Updated Preliminary
Economic Assessment,
Bolivar Mine, Mexico

Effective Date: December 31, 2019

Original Report Date: October 19, 2020

Report Updated: September 21, 2021

Prepared for

Sierra Metals Inc.

Signed by Qualified Persons:

Américo Zuzunaga Cardich, Sierra Metals Inc., Vice President Corporate Planning

Cliff Revering, P. Eng., SRK Principal Consultant (Resource Geology)

Carl Kottmeier, B.A.Sc., P. Eng., MBA, SRK Principal Consultant (Mining)

Daniel H. Sepulveda, BSc, SME-RM, SRK Associate Consultant (Metallurgy)

Jarek Jakubec, C. Eng. FIMMM, SRK Practice Leader/Principal Consultant (Mining, Geotechnical)

Prepared by

SRK Consulting (Canada) Inc.

2US043.005

September 2021

Updated Preliminary Economic Assessment, Bolivar Mine, Mexico

September 2021

Prepared for Prepared by

Sierra Metals Inc.

Av. Pedro de Osma
No. 450, Barranco,
Lima 04, Peru

SRK Consulting (Canada) Inc.

2200-1066 West Hastings Street

Vancouver, B.C., V6E 3X2

Canada

Tel: +51 1 630 3100

Web: https://www.sierrametals.com

Tel: +1 604 681 4196

Web: www.srk.com

Project No: 2US043.005

File Name: Bolivar_TR_PEA_Update_2US043.005_20210927.docx

Copyright © SRK Consulting (Canada) Inc., 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page ii

Important Notice

This PEA report was prepared as a National Instrument 43-101 Technical Report for Sierra Metals Inc. ("Sierra Metals") by SRK Consulting (Canada) Inc. ("SRK"). The quality of information, conclusions, and estimates contained herein is consistent with the level of effort involved in SRK's services, based on: i) information available at the time of preparation, ii) data supplied by outside sources, and iii) the assumptions, conditions, and qualifications set forth in this report. This report is intended for use by Sierra Metals subject to the terms and conditions of its contract with SRK and relevant securities legislation. The contract permits Sierra Metals to file this report as a Technical Report with Canadian securities regulatory authorities pursuant to National Instrument 43-101, Standards of Disclosure for Mineral Projects. Except for the purposes legislated under provincial securities law, any other uses of this report by any third party is at that party's sole risk. The responsibility for this disclosure remains with Sierra Metals. The user of this document should ensure that this is the most recent Technical Report for the property as it is not valid if a new Technical Report has been issued.

Copyright

This report is protected by copyright vested in SRK Consulting (Canada) Inc. It may not be reproduced or transmitted in any form or by any means whatsoever to any person without the written permission of the copyright holder, other than in accordance with stock exchange and other regulatory authority requirements.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page iii

1Executive Summary

Sierra Metals Inc. (Sierra Metals) own and operate the Bolivar Mine and Piedras Verdes processing plant (combined to form the Property) located in the Piedras Verdes District of Chihuahua State, Mexico, approximately 250 km southwest of the city of Chihuahua. The Property consists of 14 mineral concessions totalling 6,800 ha.

This updated report is based on a Preliminary Economic Assessment (PEA) that was previously prepared for the Bolivar Mine with a report date of October 19, 2020. This amended PEA report is unchanged from the original PEA report except to include language with regards to the potential recovery and sale of magnetite. More specifically, changes were made to relevant portions of Sections 1, 25 and 26 summarized therefrom changes to Section 2 - Introduction, and where relevant, updates regarding the recovery and sale of magnetite were made to the following sections: Section 13 - Mineral Processing and Metallurgical Testing, Section 17 - Recovery Methods, Section 18 - Infrastructure, Section 21 - Capital and Operating Costs, and Section 22 - Economic Analysis.

This Preliminary Economic Assessment (PEA) report was prepared in accordance with the Canadian Institute of Mining, Metallurgy and Petroleum Standards on Mineral Resources and Reserves: Definitions and Guidelines, May 10, 2014 (CIM, 2014).

The reader is reminded that PEA studies are indicative and not definitive and that the resources used in the proposed mine plan include Inferred Resources that are too speculative to be used in an economic analysis, except as allowed for by the Canadian Securities Administrators (CSA) National Instrument 43-101 (NI 43-101) in PEA studies. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. There is no certainty that Inferred Resources can be converted to Indicated or Measured Resources or Mineral Reserves, and as such, there is no certainty that the results of this PEA will be realized.

This PEA report is not a wholly independent report as some sections have been prepared and signed off by qualified persons (QPs) from Sierra Metals, the project owner and producing issuer. The terms 'QP' and 'producing issuer' used here are as defined under NI43-101 Standards of Disclosure for Mineral Projects. The QPs responsible for this report are listed in Sections 2.1 and 2.2.

1.1 Property Description and Ownership

The Bolivar Property is owned by Sierra Metals. The Property consists of 14 mineral concessions (approximately 6,800 ha) in the northern Mexican state of Chihuahua. The Property is in the Piedras Verdes mining district, 400 km south by road from the city of Chihuahua (population 4.8 million as of 2010) and roughly 10 km southwest of the town of Urique (population 1,102 as of 2010). The Property includes the Bolivar Mine, an historic Cu-Zn skarn deposit that has been actively mined by Sierra Metals since November 2011, as well as the Piedras Verdes processing plant, which is situated approximately 5 km by road from the mine.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page iv
1.2 Geology and Mineralization

The Bolivar deposit is a Cu-Zn skarn and is one of many precious and base metal deposits of the Sierra Madre belt, which trends north-northwest across the states of Chihuahua, Durango and Sonora in northwestern Mexico (Meinert, 2007). The deposit is located within the Guerrero composite terrane, which makes up the bulk of western Mexico and is one of the largest accreted terranes in the North American Cordillera. The Guerrero terrane, proposed to have accreted to the margin of nuclear Mexico in the Late Cretaceous, consists of submarine and lesser subaerial volcanic and sedimentary sequences ranging from Upper Jurassic to middle Upper Cretaceous in age. These sequences rest unconformably on deformed and partially metamorphosed early Mesozoic oceanic sequences.

The Piedras Verdes district is made up of Cretaceous andesitic to basaltic flows and tuffs intercalated with greywacke, limestone, and shale beds. Cu-Zn skarn mineralization is in carbonate rocks adjacent to the Piedras Verde granodiorite. Mineralization exhibits strong stratigraphic control and two stratigraphic horizons host the bulk of the mineralization: an upper calcic horizon, which predominantly hosts Zn-rich mineralization, and a lower dolomitic horizon, which predominantly hosts Cu-rich mineralization. In both cases, the highest grades are developed where structures and associated breccia zones cross these favorable horizons near skarn-marble contacts.

1.3 Status of Exploration, Development and Operations

The Bolivar Mine is currently an operational project. During 2019, the Piedras Verdes processing plant consistently produced copper concentrate of commercial quality with copper grade ranging between 21.7% Cu to 28% Cu, silver content in concentrate ranging from 392 g/t to 677 g/t, and gold content in concentrate ranging from 3.2 g/t to 7.9 g/t. Metal recovery for copper, silver, and gold averaged monthly 82.9%, 78.3% and 62.3%, respectively. The mined material is transported 5 km to the Piedras Verdes mill which currently operates at 3,500 tonnes of mineralized material per day (tpd).

1.4 Mineral Processing and Metallurgical Testing

Various development and test mining have occurred at the Bolivar Mine under Sierra Metal's ownership since 2005. Prior to late 2011, no processing facilities were available on site, and the mineralized material was trucked to the Cusi Mine's Malpaso mill located 270 km by road. Bolivar's Piedras Verdes processing facilities started operating in November 2011 at 1,000 tpd of nominal throughput. The mineralized material processing capacity was expanded to 2,000 tpd in mid-2013. The mill has been upgraded since and the current nominal throughput capacity is 3,500 tpd.

1.5 Mineral Resource Estimate

CIM Definition Standards for Mineral Resources and Mineral Reserves (May 2014) defines a Mineral Resource as follows:

"A Mineral Resource is a concentration or occurrence of solid material of economic interest in or on the Earth's crust in such form, grade or quality and quantity that there are reasonable prospects for eventual economic extraction. The location, quantity, grade or quality, continuity and other geological characteristics of a Mineral Resource are known, estimated or interpreted from specific geological evidence and knowledge, including sampling".

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page v

The "reasonable prospects for economic extraction" requirement generally implies that the quantity and grade estimates meet certain economic thresholds and that the Mineral Resources are reported at an appropriate cut-off grade (CoG) taking into account extraction scenarios and processing recoveries. To assess this at Bolivar, SRK has calculated an economic value for each block in terms of US dollars based on the grade of contained metal in the block, multiplied by the assumed recovery for each metal, multiplied by pricing established by Sierra Metals for each commodity. Costs for mining and processing are taken from data provided by Sierra Metals for their current underground mining operation.

The December 31, 2019, consolidated Mineral Resource statement for the Bolivar Mine is presented in Table 1-1.

