Denmark’s largest gas field is on track to relaunch production in March after lengthy and extension renovation, its operator reported this week.
The
The project was initially expected to be completed in 2022, but global supply chain issues caused by the coronavirus (COVID-19) pandemic delayed key work at an Indonesian shipyard, as well as other tasks. The cost of the project has also risen as a result of the complications, from
Progress is being made on the final stages of the Tyra redevelopment programme, the
If you’d like to read more about the key events shaping Europe’s oil and gas sector then please click here for NewsBase’s EurOil Monitor.