe, Q1 2023 includes 0.31 MMboe and Q2 2022 includes 0.30 MMboe primarily from feed gas purchased from Pluto non-operating participants processed through the Pluto-KGP Interconnector.

Page 7 of 16

Three months ended Year to date
June
2023
Mar
2023
June
20228
June
2023
June
20228

INTERNATIONAL

Pipeline gas

Gulf of Mexico

Mboe 349 330 122 679 122

Trinidad & Tobago

Mboe 2,723 2,236 829 4,959 829

Other9

Mboe - 30 - 30 -

Total

Mboe 3,072 2,596 951 5,668 951

Crude oil and condensate

Atlantis

Mbbl 2,792 2,696 987 5,488 987

Mad Dog

Mbbl 1,627 939 411 2,566 411

Shenzi

Mbbl 2,599 2,596 765 5,195 765

Trinidad & Tobago

Mbbl 294 297 150 591 150

Other9

Mbbl 81 39 27 120 27

Total

Mboe 7,393 6,567 2,340 13,960 2,340

NGL

Gulf of Mexico

Mbbl 350 331 119 681 119

Other9

Mbbl - 17 - 17 -

Total

Mboe 350 348 119 698 119

Total International

Mboe 10,815 9,511 3,410 20,326 3,410

Total production

Mboe 44,493 46,790 33,776 91,283 54,857
8

June 2022 reflects the performance of the interests acquired as part of the merger with BHP's Petroleum business from 1 June 2022.

9

Overriding royalty interests held in the Gulf of Mexico (GoM) for several producing wells.

Page 8 of 16

Product sales

Three months ended Year to date
June
2023
Mar
2023
June
202210
June
2023
June
202210

AUSTRALIA

LNG

North West Shelf

Mboe 9,003 10,564 5,616 19,567 10,628

Pluto

Mboe 9,592 11,310 11,094 20,902 20,527

Wheatstone11

Mboe 2,312 2,350 1,464 4,662 3,985

Total

Mboe 20,907 24,224 18,174 45,131 35,140

Pipeline gas

Bass Strait

Mboe 4,113 3,082 2,194 7,195 2,194

Other

Mboe 3,040 2,939 1,629 5,979 2,377

Total

Mboe 7,153 6,021 3,823 13,174 4,571

Crude oil and condensate

North West Shelf

Mbbl 1,855 1,089 1,018 2,944 1,636

Pluto

Mbbl 614 614 1,828 1,228 2,300

Wheatstone

Mbbl 309 350 354 659 643

Bass Strait

Mbbl 1,035 82 333 1,117 333

Ngujima-Yin

Mbbl - 1,141 2,436 1,141 3,772

Okha

Mbbl - 653 619 653 619

Macedon & Pyrenees

Mbbl 1,032 518 - 1,550 -

Total

Mboe 4,845 4,447 6,588 9,292 9,303

NGL

North West Shelf

Mbbl 255 170 - 425 -

Pluto

Mbbl 73 182 - 255 -

Bass Strait

Mbbl 903 1,109 213 2,012 213

Total

Mboe 1,231 1,461 213 2,692 213

Total Australia

Mboe 34,136 36,153 28,798 70,289 49,227
10

June 2022 reflects the performance of the interests acquired as part of the merger with BHP's Petroleum business from 1 June 2022.

11

Includes periodic adjustments reflecting the arrangements governing Wheatstone LNG sales of 0.15 MMboe in Q2 2023, 0.06 MMboe in Q1 2023 and 0.06 MMboe in Q2 2022.

Page 9 of 16

Three months ended Year to date
June
2023
Mar
2023
June
202212
June
2023
June
202212

INTERNATIONAL

Pipeline gas

Gulf of Mexico

Mboe 341 343 127 684 127

Trinidad & Tobago

Mboe 2,700 2,295 836 4,995 836

Other13

Mboe 6 7 3 13 3

Total

Mboe 3,047 2,645 966 5,692 966

Crude oil and condensate

Atlantis

Mbbl 2,710 2,668 883 5,378 883

Mad Dog

Mbbl 1,628 941 379 2,569 379

Shenzi

Mbbl 2,652 2,673 718 5,325 718

Trinidad & Tobago

Mbbl 248 413 204 661 204

Other13

Mbbl 65 63 28 128 28

Total

Mboe 7,303 6,758 2,212 14,061 2,212

NGL

Gulf of Mexico

Mbbl 363 342 124 705 124

Other13

Mbbl 3 4 2 7 2

Total

Mboe 366 346 126 712 126

Total International

Mboe 10,716 9,749 3,304 20,465 3,304

MARKETING

LNG14

Mboe 3,532 4,483 3,741 8,015 7,079

Total

Mboe 3,532 4,483 3,741 8,015 7,079

Total Marketing

Mboe 3,532 4,483 3,741 8,015 7,079

Total sales

Mboe 48,384 50,385 35,843 98,769 59,610
12

June 2022 reflects the performance of the interests acquired as part of the merger with BHP's Petroleum business from 1 June 2022.