Table 1-1: Consolidated Bolivar Mine Mineral Resource Statement as of December 31, 2019 - SRK Consulting (Canada), Inc. (1)(2)(3)(4)(5)

Category Tonnes
(Mt)
Ag (g/t) Au (g/t) Fe (%) Cu (%)

Ag

(M oz)

Au

(k oz)

Cu (t)
Indicated 19.4 15.1 0.21 13.8 0.77 9.4 127.8 149,116
Inferred 21.4 14.2 0.21 13.5 0.78 9.8 145.6 167,077

Source: SRK, 2020

(1) Mineral resources are reported inclusive of ore reserves.
(2) Mineral resources are not ore reserves and do not have demonstrated economic viability.
(3) All figures are rounded to reflect the relative accuracy of the estimates.
(4) Mineral resources are reported at a value per tonne cut-off of US$24.25/t using the following metal prices and recoveries; Cu at US$3.08/t and 88% recovery; Ag at US$17.82/oz and 78.6% recovery, Au at US$1,354/oz and 62.9% recovery.

(5) Total Fe does not represent an estimate of magnetite content nor should be used as a proxy for a recoverable

magnetite product.

1.6 Mineral Reserve Estimate

A Mineral Reserve is the economically mineable part of a Measured and/or Indicated Resource. It includes diluting material and allowances for losses, which may occur when the material is mined or extracted and is defined by studies at Pre-feasibility or Feasibility level as appropriate that include the application of Modifying Factors.

A Mineral Reserve has not been estimated for the project as part of this PEA.

The PEA includes Inferred Mineral Resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as Mineral Reserves.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page vi
1.7 Mining Methods

Bolivar Mine is a producing operation. The primary mining method is underground room and pillar mining. Previous mining at Bolivar has sometimes used lower cost and more productive longhole stope mining in areas where the mineralized zones have a steeper dip angle, and the mine plans to undertake a geotechnical assessment program in 2020/2021 to expand the use of longhole stope mining.

Current mineralized material production is from the El Gallo Inferior, Chimenea 1 and 2, and the Bolivar West mineralized zones.

The PEA evaluated seven different possible production rates for the Bolivar Mine:

· 5,000 tpd (base case)
· 7,000 tpd in 2024
· 10,000 tpd in 2024
· 10,000 tpd in 2026
· 12,000 tpd in 2024
· 12,000 tpd in 2026
· 15,000 tpd in 2024

An economic analysis of these production rates is provided in Section 22.

Development waste rock is primarily stored underground in historic mine openings. Mineralized material is hauled to the surface using one of several adits or declines accessing the mineralized material, and then dumped onto small surface storage pads outside the portals. The mineralized material is then loaded into rigid-frame, over-the-road trucks and hauled on a gravel road approximately 5 km south to the Piedras Verdes mill. As explained in more detail in Section 18, the mine is constructing an underground tunnel that will enable mineralized material to be delivered via underground truck transport to a portal adjacent to the mill. This development will eliminate the impact of bad weather on the current surface truck haulage system and will provide a lower cost and more reliable method of delivering mineralized material to the plant.

Mine production at Bolivar in 2019 averaged approximately 3,500 tpd, but frequently surpassed 4,000 tpd and achieved rates of 5,000 tpd in early 2020.

1.8 Recovery Methods

Sierra Metals operates a conventional concentration plant consisting of crushing, grinding, flotation, thickening, and filtration of the final concentrate. Flotation tails are disposed of in a conventional tailings facility and future tailings (mid-2020) will be deposited as dry-stack tailings. Run of mine mineralized material feed in 2019 totaled 1,269,697 t, equivalent to an average of 105,000 tonnes per month (t/m), or 3,500 tpd. The plant has repeatedly demonstrated that it can process 5,000 tpd and is doing so in 2020.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page vii

During 2019, production of copper concentrate consistently ranged between approximately 2,370 t/m and 3,850 t/m, equivalent to roughly a 2.9% mass pull. The monthly average concentrate consistently reached commercial quality with copper grade averaging 24.1% Cu and credit metals content in concentrate averaging 531.6 g/t silver and 5.57 g/t gold. Average monthly metal recovery for copper, silver, and gold was 82.9%, 78.3% and 62.3%, respectively.

1.9 Project Infrastructure

The project has fully developed infrastructure including access roads, a man-camp capable of supporting 329 persons that includes a cafeteria, laundry facilities, maintenance facilities for the underground and surface mobile equipment, electrical shop, guard house, fuel storage, laboratories, warehousing, storage yards, administrative offices, plant offices, truck scales, explosives storage, processing plant and associated facilities, tailings storage facility (TSF), and water storage reservoir and water tanks.

The site has fully developed and functioning electric power from the Mexican power grid, backup diesel generators and heating from site propane tanks.

The project has developed waste handling and storage facilities. The site has minimal waste rock requirements but does have a small, permitted area to dispose of waste rock. The tailings management plan at the Bolivar Mine includes placement of tails in several locations in and around the TSF that has been in operation since late 2011. The existing TSF has five locations to store tailings (TSF1 through TSF5).

A new dry-stack TSF (herein referred to as "New TSF") is to be located just to the west of the existing facility and has an expected life through 2025. The site is also installing an additional thickener and filter presses to allow additional water recovery. Thickened tails (60% solids) are being placed currently. After the filter presses are constructed, dry-stack tailings will be placed in the TSF starting in the latter part of 2020.

This PEA considers the use of tailings as backfill and has included the capital and operating costs for a backfill plant. Storing some of the tailings underground would increase the life of the TSF, and potentially permit the removal of mineralized material pillars that are currently unrecoverable.

The overall Project infrastructure exists already and is functioning and adequate for the purpose of the supporting the mine and mill.

1.10 Environmental Studies and Permitting

Sierra Metals intends to build additional tailings capacity concurrent with mine operations, and the permitting associated with the TSF expansion has been completed.

Geochemical characterization results for 2014 and 2015, provided to SRK, indicate low metals leaching potential and either uncertain or non-acid generating potential. The 2016 ABA results (NP = 52.5 kg CaCO3/ton; AP = 141 kg CaCO3/ton), however, suggest that some of the more recent material may be potentially acid generating: NP/AP = 0.372. Additional investigation of the current materials being deposited into the tailings impoundment may be warranted; however, given the dryness of the Chihuahuan Desert, this may not necessarily be a material issue for the project.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page viii

The required permits for continued operation at the Bolivar Mine, including exploration of the site, have been obtained. SRK has not conducted an investigation as to the current status of all the required permits. At this time, SRK is not aware of any outstanding permits or any non-compliance at the project or nearby exploration sites.

In February 2017, Treviño Asociados Consultores presented to Sierra Metals a work breakdown of the anticipated tasks for closure and reclamation of the Bolivar Mine. The closure costs were estimated to be MX$9,259,318 (~US$475,324 based on the exchange rate at February 2020). SRK's scope of work did not include an assessment of the veracity of this closure cost estimate, but, based on projects of similar nature and size within Mexico, the estimate appears low in comparison.

1.11 Capital and Operating Costs

Based on a planned production rate of 10,000 tpd (2024), the yearly capital expenditure by area is summarized in Table 1-2.

Table 1-2: Capital Cost Summary (not including magnetite recovery project)

Description Total [US$ 000s]
Development sustaining capital 89,940
Ventilation sustaining capital 4,588
Development expansion capital 5,852
Equipment sustaining capital 41,200
Exploration sustaining capital 18,800
Exploration capital 35,897
Backfill plant capital 24,884
Plant sustaining capital 13,940
Plant expansion capital 67,500
Tailings storage facility capital 5,369
Tailings storage facility sustaining capital 1,380
Additional studies capital 2,274
Closure capital 5,000
Total Capital 316,624

Source: Sierra Metals, 2020

The addition of the proposed magnetite recovery project adds capital expenditure and is shown in Table 1-3 for the 10,000 tpd (2024) production case.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page ix

Table 1-3: Capital Cost Summary (including magnetite recovery project)

Description Total [US$ 000s]
Development sustaining capital 89,940
Ventilation sustaining capital 4,588
Development expansion capital 5,852
Equipment sustaining capital 41,200
Exploration sustaining capital 18,800
Exploration capital 35,897
Backfill plant capital 24,884
Plant sustaining capital 13,940
Plant expansion capital 67,500
Tailings storage facility capital 5,369
Tailings storage facility sustaining capital 1,380
Magnetite recovery project 28,172
Additional studies capital 2,274
Closure capital 5,000
Total Capital 344,796

Source: Sierra Metals, 2021

The operating cost estimate is based on site specific data and has been factored to account for an expansion to 10,000 tpd (2024). Table 1-4 provides a summary of total operating costs and unit operating costs.

Table 1-4: Operating Cost Summary (not including magnetite recovery project)

Description Life of Mine Life of Mine Life of Mine
(US$000's) (US$/t mineralized material) (US$/Cu equivalent lb)
Underground Mining 433,099 10.36 0.61
Process 225,578 5.40 0.32
G&A 55,409 1.33 0.08
Backfill plant 112,383 2.69 0.16
Total Operating 826,469 19.77 1.16

Source: Sierra Metals, 2020

Note: numbers may not add up due to rounding

The addition of the proposed magnetite recovery project adds operating expenditure and is shown in Table 1-5 for the 10,000 tpd (2024) production case. The LOM US$/Cu equivalent lb data is shown in two ways, with and without the magnetite sales revenue included.

Table 1-5: Operating Cost Summary (including magnetite recovery project)

Description

LOM

(US$ 000s)

LOM

(US$/t mineralized material)

LOM US$/Cu lb equivalent (without magnetite sales revenue) LOM US$/Cu lb equivalent (with magnetite sales revenue)
Underground Mining 433,099 10.36 0.61 0.51
Process 225,578 5.37 0.32 0.27
G&A 55,409 1.33 0.08 0.07
Magnetite recovery 290,958 6.96 0.41 0.34
Backfill plant 112,383 2.69 0.16 0.13
Total Operating 1,117,427 26.73 1.56 1.32

Source: Sierra Metals, 2021

Note: numbers may not add up due to rounding

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page x
1.12 Economic Analysis

The economic analysis for this PEA was prepared by Sierra Metals and reviewed by SRK. The analysis is based on Mineral Resources only and includes Inferred Mineral Resources. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability and must be supported at least by a pre-feasibility study. This PEA is preliminary in nature and there is no certainty that the results of the PEA will be realized.

The economic results shown in subsection 1.12 do not include the magnetite recovery project. Subsection 1.13 is an update to this PEA report and describes the economic analysis of the magnetite recovery project.

The commodity prices, and their sources, used in the economic analysis are described in Section 19 and are shown in Table 1-6.

Table 1-6: Commodity Price Forecast by Year

Metal Unit 2020 2021 2022 2023 Long Term (LT)
Au $/oz 1,755 1,907 1,782 1,737 1,541
Ag $/oz 19.83 24.12 22.22 22.47 20.0
Cu $/lb 2.65 2.86 2.89 2.93 3.05
Pb $/lb 0.82 0.87 0.89 0.90 0.91
Zn $/lb 0.94 0.99 1.04 1.04 1.07

Source: Sierra Metals, 2020

In addition to the prices listed above in Table 1-6, the NSR factors in Table 1-7 and the economic factors in Table 1-8 were also used in the economic analysis.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page xi

Table 1-7: NSR Factors

Process Recoveries*
Cu % 88
Ag % 78.7
Au % 62.43
Concentrate Grades
Cu % 25
Ag g/t 570
Au g/t 6.8
Moisture content % 8
Freight, Insurance and Marketing
Transport losses % 0.5
Transportation US$/wmt 42
Port US$/wmt 9
Load US$/wmt 40
Marketing US$/dmt 10
Insurances US$/wmt 10
Total US$/dmt 102.92
Smelter Terms
Cu payable % 96
Ag payable % 90
Au payable % 92
Cu minimum deduction % 1
Ag minimum deduction oz/t 0
Au minimum deduction oz/t 0
Treatment Charges/Refining Charges (TC/RC)
Cu Concentrate TC US$/dmt 69.00
Cu Refining charge US$/lb Cu 0.069
Cu Refining cost US$/t Cu 152.12
Cu Price Participation US$/dmt 0
Average Penalties US$/dmt 10
Ag Refining charge US$/oz 0.35
Au Refining charge US$/oz 6
Total treatment cost US$/t Cu 727.68
Total cost of sales US$/t Cu 879.80
Net Smelter Return Factors
Cu US$/t/% 48.8171
Ag US$/t/g/t 0.4444
Au US$/t/g/t 28.1940

Source: Sierra Metals, 2020

* NI 43-101 Technical Report (SRK Consulting (Canada) Inc. May 8, 2020)

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page xii

Other economic factors and assumptions used in the economic analysis include:

Table 1-8: Economic Factors

Measure Unit Value
Discount Rate % 8
LOM Average grade - Au g/t 0.19
LOM Average grade - Ag g/t 13.56
LOM Average grade - Cu % 0.72
Ordinary Mining Entitled Royalty US$/year 220,000
Extraordinary Mining Entitled Royalty (applied to precious metals) % 0.5
Variable Special Mining Royalty US$/year Depends on operating margin
Tax Rate % 30

Source: Sierra Metals, 2020

Numbers are presented on a 100% ownership basis and do not include financing costs.

The economic analysis is based on mine schedule, CAPEX and OPEX estimation, and price assumptions detailed above. Table 1-9 shows the results of the economic evaluations for the production rates evaluated in this PEA using the metal prices in Table 1-6. The production rate option of 15,000 tpd (2024) has the highest post tax NPV with respect to the other options and both the 10,000 tpd (2024) and 12,000 tpd (2024) options have better returns than their 2026 counterparts.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page xiii

Table 1-9: Summary Economic Evaluation

Summary Economic Evaluation
Description Units

5 KTPD

7 KTPD 10 KTPD 10 KTPD 12 KTPD 12 KTPD 15 KTPD
2024 2024 2026 2024 2026 2024
Life of mine Years 24 18 14 15 13 13 11
Market Prices (Long Term)
Gold $/oz 1,541 1,541 1,541 1,541 1,541 1,541 1,541
Silver $/oz 20 20 20 20 20 20 20
Copper $/lb 3.05 3.05 3.05 3.05 3.05 3.05 3.05
Net Sales
Gold k$ 233,617 233,617 233,617 233,617 233,617 233,617 233,617
Silver k$ 265,316 265,316 265,316 265,316 265,316 265,316 265,316
Copper k$ 1,680,297 1,680,297 1,680,297 1,680,297 1,680,297 1,680,297 1,680,297
Gross Revenue k$ 2,179,230 2,179,230 2,179,230 2,179,230 2,179,230 2,179,230 2,179,230
Charges for treatment, refining, impurities k$ 172,461 172,461 172,461 172,461 172,461 172,461 172,461
Gross Revenue After Selling and Treatment Costs k$ 2,006,769 2,006,769 2,006,769 2,006,769 2,006,769 2,006,769 2,006,769
Royalties and Mining Permits k$ 83,539 88,233 94,097 93,335 96,937 95,509 99,936
Gross Revenue After All Costs k$ 1,923,230 1,918,536 1,912,672 1,913,435 1,909,832 1,911,260 1,906,833
Operating Costs
Mine k$ 512,790 472,036 433,099 438,771 414,747 423,093 393,612
Plant k$ 259,792 242,443 225,578 228,035 217,521 221,151 208,147
G&A k$ 78,009 73,397 55,409 58,030 48,414 52,053 41,419
Back Fill k$ 145,984 128,510 112,383 114,732 104,987 108,413 96,638
Total Operating k$ 996,574 916,385 826,469 839,567 785,669 804,711 739,815
EBITDA k$ 926,656 1,002,151 1,086,203 1,073,867 1,124,163 1,106,550 1,167,018
LoM Capital + Sustaining Capital k$ 244,825 268,624 316,624 319,854 355,105 357,639 408,345
Working Capital k$ 18,849 18,276 18,146 18,696 18,950 17,566 18,146
Income Taxes k$ -209,021 -220,058 -230,874 -230,410 -242,044 -224,673 -230,807
Cash flow before Taxes k$ 662,982 715,251 751,433 735,317 750,108 731,344 740,527
Cash flow after Taxes k$ 453,961 495,193 520,559 504,908 508,064 506,671 509,720
Post Tax NPV @ 5% k$ 282,882 320,898 350,787 334,178 349,978 336,798 354,455
Post Tax NPV @ 8% k$ 225,191 256,236 282,546 267,228 284,080 268,832 288,105
Post Tax NPV @ 10% k$ 197,271 223,529 246,605 232,484 248,693 233,214 252,002

Source: Sierra Metals, 2020

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page xiv

A sensitivity analysis of the Post Tax NPV vs Tonnes Per Day throughput is shown in Figure 1-1.

Source: Sierra Metals, 2020

Note: 5,000 tpd (base case), 7,000 tpd, 10,000 tpd (2024), 12,000 tpd (2024), 15,000 tpd are shown

Figure 1-1: Sensitivity Analysis - NPV vs TPD

Table 1-10: Incremental Post Tax NPV and Post Tax IRR

Production Rates Post Tax NPV US$ Post Tax IRR %
7ktpd - 5ktpd 31,044,119 29.21%
10ktpd (2024) - 5ktpd 57,354,818 27.87%
10ktpd (2024) - 7ktpd 26,310,699 26.83%
12ktpd (2024) - 5ktpd 58,888,188 26.63%
12ktpd (2024) - 7ktpd 27,844,069 25.20%
12ktpd (2024) - 10ktpd (2024) 1,533,370 5.75%
15ktpd - 5ktpd 62,914,037 24.84%
15ktpd - 7ktpd 31,869,917 23.03%
15ktpd - 10ktpd (2024) 5,559,219 18.31%
15ktpd - 12ktpd (2024) 4,025,848 16.84%

Source: Sierra Metals, 2020

As seen in Table 1-10, the incremental benefit generated by increasing the production rate from 5,000 tpd to 10,000 tpd is very significant with an incremental post tax NPV of US$ 57.4 M and an incremental post tax IRR of 28%. However, the incremental benefit generated by increasing the production rate to 12,000 tpd or 15,000 tpd is far less significant and given that trebling the production rate can potentially present significant operational challenges, Sierra Metals has therefore selected the 10,000 tpd (2024) production rate as the preferred option.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page xv

The 10,000 tpd (2024) proposed mine plan requires a capital requirement (initial and sustaining) of US$ 317 M over the life of mine; efficiencies associated with higher throughputs are expected to drive a reduction in operating costs on a per tonne basis. This PEA indicates a post tax NPV (8%) at 10,000 tpd (in 2024) of US$ 283 M. Total operating cost for the life of mine is US$ 827 M, equating to a total operating cost of US$ 19.77 per tonne milled and US$ 1.16 per pound copper equivalent.