13

Overriding royalty interests held in the GoM for several producing wells.

14

Purchased LNG volumes sourced from third parties.

Page 10 of 16

Revenue (US$ million)

Three months ended Year to date
June
2023
Mar
2023
June
202215
June
2023
June
202215

AUSTRALIA

North West Shelf

667 1,270 523 1,937 1,159

Pluto

724 1,131 1,286 1,855 2,115

Wheatstone16

204 324 160 528 427

Bass Strait

328 211 232 539 232

Macedon

53 51 16 104 16

Ngujima-Yin

- 100 288 100 436

Okha

- 56 67 56 67

Pyrenees

89 50 1 139 1

INTERNATIONAL

Atlantis

203 199 109 402 109

Mad Dog

116 68 44 184 44

Shenzi

200 199 83 399 83

Trinidad & Tobago

112 136 66 248 66

Other17

4 5 3 9 3

Marketing revenue18

344 479 511 823 990

Total sales revenue19

3,044 4,279 3,389 7,323 5,748

Processing revenue

38 47 42 85 77

Shipping and other revenue

2 4 7 6 8

Total revenue

3,084 4,330 3,438 7,414 5,833

Realised prices

Three months ended Three months ended
Units June
2023
Mar
2023
June
202215
Units June
2023
Mar
2023
June
202215

LNG produced20

$/MMBtu 10.9 16.7 13.8 $/boe 69 105 87

LNG traded21

$/MMBtu 11.0 16.7 21.5 $/boe 70 105 137

Pipeline gas

$/boe 37 38 57

Oil and condensate

$/bbl 75 76 115 $/boe 75 76 115

NGL

$/bbl 41 51 48 $/boe 41 51 48

Average realised price

$/boe 63 85 95

Dated Brent

$/bbl 78 81 114

JCC (lagged three months)

$/bbl 87 100 86

WTI

$/bbl 73.8 76.1 108.4

JKM

$/MMBtu 12.6 26.0 31.3

TTF

$/MMBtu 12.6 24.7 31.6

Average realised price was A$6.1/GJ in Western Australia, A$12.6/GJ in east coast Australia and $6.7/Mcf for International in Q2 2023.

15

June 2022 reflects the performance of the interests acquired as part of the merger with BHP's Petroleum business from 1 June 2022.

16

Q2 2023 includes $11 million, Q1 2023 includes $3 million and Q2 2022 includes $5 million recognised in relation to periodic adjustments reflecting the arrangements governing Wheatstone LNG sales. These amounts will be included within other income/(expenses) in the financial statements rather than operating revenue.

17

Overriding royalty interests held in the GoM for several producing wells.

18

Values include revenue generated from purchased LNG volumes, as well as the marketing margin on the sale of Woodside's produced liquids portfolio. Hedging impacts are excluded.

19

Total sales revenue excludes all hedging impacts.

20

Realised prices include the impact of periodic adjustments reflecting the arrangements governing Wheatstone LNG sales.

21

Excludes any additional benefit attributed to produced LNG through third-party trading activities.

Page 11 of 16

Expenditure (US$ million)

Three months ended Year to date
June
2023
Mar
2023
June
202222
June
2023
June
202222

Exploration and evaluation expense

Exploration and evaluation expensed

81 52 27 133 34

Permit amortisation

2 2 2 4 3

Total

83 54 29 137 37

Capital expenditure

Exploration and evaluation capitalised23,24

92 37 5 129 10

Oil and gas properties

1,229 1,279 748 2,508 1,505

Total

1,321 1,316 753 2,637 1,515

Trading costs

237 385 442 622 793

Key project expenditure (US$ million)

Three months ended Year to date
June
2023
Mar
2023
June
2022
June
2023
June
2022

Capital expenditure

Scarborough25

578 626 353 1,204 800

Sangomar

272 279 207 551 449
22

June 2022 reflects the performance of the interests acquired as part of the merger with BHP's Petroleum business from 1 June 2022.

23

Exploration capitalised represents expenditure on successful and pending wells, plus permit acquisition costs during the period and is net of well costs reclassified to expense on finalisation of well results.

24

Project final investment decisions result in amounts of previously capitalised exploration and evaluation expense (from current and prior years) being transferred to oil and gas properties. This table does not reflect the impact of such transfers.