The proposed mine plan is conceptual in nature and would benefit from further, more definitive, investigation. The Piedras Verdes processing plant can be adapted to process 10,000 tpd and would require:

· Temporary shutdown to overhaul equipment.
· Purchase of mobile jaw and cone crushers.
· Overhaul and reintroduction of idle equipment.

The availability of tailings storage capacity is a risk to the proposed mine plan, but it is noted that there is ample underground storage that could be utilized for the storage of tailings and the financial analysis has allowed for capital and operating costs for the operation of a tailings backfill plant.

1.13 Magnetite Recovery Project

The magnetite recovery project was evaluated as an incremental addition to the Bolivar mine project. In this section, an economic evaluation of the magnetite recovery project is provided and is based on the 10,000 tonnes/day (10,000 tpd in 2024) case.

The commodity price forecast is shown in Table 1-11. The modified Fe price forecast values used in the financial model are provided in Section 19 in Table 19-2.

Table 1-11: Commodity Price Forecast by Year

Metal Unit 2020 2021 2022 2023 Long Term (LT)
Au $/oz 1,755 1,907 1,782 1,737 1,541
Ag $/oz 19.83 24.12 22.22 22.47 20.0
Cu $/lb 2.65 2.86 2.89 2.93 3.05
Pb $/lb 0.82 0.87 0.89 0.90 0.91
Zn $/lb 0.94 0.99 1.04 1.04 1.07
Fe $/tonne N/A 153.00 125.00 100.00 80.00

Source: CIBC, Sierra Metals, 2021 (except Fe, Jeffries, June 2021)

The economic analysis of the Bolivar mine, including the incremental addition of the magnetite recovery project, indicates an after tax NPV of US$361 million (using a discount rate of 8%) at 10,000 tonnes/day (10,000 tpd in 2024). Total operating cost for the life of mine is US$1,117 million, equating to a total operating cost of US$26.73 per tonne milled and US$1.56 per pound copper equivalent not including the revenue from magnetite, and US$1.32 per pound copper equivalent including the magnetite revenue. Highlights of the economic analysis are provided in Table 1-12.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page xvi

Table 1-12: Economic analysis of project including magnetite recovery project

Measure Unit Value
Net Present Value (After Tax 8% Discount Rate) US$ M 361
LOM Mill Feed (ROM ore) Tonnes (Mt) 41.8
LOM Mill Feed (tailings) Tonnes (Mt) 6.0
Mining Production Rate t/year 3,600,000
LOM Project Operating Period Years 14
Total Life of Mine (LoM) Capital Costs US$ M 345
Total Life of Mine (LoM) Operating Costs US$ M 1,117
Net After - Tax Cashflow US$ M 650
EBITDA US$ M 1,299
Total Operating Unit Costs US$/t 26.73
LOM Copper Production (Payable) Mt 0.25
LOM Gold Production (Payable) Moz 0.15
LOM Silver Production (Payable) Moz 12.9
LOM Iron Concentrate Production, 62% Fe (Payable) Mt 5.7

Source: Sierra Metals, 2021

The magnetite recovery project is also expected to provide additional benefits that have not been accounted for in the PEA report's economic evaluation:

1. Reduction of overall tailings management costs (less tailings to be handled and stored, reduced tailings storage development capital).
2. Reduction in future closure costs.
1.14 Conclusions and Recommendations
1.14.1 Geology and Mineral Resources

SRK is of the opinion that the MRE has been conducted in a manner consistent with industry standards and that the data and information supporting the stated Mineral Resources are sufficient for declaration of Indicated and Inferred classifications of resources. SRK has not classified any of the resources in the Measured category due to some uncertainties regarding the data supporting the MRE.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page xvii

General deficiencies related to the Geology and Mineral Resources of Bolivar include:

· No QA/QC program was conducted prior to 2016. This has been addressed by a limited resampling campaign of historical drill core and a more recent QA/QC program that was implemented in 2016. Continuation of the current QA/QC program will be required in order to achieve Measured Resources which generally are supported by high resolution drilling and sampling data that feature consistently implemented and monitored QA/QC.
· There is limited to no downhole deviation survey data for the historic drilling. The survey data obtained to date show significant deviations from planned orientations as well as local downhole deviations that influence the exact position of mineralized intervals.
· There is currently insufficient density sampling and analysis to adequately define this characteristic for the different lithological units and mineralization types in the various areas of the project. Correlation of density to mineralization characteristics is important for this type of deposit and therefore additional density sampling and analysis will be required for all future drilling.
· There is inadequate detailed structural geology data collection from drill core to support interpretation of local mineralization controls and geotechnical characteristics.
· A significant portion of the current sample database is missing gold analysis and therefore the current Mineral Resources may not accurately reflect the true value of Bolivar mineralization locally.
· Bolivar currently does not have an adequate production reconciliation system to allow for robust comparison of mill production to mine forecasts.

SRK recommends the following action items for Bolivar:

· Complete downhole surveys for all future exploration and delineation drill holes using a non-magnetic downhole survey instrument.
· Continue to improve upon the current sample assay QA/QC program and monitor progress of the program over time to identify trends in the preparation and analytical phases of sample analysis.
· Complement the QA/QC protocol using additional controls including coarse blanks, twin samples, fine and coarse duplicates, and a second lab control using a certified laboratory to control the different phases of the preparation and chemical analysis process.
· Document the failures in the quality control protocol and the correction measurements taken.
· Implement a consistent density testing program including the representative selection of drill core from the different lithological units and mineralization types for the various areas of Bolivar and La Sidra. Multiple density samples should be collected from every drill hole so that local density fluctuations can be assessed.
· Density samples should be submitted for geochemical analysis to allow for correlation of density to mineralization type and extent.
CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page xviii
· Density check samples (approximately 5 to 10% of total) should be submitted to a third-party independent laboratory such as ALS Minerals for testing using ASTM standards as part of the QA/QC program. These samples should also be analyzed using the current methods employed by Sierra and reviewed to ensure that the mine site analytical performance is reasonable.
· Drill core samples previously not analyzed for gold content should be re-analyzed for gold content. Current Mineral Resources may not reflect the true value of the mineralization and metal content due to missing gold analysis. All future drill core samples should be summitted for the full suite of geochemical analyses.
· Delineation and infill drilling are recommended in areas of Inferred Mineral Resources to facilitate upgrading to higher confidence resource categories (i.e. Indicated or Measured Mineral Resource) to support life of mine planning activities. A drill hole spacing study should be completed to provide guidance on drill hole density requirements.
· Detailed structural geology data collection (i.e. oriented drill core) should be implemented for all future drill holes to allow for more detailed analysis of mineralization controls and geotechnical assessments to support mine design.
· Continue to develop a site wide litho-structural model to support exploration, Mineral Resource delineation and mine design activities.
· Implement a production reconciliation system to allow for proper reconciliation of mill production to mine forecasts. This should include the development of a dynamic grade control model to support short- and long-term mine planning activities.
· Undertake a backfill study to determine the suitability of using tailings as backfill in stopes.
1.14.2 Recovery Methods

There is a high level of month-to-month variability for both tonnes and head grade input to processing. Better integration between geology, mine planning and processing can significantly reduce this variability. Additional work is also needed in the processing facilities to stabilize the operation. Improvements include the implementation of a preventive maintenance program and training programs to improve operators' skill, with the ultimate objective of improving metal recovery and lowering operating cost, while maintaining or improving concentrate quality.

Regarding the recovery of magnetite from both newly produced tailings from the run-of-mine ore and from the old (legacy) tailings, a 70% recovery figure is deemed to be reasonable based on the preliminary testwork done to date. The following conclusions are made regarding the recovery of magnetite:

· It is necessary to evaluate the installation of regrinding mill ahead of the magnetic concentration stage. The regrind mill would likely improve liberation of the iron, as well as impurities, therefore allowing the multi-stage magnetic separation to produce a commercial quality iron concentrates in terms of iron grade and impurities content.
CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page xix
· Additional testwork is necessary to narrow down the target regrind P80. The available data suggests that achieving a grind size of 100% less than 100 micrometres should achieve the desired iron recovery and impurities content.
· The magnetic concentration plant needs a multi-stage circuit with a minimum of three stages: a rougher stage followed by two cleaning stages, with tails from the cleaning stages being recirculated back to the rougher stage.
· Bolivar needs to execute further magnetic separation tests on head grade variability for old tailings and "new" tailings from the future processing of ore. All these tests need to be carried out under a standard flowsheet as described previously.
1.14.3 Tailings Management

As part of the overall tailings management plan, Bolivar is moving to filtered tailings (also known as dry-stack tailings). Expansion in the immediate area of the currently operating facility will occur as the site was first moved to thickened tailings in mid-2017 and will move to filtered tailings in mid-2020. An analysis of utilizing tailings as backfill in the mine should be carried out, and a trade-off study should be completed to determine if the size of the New TSF can be reduced.

Based on the 2016 geochemical characterization data, a more robust and comprehensive closure program for the tailings should be undertaken with an emphasis on closure of the existing facilities in such a manner as to not pose a risk to local groundwater resources.