25

Scarborough key project expenditure includes Scarborough offshore, Pluto Train 2, Pluto Train 1 modification and Train 2 tie-in spend. Prior period comparatives have been restated to include Pluto Train 1 modification and Train 2 tie-in spend of $21 million in Q2 2022 and $34 million in YTD Q2 2022.

Page 12 of 16

Exploration

In the US Gulf of Mexico, Woodside acquired a 44% working interest in two leases in Green Canyon and spudded the Spinel well with co-owner and operator BP in early June 2023.

Woodside has acquired five of the leases for which it was the highest bidder in lease sale 259 - four operated and one non-operated.

Seismic acquisition was completed over Petroleum Exploration Licence 87, in the Orange Basin offshore Namibia. A decision on exercising the option to enter will follow evaluation of seismic data.

Exploration or appraisal wells drilled

Region

Permit
area

Well

Target

Interest (%)

Spud date Water
depth (m)
Planned well
depth (m)26

Remarks

Gulf of Mexico

GC 868 Mad Dog SWX4 Oil 23.9% Non-operator 12 March 2023 1,331 7,437 Drilling complete

Gulf of Mexico

GC 436 Spinel Oil 44% Non-operator 7 June 2023 1,258 7,042 Drilling ongoing

Permits and licences

Key changes to permit and licence holding during the quarter ended 30 June 2023 are noted below.

Region

Permits or licence areas

Change in
interest (%)
Current
interest (%)

Remarks

Myanmar

A-6 (40 ) 0

Operated

Korea

Blocks 8 & 6-1N

(50 ) 0

Operated

Trinidad & Tobago

TTDA-5

(65 ) 0

Operated

Gulf of Mexico

GC436, GC480

44 44 27

Non-operated

Gulf of Mexico

GC210, GC211,

100 100 Operated

AC125, AC126

Gulf of Mexico

GC598

40 40

Non-operated

Seismic and geophysical survey activity

Region

Field

Permits or licence areas

Remarks

Namibia PEL 87 - Orange Basin Deep Water PEL 87 Licence Acquisition of 6,593 km2 of 3D seismic completed
26

Well depths are referenced to the rig rotary table.

27

Pending regulatory approval.

Page 13 of 16

Production rates

Average daily production rates (100% project) for the quarter ended 30 June 2023:

Woodside
share28
Production rate

Remarks

(100% project, Mboe/d)
June
2023
Mar
2023

AUSTRALIA

NWS Project

LNG

29.91 % 321 340

Crude oil and condensate

29.98 % 57 59

NGL

33.27 % 11 10

Pluto LNG

LNG

90.00 % 83 117

Production was lower due to planned

facilities turnaround.

Crude oil and condensate

90.00 % 8 11

Pluto-KGP Interconnector

LNG

100.00 % 22 30
Crude oil and condensate 100.00 % 1 1

Production was lower due to planned

facilities turnaround.

NGL

100.00 % 0 1

Wheatstone29

LNG

11.86 % 240 229

Crude oil and condensate

14.90 % 31 30

Bass Strait

Pipeline gas

43.75 % 105 82

Production was higher due to seasonal

Crude oil and condensate

45.96 % 22 18

demand and reduced onshore and offshore

NGL

45.83 % 29 19

maintenance activities.

Australia Oil

Ngujima-Yin 60.00 % 0 16

Production was lower due to planned

maintenance turnaround.

Okha

50.00 % 9 10

Pyrenees

64.97 % 13 11

Other

Pipeline gas30

34 34
28

Woodside share reflects the net realised interest for the period.

29

The Wheatstone asset processes gas from several offshore gas fields, including the Julimar and Brunello fields, for which Woodside has 65% participating interest and is the operator.

30

Includes the aggregate Woodside equity domestic gas production from all Western Australian projects.

Page 14 of 16

Woodside
share31
Production rate

Remarks

(100% project, Mboe/d)
June
2023
Mar
2023

INTERNATIONAL

Atlantis

Crude oil and condensate

38.50 % 80 78

NGL

38.50 % 5 5

Pipeline Gas

38.50 % 7 6

Mad Dog

Crude oil and condensate

20.86 % 86 50

NGL

20.86 % 2 2

Mad Dog Phase 2 started up in April.

Pipeline Gas

20.86 % 2 1

Shenzi

Crude oil and condensate

64.39 % 44 45

NGL

64.39 % 2 2

Pipeline Gas

64.39 % 1 1

Trinidad & Tobago

Crude oil and condensate

61.07 %32 5 6

Pipeline gas

52.58 %32 57 56
31

Woodside share reflects the net realised interest for the period.