1.14.4 Environmental, Permitting, and Social

It does not appear that there are currently any known environmental issues that could materially impact the extraction and beneficiation of Mineral Resources at Bolivar Mine.

Ongoing management of dust on surface roadways between the mine and the plant location should be actively performed to protect Sierra Metals's social license and avoid regulatory compliance violations.

More recent geochemical characterization data suggest that some of the material from the underground mine may be potentially acid generating. Additional investigation of the current materials being deposited into the tailings impoundment may be warranted; however, given the dryness of the Chihuahuan Desert, this may not necessarily be a material issue for the project.

The required permits for continued operation at the Bolivar Mine, including exploration of the site, have been obtained based on information provided by Sierra Metals. Currently, SRK is not aware of any outstanding permits or any non-compliance at the project or nearby exploration sites.

SRK's scope of work did not include an assessment of the veracity of the closure cost estimate completed in 2017 by Treviño Asociados Consultores, but, based on projects of similar nature and size within Mexico, the estimate appears low in comparison.

SRK has the following recommendations regarding environment, permitting, and social or community impact at Bolivar:

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page xx
· The issue of surface road fugitive dust emissions should be addressed as soon as possible to avoid jeopardizing the mine's social license and incurring compliance violation from the regulatory authorities.
· SRK recommends that Sierra Metals contract an independent, outside review of the closure cost estimate, with an emphasis on benchmarking against other projects in northern Mexico. This may require a site investigation and the preparation of a more comprehensive and detailed closure and reclamation plan before a closure specialist evaluates the overall closure approach and costs.

In 2017, FLOPAC Ingenieria signed a contract to conduct geophysics, geotechnical and hydrological studies. Based on the results of these studies, a new tailings dam was designed.

CK/JJ September 2021
SRK Consulting
2US043.005 Sierra Metals Inc.
Bolivar_Technical_Report_PEA_Update Page xxi

Table of Contents

1 Executive Summary ii
1.1 Property Description and Ownership ii
1.2 Geology and Mineralization iv
1.3 Status of Exploration, Development and Operations iv
1.4 Mineral Processing and Metallurgical Testing iv
1.5 Mineral Resource Estimate iv
1.6 Mineral Reserve Estimate v
1.7 Mining Methods vi
1.8 Recovery Methods vi
1.9 Project Infrastructure vii
1.10 Environmental Studies and Permitting vii
1.11 Capital and Operating Costs viii
1.12 Economic Analysis x
1.13 Magnetite Recovery Project xv
1.14 Conclusions and Recommendations xvi
1.14.1 Geology and Mineral Resources xvi
1.14.2 Recovery Methods xvii
1.14.3 Tailings Management xix
1.14.4 Environmental, Permitting, and Social xix
2 Introduction 1
2.1 Qualifications of Consultants (SRK) 2
2.2 Qualifications of Consultants (Sierra Metals) 2
2.3 Details of Inspection 3
2.4 Sources of Information 3
2.5 Effective Date 3
2.6 Units of Measure 3
3 Reliance on Other Experts 3
4 Property Description and Location 4
4.1 Property Location 4
4.2 Mineral Titles 5
4.2.1 Nature and Extent of Issuer's Interest 7
4.3 Royalties, Agreements and Encumbrances 8
4.3.1 Purchase Agreements 8
4.3.2 Legal Contingencies 8
CK/JJ September 2021
SRK Consulting
2US043.005 Sierra Metals Inc.
Bolivar_Technical_Report_PEA_Update Page xxii
4.4 Environmental Liabilities and Permitting 9
4.4.1 Environmental Liabilities 9
4.4.2 Required Permits and Status 9
4.5 Other Significant Factors and Risks 9
5 Accessibility, Climate, Local Resources, Infrastructure and Physiography 9
5.1 Topography, Elevation and Vegetation 9
5.2 Accessibility and Transportation to the Property 9
5.3 Climate and Length of Operating Season 9
5.4 Infrastructure Availability and Sources 10
5.4.1 Power 10
5.4.2 Water 10
5.4.3 Mining Personnel 10
5.4.4 Potential Tailings Storage Areas 10
5.4.5 Potential Waste Rock Disposal Areas 10
5.4.6 Potential Processing Plant Sites 10
6 History 11
6.1 Exploration and Development Results of Previous Owners 11
6.2 Historic Mineral Resource and Reserve Estimates 11
6.3 Historic Production 12
7 Geological Setting and Mineralization 14
7.1 Regional Geology 14
7.2 Local Geology 15
7.3 Property Geology 16
7.3.1 Skarn-hosting Sedimentary Rocks 16
7.3.2 Intrusive Rocks 16
7.4 Significant Mineralized Zones 19
8 Deposit Types 20
8.1 Mineral Deposit 20
8.2 Geological Model 20
9 Exploration 21
9.1 Relevant Exploration Work 21
9.2 Sampling Methods and Sample Quality 22
9.3 Significant Results and Interpretation 22
10 Drilling 23
10.1 Type and Extent 23
10.2 Procedures 24
10.3 Interpretation and Relevant Results 25
CK/JJ September 2021
SRK Consulting
2US043.005 Sierra Metals Inc.
Bolivar_Technical_Report_PEA_Update Page xxiii
11 Sample Preparation, Analyses, and Security 26
11.1 Security Measures 26
11.2 Sample Preparation for Analysis 26
11.3 Sample Analysis 26
11.4 Quality Assurance/Quality Control Procedures 27
11.4.1 Certified Reference Materials 27
11.4.2 Blanks 32
11.4.3 Duplicates 32
11.4.4 Results 34
11.4.5 Actions 34
11.5 Opinion on Adequacy 35
12 Data Verification 36
12.1 Procedures 36
12.2 Limitations 36
12.3 Opinion on Data Adequacy 36
13 Mineral Processing and Metallurgical Testing 37
13.1 Testing and Procedures 39
13.2 Recovery Estimate Assumptions 40
13.3 Analysis of Magnetite Testing 42
14 Mineral Resource Estimates 50
14.1 Drill hole and Channel Sample Database 50
14.1.1 Drilling Database 50
14.1.2 Downhole Deviation 51
14.1.3 Missing and Unsampled Intervals 52
14.2 Geological Model 52
14.2.1 Bolivar Area Mineralization 53
14.3 Assay Sample Summary 56
14.3.1 Assay Sample Length 56
14.3.2 Assay Grade Summary 56
14.3.3 Compositing 59
14.3.4 Outlier Analysis and Grade Capping 62
14.4 Density 66
14.5 Variography 68
14.6 Block Model Configuration 70
14.7 Estimation Parameters 71
14.8 Model Validation 73
14.9 Mineral Resource Classification 78
CK/JJ September 2021
SRK Consulting
2US043.005 Sierra Metals Inc.
Bolivar_Technical_Report_PEA_Update Page xxiv
14.10 Depletion for Mining 78
14.11 Mineral Resource Statement 80
14.12 Mineral Resource Sensitivity 80
14.13 Previous Resource Estimates 81
14.14 Relevant Factors 82
15 Mineral Reserve Estimates 83
16 Mining Methods 84
16.1 Introduction 84
16.2 Current Mining Methods 85
16.2.1 Sub-Level Stoping - Bolivar West 88
16.2.2 Sub-Level Stoping - El Gallo Inferior 88
16.2.3 Drilling, Blasting, Loading and Hauling 89
16.2.4 Mineralized Material and Waste Handling 92
16.3 Geomechanical Parameters 93
16.3.1 Stability Design Criteria 93
16.3.2 Excavation Design for El Gallo Inferior 98
16.3.3 Geomechanical Characterization of Bolivar West 104
16.3.4 Excavation Design for Bolivar West 107
16.3.5 Pillar Recovery Potential and Mining Method Alternatives 112
16.3.6 Hydrological 115
16.4 Proposed Mine Plan 115
16.4.1 Proposed Mine Plan 115
16.4.2 Dilution and Recovery Factor 117
16.5 Mineable Inventory 125
16.6 Mine Design 123
16.7 Mine Production Schedule (Base Case) 125
16.8 Waste Storage 133
16.9 Major Mining Equipment 133
16.10 Ventilation 136
17 Recovery Methods 146
17.1 Process Description 146
17.1.1 Crushing Stage 146
17.1.2 Grinding Circuit 147
17.1.3 Flotation Circuit 147
17.1.4 Thickening and Filtration 147
17.1.5 Magnetite Concentration Circuit (Projected) 148
17.1.6 Tails Storage Facility 148
CK/JJ September 2021
SRK Consulting
2US043.005 Sierra Metals Inc.
Bolivar_Technical_Report_PEA_Update Page xxv
17.2 Piedras Verdes Concentrator Performance 148
17.2.1 Operational Performance 148
17.2.2 Process Plant, Operating Costs and Consumables 153
17.3 Plant Design and Equipment Characteristics 154
17.4 Conclusion and Recommendations 156
18 Project Infrastructure 158
18.1 Access and Local Communities 159
18.2 Service Roads 161
18.3 Mine Operations and Support Facilities 162
18.4 New Ore Delivery Tunnel 162
18.5 Process Support Facilities 164
18.6 Energy 166
18.6.1 Propane 166
18.6.2 Power Supply and Distribution 166
18.6.3 Fuel Storage 167
18.7 Water Supply 167
18.7.1 Potable Water 167
18.7.2 Process Water 168
18.8 Site Communications 169
18.9 Site Security 169
18.10 Logistics 170
18.11 Waste Handling and Management 170
18.11.1 Waste Management 170
18.11.2 Waste Rock Storage 171
18.12 Tailings Management 171
18.12.1 Existing Tailings Storage Facility 171
18.12.2 Tailings Facility Expansion 173
18.13 Reprocessing of Old Tailings to Recover Magnetite 177
18.14 Back-fill Plant 178
19 Market Studies and Contracts 180
20 Environmental Studies, Permitting, and Social or Community Impact 181
20.1 Environmental Studies and Liabilities 181
20.2 Environmental Management 181
20.2.1 Tailings Disposal 181
20.3 Geochemistry 182
20.3.1 Emission and Waste Management 182
20.4 Mexican Environmental Regulatory Framework 183
CK/JJ September 2021
SRK Consulting
2US043.005 Sierra Metals Inc.
Bolivar_Technical_Report_PEA_Update Page xxvi
20.4.1 Mining Law and Regulations 183
20.4.2 General Environmental Laws and Regulations 183
20.4.3 Other Laws and Regulations 186
20.4.4 Expropriations 188
20.4.5 NAFTA 188
20.4.6 International Policy and Guidelines 188
20.4.7 The Permitting Process 188
20.4.8 Required Permits and Status 190
20.4.9 MIA and CUS Authorizations 191
20.5 Social Management Planning and Community Relations 192
20.6 Closure and Reclamation Plan 192
21 Capital and Operating Costs 194
21.1 Capital Cost (Capex) 194
21.2 Operating cost (Opex) 194
21.3 Incremental Opex and Capex of the Magnetite Recovery Project 201
22 Economic Analysis 203
22.1 Economic Analysis without the magnetite recovery project 203
22.2 Magnetite Recovery Project 222
22.3 Risk Assessment 223
23 Adjacent Properties 226
24 Other Relevant Data and Information 227
25 Interpretation and Conclusions 228
25.1 Geology and Mineral Resources 228
25.2 Mineral Reserve Estimate 228
25.3 Metallurgy and Processing 228
25.4 Environmental, Permitting and Social 229
25.5 Economic Analysis 230
25.5.1 Economic Analysis (Not Including the Magnetite Recovery Project) 230
25.5.2 Economic Analysis (Including the Magnetite Recovery Project) 231
26 Recommendations 233
26.1 Recommended Work Programs and Costs 233
26.1.1 Geology and Mineral Resources 233
26.1.2 Mining and Geotechnical 234
26.1.3 Tailings Management 234
26.1.4 Environmental, Permitting and Social or Community Impact 234
26.1.5 Costs 235
CK/JJ September 2021
SRK Consulting
2US043.005 Sierra Metals Inc.
Bolivar_Technical_Report_PEA_Update Page xxvii
27 References 236
28 Glossary 238
28.1 Mineral Resources 238
28.2 Mineral Reserves 238
28.3 Abbreviations 240
CK/JJ September 2021
SRK Consulting
2US043.005 Sierra Metals Inc.
Bolivar_Technical_Report_PEA_Update Page xxviii

List of Tables

Table 1-1: Consolidated Bolivar Mine Mineral Resource Statement as of December 31, 2019 - SRK Consulting (Canada), Inc. (1)(2)(3)(4)(5) v
Table 1-2: Capital Cost Summary (not including magnetite recovery project) viii
Table 1-3: Capital Cost Summary (including magnetite recovery project) ix
Table 1-4: Operating Cost Summary (not including magnetite recovery project) ix
Table 1-5: Operating Cost Summary (including magnetite recovery project) ix
Table 1-6: Commodity Price Forecast by Year x
Table 1-7: NSR Factors xi
Table 1-8: Economic Factors xii
Table 1-9: Summary Economic Evaluation xiii
Table 1-10: Incremental Post Tax NPV and Post Tax IRR xiv
Table 1-11: Commodity Price Forecast by Year xv
Table 1-12: Economic analysis of project including magnetite recovery project xvi
Table 2-1: Site Visit Participants 3
Table 4-1: Concessions for the Bolivar Mine 5
Table 6-1: Ownership History and Acquisition Dates for Claims at the Bolivar Property 11
Table 6-2: 2011 to 2019 Bolivar Production 13
Table 10-1: Summary of Drilling by Sierra Metals on the Bolivar Property, 2003 to 2019 23
Table 11-1: 2015 to 2017 CRM Expected Means and Tolerances 28
Table 11-2: 2018-2019 CRM Expected Means and Tolerances 28
Table 13-1: Metallurgical Data Set 44
Table 14-1: Bolivar Drilling History 50
Table 14-2: Drilling Types 51
Table 14-3: Sample Assay Descriptive Statistics - All Drilling (length weighted) 51
Table 14-4: Drill Hole Downhole Survey Details 52
Table 14-5: Bolivar Mineralization Domains and Codes 54
Table 14-6: Summary Assay Statistics for Cu (%) 57
Table 14-7: Summary Assay Statistics for Ag (g/t) 58
Table 14-8: Summary Assay Statistics for Au (g/t) 59
Table 14-9: Composited Assay Summary Statistics for Cu (%) 60
Table 14-10: Composited Assay Summary Statistics for Ag (g/t) 61
CK/JJ September 2021
SRK Consulting
2US043.005 Sierra Metals Inc.
Bolivar_Technical_Report_PEA_Update Page xxix
Table 14-11: Composited Assay Summary Statistics for Au (g/t) 62
Table 14-12: Capped Composite Summary Statistics for Cu (%) 63
Table 14-13: Capped Composite Summary Statistics for Ag (g/t) 64
Table 14-14: Capped Composite Summary Statistics for Au (g/t) 65
Table 14-15: Assigned Average Density Values for Mineralized Domains 67
Table 14-16: Variogram Parameters for Copper 69
Table 14-17: Variogram Parameters for Silver 69
Table 14-18: Variogram Parameters for Gold 69
Table 14-19: Block Model Configuration Parameters 70
Table 14-20: Search Ellipse Orientation Parameters 72
Table 14-21: Summary of Estimation Parameters 72
Table 14-22: Consolidated Bolivar Mine Mineral Resource Statement as of December 31, 2019(1)(2)(3)(4)(5) 80
Table 14-23: Consolidated Bolivar Mine Mineral Resource Statement as of October 31, 2017-SRK Consulting (U.S.), Inc. 81
Table 16-1: Rock Mass Characteristics of El Gallo Inferior, Chimenea 1 and Chimenea 2 and Bolivar West 87
Table 16-2: Determination of Stope Stability - El Gallo Inferior 99
Table 16-3: Factor B and Factor C - El Gallo Inferior 99
Table 16-4: Estimation of Induced Stresses (Part 1) - El Gallo Inferior 100
Table 16-5: Estimation of Induced Stresses (Part 2) - El Gallo Inferior 100
Table 16-6: Stability Number - El Gallo Inferior 101
Table 16-7: Geomechanical Calculation Results 103
Table 16-8: Determination of Stope Stability - Bolivar West 118
Table 16-9: Factor B and Factor C - Bolivar West 118
Table 16-10: Estimation of Induced Stresses (Part 1) - Bolivar West 118
Table 16-11: Estimation of Induced Stresses (Part 2) - Bolivar West 119
Table 16-12: Stability Number - Bolivar West 119
Table 16-13: Geomechanical Calculation Results 111
Table 16-14: Unit Value Metal Price Assumptions 119
Table 16-15: Metallurgical Recoveries 119
Table 16-16: NSR Calculation Parameters 120
CK/JJ September 2021
SRK Consulting
2US043.005 Sierra Metals Inc.
Bolivar_Technical_Report_PEA_Update Page xxx
Table 16-17: NSR Calculation Parameters - Site Operating Costs Per Tonne 121
Table 16-18: Parameters for Sub-Level Stoping Mining Method 121
Table 16-19: Resource Report 122
Table 16-20: Mineable Inventory 123
Table 16-21: Bolivar Mine - Development Meters in the LOM Plan 124
Table 16-22: LOM Production Rates 125
Table 16-23: LOM Production Schedule for 5,000 Tonnes/Day 126
Table 16-24: LOM Development Schedule for 5,000 Tonnes/Day 126
Table 16-25: LOM Production Schedule for 7,000 Tonnes/Day (7,000 tpd in 2024) 127
Table 16-26: LOM Development Schedule for 7,000 Tonnes/Day (7,000 tpd in 2024) 127
Table 16-27: LOM Production Schedule for 10,000 Tonnes/Day (10,000 tpd in 2024) 128
Table 16-28: LOM Development Schedule for 10,000 Tonnes/Day (10,000 tpd in 2024) 128
Table 16-29: LOM Production Schedule for 10,000 Tonnes/Day (10,000 tpd in 2026) 129
Table 16-30: LOM Development Schedule for 10,000 Tonnes/Day (10,000 tpd in 2026) 129
Table 16-31: LOM Production Schedule for 12,000 Tonnes/Day (12,000 tpd in 2024) 130
Table 16-32: LOM Development Schedule for 12,000 Tonnes/Day (12,000 tpd in 2024) 130
Table 16-33: LOM Production Schedule for 12,000 Tonnes/Day (12,000 tpd in 2026) 131