32

Operations governed by production sharing contracts, Woodside share changes monthly.

Page 15 of 16

Forward looking statements and other conversion factors

Disclaimer and important notice

This announcement contains forward-looking statements with respect to Woodside's business and operations, market conditions, results of operations and financial condition. All forward-looking statements contained in this announcement reflect Woodside's views held as at the date of this announcement. All statements, other than statements of historical or present facts, are forward-looking statements and generally may be identified by the use of forward-looking words such as 'guidance', 'foresee', 'likely', 'potential', 'anticipate', 'believe', 'aim', 'estimate', 'expect', 'intend', 'may', 'target', 'plan', 'forecast', 'project', 'schedule', 'will', 'should', 'seek' and other similar words or expressions. Similarly, statements that describe the objectives, plans, goals or expectations of Woodside or other statements about Woodside's future plans for projects and the timing thereof, the implementation of Woodside's strategy and Woodside's expectations and guidance with respect to production and certain financial and operating results, are or may be forward-looking statements. The information and statements in this announcement about Woodside's future strategy and other forward-looking statements are not guidance, forecasts, guarantees or predictions of future events or performance, but are in the nature of aspirational targets that Woodside has set for itself and its management of the business. Those statements and any assumptions on which they are based are only opinions and are subject to change without notice and are subject to inherent known and unknown risks, uncertainties, assumptions and other factors, many of which are beyond the control of Woodside, its related bodies corporate and their respective officers, directors, employees, advisers or representatives. Important factors that could cause actual results to differ materially from those in the forward-looking statements include, but are not limited to, fluctuations in commodity prices; actual demand; currency fluctuations; geotechnical factors; drilling and production results; gas commercialisation; development progress; operating results; engineering estimates; reserve estimates; loss of market; industry competition; environmental risks; climate related risks; physical risks; legislative, fiscal and regulatory developments; changes in accounting standards; economic and financial markets conditions in various countries and regions; political risks; project delay or advancement; regulatory approvals; the impact of armed conflict and political instability (such as the ongoing conflict in Ukraine) on economic activity and oil and gas supply and demand; cost estimates; the effect of future regulatory or legislative actions on Woodside or the industries in which it operates, including potential changes to tax laws; as well as general economic conditions, inflationary conditions, prevailing exchange rates and interest rates and conditions in financial markets. Details of the key risks relating to Woodside and its business can be found in the "Risk" section of Woodside's most recent Annual Report released to the Australian Securities Exchange and London Stock Exchange, and in Woodside's most recent Annual Report on Form 20-F filed with the U.S. Securities and Exchange Commission and available on the Woodside website at https://www.woodside.com/investors/reports-investor-briefings. You should review and have regard to these risks when considering the information contained in this announcement.

If any of the assumptions on which a forward-looking statement is based were to change or be found to be incorrect, this would likely cause outcomes to differ from the statements made in this announcement.

Investors are strongly cautioned not to place undue reliance on any forward-looking statements. Actual results or performance may vary materially from those expressed in, or implied by, any forward-looking statements. Except as required by law or regulation, Woodside does not undertake to update or revise any forward-looking statements contained in this announcement, whether as a result of new information, future events, or otherwise.

All figures are Woodside share for the quarter ending 30 June 2023, unless otherwise stated.

All references to dollars, cents or $ in this presentation are to US currency, unless otherwise stated.

References to "Woodside" may be references to Woodside Energy Group Ltd or its applicable subsidiaries.

Product

Unit Conversion
factor

Natural gas

5,700 scf 1boe

Condensate

1bbl 1boe

Oil

1bbl 1boe

Natural gas liquids (NGL)

1bbl 1boe

Facility

Unit LNG conversion
factor

Karratha Gas Plant

1tonne 8.08 boe

Pluto Gas Plant

1tonne 8.34 boe

Wheatstone

1tonne 8.27 boe
bbl barrel
bcf billion cubic feet of gas
boe barrel of oil equivalent
Mbbl thousand barrels
Mboe thousand barrels of oil equivalent
Mcf thousand cubic feet of gas
MMboe million barrels of oil equivalent
MMBtu million British thermal units
MMscf million standard cubic feet of gas
scf standard cubic feet of gas

The LNG conversion factor from tonne to boe is specific to volumes produced at each facility and is based on gas composition which may change over time.

Page 16 of 16

Attachments

Disclaimer

Woodside Energy Group Ltd. published this content on 19 July 2023 and is solely responsible for the information contained therein. Distributed by Public, unedited and unaltered, on 19 July 2023 10:09:46 UTC.