Table 16-34: LOM Development Schedule for 12,000 Tonnes/Day (12,000 tpd in 2026) 131
Table 16-35: LOM Production Schedule for 15,000 Tonnes/Day (15,000 tpd in 2024) 132
Table 16-36: LOM Development Schedule for 15,000 Tonnes/Day (15,000 tpd in 2024) 132
Table 16-37: Current List of Major Underground Mining Equipment at Bolivar 133
Table 16-38: Main Planned Underground Mining Equipment (5,000 tpd) 134
Table 16-39: Main Planned Underground Mining Equipment (7,000 tpd - 2024) 134
Table 16-40: Main Planned Underground Mining Equipment (10,000 tpd - 2024) 134
Table 16-41: Main Planned Underground Mining Equipment (10,000 tpd - 2026) 134
Table 16-42: Main Planned Underground Mining Equipment (12,000 tpd - 2024) 135
Table 16-43: Main Planned Underground Mining Equipment (12,000 tpd - 2026) 135
Table 16-44: Main Planned Underground Mining Equipment (15,000 tpd - 2024) 135
Table 16-45: Auxiliary Mining Equipment 136
Table 16-46: Ventilation Requirements for Equipment and Personnel (5,000 tpd) 137
Table 16-47: Ventilation Requirements by Year (5,000 tpd) 138
Table 16-48: Ventilation Requirements by Year (7,000 tpd - 2024) 139
CK/JJ September 2021
SRK Consulting
2US043.005 Sierra Metals Inc.
Bolivar_Technical_Report_PEA_Update Page xxxi
Table 16-49: Ventilation Requirements by Year (10,000 tpd - 2024) 140
Table 16-50: Ventilation Requirements by Year (10,000 tpd - 2026) 141
Table 16-51: Ventilation Requirements by Year (12,000 tpd - 2024) 142
Table 16-52: Ventilation Requirements by Year (12,000 tpd - 2026) 143
Table 16-53: Ventilation Requirements by Year (15,000 tpd - 2024) 144
Table 17-1: Piedras Verdes Performance - 18-month Period July 2018 to December 2019 149
Table 17-2: Piedras Verdes' Performance Comparison - Q4 2018 and Q4 2019 150
Table 17-3: Piedras Verdes Mill's Major Process Equipment 155
Table 17-4: Piedras Verdes Mill's Magnetic Separation Equipment 156
Table 18-1: Tunnel Dimensions and Lengths 163
Table 18-2: Propane Tank Location and Capacities 166
Table 18-3: Fuel Tank Storage and Capacity Summary 167
Table 18-4: Site Water Use (January to December 2018) 169
Table 18-5: Site Water Use (January to December 2019) 169
Table 19-1: Forecast Metal Prices for Au, Ag and Cu 180
Table 19-2: Forecast Metal Prices for Fe 180
Table 20-1: Permit and Authorization Requirements for the Bolivar Mine 190
Table 20-2: Bolivar Project Concessions 191
Table 20-3: Bolivar Mine - Estimated Cost of Reclamation and Closure of the Mine 192
Table 21-1: Opex Estimate at 5,000 Tonnes/Day (US$) 195
Table 21-2: Capex Estimate at 5,000 Tonnes/Day (US$) 195
Table 21-3: Opex Estimate at 7,000 Tonnes/Day (US$) (7,000 tpd in 2024) 196
Table 21-4: Capex Estimate at 7,000 Tonnes/Day (US$) (7,000 tpd in 2024) 196
Table 21-5: Opex Estimate at 10,000 Tonnes/Day (US$) (10,000 tpd in 2024) 197
Table 21-6: Capex Estimate at 10,000 Tonnes/Day (US$) (10,000 tpd in 2024) 197
Table 21-7: Opex Estimate at 10,000 Tonnes/Day (US$) (10,000 tpd in 2026) 198
Table 21-8: Capex Estimate at 10,000 Tonnes/Day (US$) (10,000 tpd in 2026) 198
Table 21-9: Opex Estimate at 12,000 Tonnes/Day (US$) (12,000 tpd in 2024) 199
Table 21-10: Capex Estimate at 12,000 Tonnes/Day (US$) (12,000 tpd in 2024) 199
Table 21-11: Opex Estimate at 12,000 Tonnes/Day (US$) (12,000 tpd in 2026) 200
Table 21-12: Capex Estimate at 12,000 Tonnes/Day (US$) (12,000 tpd in 2026) 200
CK/JJ September 2021
SRK Consulting
2US043.005 Sierra Metals Inc.
Bolivar_Technical_Report_PEA_Update Page xxxii
Table 21-13: Opex Estimation 10,000 Tonnes/Day (US$) (2024) including the Magnetite Recovery Project 202
Table 21-14: Opex Estimation Detail for the Magnetite Recovery Project 202
Table 21-15: Capex Estimation 10,000 Tonnes/Day (US$) (2024) including the Magnetite Recovery Project 202
Table 21-16: Capex Estimation Detail for the Magnetite Recovery Project 202
Table 22-1: Commodity Price Forecast by Year 203
Table 22-2: NSR Factors 204
Table 22-3: Economic Factors 205
Table 22-4: Summary Economic Evaluation 206
Table 22-5: Incremental Post Tax NPV and IRR 207
Table 22-6: Sensitivity Analysis NPV - 5,000 Tonnes/Day (US$) 209
Table 22-7: Sensitivity Analysis NPV - 7,000 Tonnes/Day (US$) 211
Table 22-8: Sensitivity Analysis NPV - 10,000 Tonnes/Day (US$) (10,000 tpd in 2024) 213
Table 22-9: Sensitivity Analysis NPV - 10,000 Tonnes/Day (US$) (10,000 tpd in 2026) 215
Table 22-10: Sensitivity Analysis NPV - 12,000 Tonnes/Day (US$) (12,000 tpd in 2024) 217
Table 22-11: Sensitivity Analysis NPV - 12,000 Tonnes/Day (US$) (12,000 tpd in 2026) 219
Table 22-12: Sensitivity Analysis NPV - 15,000 Tonnes/Day (US$) (15,000 tpd in 2024) 221
Table 22-13: Commodity Price Forecast by Year 222
Table 22-14: Economic analysis of project including magnetite recovery project 223
Table 22-15: Bolivar Mine - Risk Assessment 224
Table 25-1: Economic analysis of project including the magnetite recovery project 232
Table 26-1: Summary of Costs for Recommended Work 235
Table 28-1: Definition of Terms 239
Table 28-2: Abbreviations 240
CK/JJ September 2021
SRK Consulting
2US043.005 Sierra Metals Inc.
Bolivar_Technical_Report_PEA_Update Page xxxiii

List of Figures

Figure 1-1: Sensitivity Analysis - NPV vs TPD xiv
Figure 4-1: Map Showing the Location of the Bolivar Property in Chihuahua, Mexico 4
Figure 4-2: Land Tenure Map showing Bolivar Concessions 6
Figure 4-3: Map of the Bolivar Property 7
Figure 7-1: Regional Geology Map showing the Locations of Various Mines in the Sierra Madre Occidental Precious Metals Belt 14
Figure 7-2: Local Geology Map Showing the Location of the Bolivar Property 15
Figure 7-3: Stratigraphic Column of the Bolivar Property 17
Figure 7-4: Geologic Map of the Bolivar Property 18
Figure 7-5: Mineralized Andradite Garnet Skarn - El Gallo Area Core Sample 19
Figure 10-1: Location Map of Drill Hole Collars (green) and Traces (grey) 24
Figure 11-1: CRM Performance for MCL-01, MCL-02 and PLSUL-03 for Cu 29
Figure 11-2: CRM Performance for SKRN-05, OXHYO-03 and STRT-01 for Cu 30
Figure 11-3: CRM Performance for MCL-03, PLSUL-08 and PLSUL-11 for Cu 31
Figure 11-4: Fine Blank Performance - Cu 32
Figure 11-5: Duplicate Sample Analysis for Cu (2018 and 2019 campaigns) 33
Figure 11-6: Duplicate Sample Analysis for Ag (2018 and 2019 campaigns) 33
Figure 11-7: Duplicate Sample Analysis for Au (2018 and 2019 campaigns) 34
Figure 13-1: The Piedras Verdes Processing Plant's Flotation Area 37
Figure 13-2: Piedras Verdes Flowsheet 38
Figure 13-3: Magnetite Testing - All Results 39
Figure 13-4: Piedras Verdes Monthly Average Performance in 2019 41
Figure 13-5: Copper Concentrate and Metal Recoveries 41
Figure 14-1: December 2019 Mineralization Model for Bolivar 53
Figure 14-2: 3D View of Piedras Verde Granodiorite Relative to Mineralization Zones 55
Figure 14-3: Assay Sample Interval Summary Statistics 56
Figure 14-4: Scatter Plots of Density (t/m3) Relative to Cu (%), Fe (%) and Combined Cu + Fe + Zn (%) Mineralization 68
Figure 14-5: 2020 Bolivar MRE Block Models 70
Figure 14-6: Swath Plot of Cu (%) Grade for the EGI Domain 74
Figure 14-7: Swath Plot of Ag (g/t) Grade for the EGI Domain 75
CK/JJ September 2021
SRK Consulting
2US043.005 Sierra Metals Inc.
Bolivar_Technical_Report_PEA_Update Page xxxiv
Figure 14-8: Comparison of Average Cu (%) Grade Between Block Model Estimate and Declustered Nearest Neighbour Model for Each Mineralized Domain (Note: Grey Bars Represent Volume of Individual Domains) 76
Figure 14-9: Comparison of Average Ag (g/t) Grade Between Block Model Estimate and Declustered Nearest Neighbour Model for Each Mineralized Domain (Note: Grey Bars Represent Volume of Individual Domains) 76
Figure 14-10: EGI Domain Cross-section Comparison of Estimated Block Cu (%) Grades Relative to Drill Hole Assay Composites 77
Figure 14-11: BNW4 Domain Cross-section Comparison of Estimated Block Cu (%) Grades Relative to Drill Hole Assay Composites 77
Figure 14-12: Areas of Mine Production as of December 31, 2019 79
Figure 14-13: Grade-Tonnage Curve for Indicated and Inferred Mineral Resources 81
Figure 16-1: Overview of Bolivar Mine Design - Plan View 84
Figure 16-2: Bolivar Overview - Plan View 85
Figure 16-3: Plan View of Bolivar Mineralized Zone Location and Mined Out Areas 86
Figure 16-4: Isometric View of El Gallo Inferior, Chimenea 1 and Chimenea 2 86
Figure 16-5: Isometric View of Bolivar W, Bolivar NW and Mined Out Areas 87
Figure 16-6: Typical Section Showing Sub-Level Stoping 88
Figure 16-7: Typical Section Showing Sub-Level Stoping 89
Figure 16-8: Typical 4 m x 4 m Development Blast Pattern 1 90
Figure 16-9: Typical 4 m x 4 m Development Blast Pattern 2 90
Figure 16-10: Blasting Design for Longholes in Bolivar West 91
Figure 16-11: Blasting Design for Longholes in El Gallo Inferior 91
Figure 16-12: Drill Jumbo Drilling a Blast Pattern in an El Gallo Inferior Production Stope 92
Figure 16-13: Stress Factor in Rock A, for Different Values of σc / σ1 94
Figure 16-14: Orientation of the Critical Joint with Respect to the Excavation Surface (Potvin, 1988) 95
Figure 16-15: Adjustment Factor B (Potvin, 1988) 95
Figure 16-16: Gravity Adjustment Factor C, for Gravity Falls and Slumps (Potvin, 1988) 96
Figure 16-17: Gravity Adjustment Factor C, for Slip Failure Modes (Potvin, 1988) 97
Figure 16-18: Stope Stability Graph for Large Excavations (Potvin, 1988) 97
Figure 16-19: El Gallo Inferior Cross-section 98
Figure 16-20: Hydraulic Radii - El Gallo Inferior 101
Figure 16-21: Maximum Spans - El Gallo Inferior 102
CK/JJ September 2021
SRK Consulting
2US043.005 Sierra Metals Inc.
Bolivar_Technical_Report_PEA_Update Page xxxv
Figure 16-22: Stability Factor of Excavations in El Gallo Inferior with Maximum Openings of 40 m (Stable, lower dilution) and 65 m (Unstable, higher dilution) 102
Figure 16-23: Column Stability 103
Figure 16-24: El Gallo Inferior - Plan Section 104
Figure 16-25: Geomechanical Zoning of Bolivar West 104
Figure 16-26: Drilling Logging - Bolivar West 105
Figure 16-27: Drilling Logging - Bolivar West 106
Figure 16-28: Geomechanical Model of Bolivar West Along the Mineralized Structure (RMR 20 - 40, poor quality) 107
Figure 16-29: Hydraulic Radii - Bolivar West 109
Figure 16-30: Stability and Failure Probabilities - Bolivar West 110
Figure 16-31: Maximum Spans - Bolivar West 110
Figure 16-32: Stability Factor of the Excavations in Bolivar West with maximum openings of 9.0 m (stable and less dilution) and vertical pillars of 7.0 x7.0 m for heights of 12 m 111
Figure 16-33: Example of Slender Pillar 112
Figure 16-34: Proposed Pillar Recovery Program Scheme 115
Figure 16-35: Typical Section Bolivar NW 116
Figure 16-36: Typical Room and Pillar Section Bolivar West (Lower Area) 116
Figure 16-37: Mine Design and Mineralized Areas 124
Figure 16-38: LOM Production - Tonnes, Cu Grade and Cu Equivalent Grade by Year 126
Figure 16-39: LOM Production - Tonnes per Year and Tonnes Per Day 126
Figure 16-40: LOM Production - Tonnes, Cu Grade and Cu Equivalent Grade by Year 127
Figure 16-41: LOM Production - Tonnes per Year and Tonnes Per Day 127
Figure 16-42: LOM Production - Tonnes, Cu Grade and Cu Equivalent Grade by Year 128
Figure 16-43: LOM Production - Tonnes per Year and Tonnes Per Day 128
Figure 16-44: LOM Production - Tonnes, Cu Grade and Cu Equivalent Grade by Year 129
Figure 16-45: LOM Production - Tonnes per Year and Tonnes Per Day 129
Figure 16-46: LOM Production - Tonnes, Cu Grade and Cu Equivalent Grade by Year 130
Figure 16-47: LOM Production - Tonnes per Year and Tonnes Per Day 130
Figure 16-48: LOM Production - Tonnes, Cu Grade and Cu Equivalent Grade by Year 131
Figure 16-49: LOM Production - Tonnes per Year and Tonnes Per Day 131
Figure 16-50: LOM Production - Tonnes, Cu Grade and Cu Equivalent Grade by Year 132
Figure 16-51: LOM Production - Tonnes per Year and Tonnes Per Day 132
CK/JJ September 2021
SRK Consulting
2US043.005 Sierra Metals Inc.
Bolivar_Technical_Report_PEA_Update Page xxxvi
Figure 16-52: Sierra Metals Ventilation Model for Existing Workings 136
Figure 16-53: Bolivar W/Bolivar NW/El Gallo Inferior Key Ventilation Development Layout 2020-2023 Mine Production 12,000 tpd 145
Figure 16-54: Bolivar W/Bolivar NW/El Gallo Inferior Key Ventilation Development Layout 2024-2032 Mine Production 12,000 tpd 145
Figure 17-1: Piedras Verdes Mill - Block Diagram 146
Figure 17-2: Piedras Verdes - Mineralized Material Throughout (Tonnes) and Copper Head Grade % 151
Figure 17-3: Piedras Verdes - Mill Feed Head Grade (Cu %, Ag g/t, Au x 10 g/t) 151
Figure 17-4: Piedras Verdes - Copper Concentrate and Metal Recoveries 152
Figure 17-5: Piedras Verdes - Copper Concentrate Operating Cost 153
Figure 17-6: Piedras Verdes - Operating Cost Breakdown Q3 2019 154
Figure 18-1: Bolivar General Facilities Location 158
Figure 18-2: Bolivar Camp - Accommodation Units 160
Figure 18-3: Bolivar Camp - Plan Layout 161
Figure 18-4: Bolivar Maintenance Shop 162
Figure 18-5: Isometric View of New Mineralized Material Delivery Tunnel 163
Figure 18-6: Aerial View of the Piedras Verdes Processing Plant 164
Figure 18-7: Inside the Piedras Verdes Processing Plant 165
Figure 18-8: Piedras Verdes Tailings Storage Facility - Looking South 165
Figure 18-9: Monthly Power Consumption 167
Figure 18-10: Piedras Verdes Water Reservoir 168
Figure 18-11: Concentrate Trucking Route 170
Figure 18-12: Active Tailings Area Location 171
Figure 18-13: TSF Operational Area 172
Figure 18-14: Active Tailings Area 173
Figure 18-15: Current TSF - Isometric View of Flopac Ingenieria Study Area 174
Figure 18-16: Isometric View of the New TSF 175
Figure 18-17: Plan View of the Current TSF and New TSF Locations 176
Figure 18-18: New TSF for tailings following magnetite recovery 177
Figure 18-19: Tailings compaction process in the new TSF 178
Figure 18-20: Tailings return pipeline to potential back-fill plant 179
Figure 20-1: Construction and Start-up Authorization for Industrial Facilities 189
CK/JJ September 2021
SRK Consulting
2US043.005 Sierra Metals Inc.
Bolivar_Technical_Report_PEA_Update Page xxxvii
Figure 22-1: Sensitivity Analysis - Post Tax NPV vs TPD 207
Figure 22-2: Sensitivity Analysis - 5,000 tpd 209
Figure 22-3: Sensitivity NPV vs Discount Rate - 5,000 tpd 210
Figure 22-4: Sensitivity Analysis - 7,000 tpd 211
Figure 22-5: Sensitivity NPV vs Discount Rate - 7,000 tpd 212
Figure 22-6: Sensitivity Analysis - 10,000 tpd in 2024 213
Figure 22-7: Sensitivity NPV vs Discount Rate - 10,000 tpd in 2024 214
Figure 22-8: Sensitivity Analysis - 10,000 tpd in 2026 215
Figure 22-9: Sensitivity NPV vs Discount Rate - 10,000 tpd in 2026 216
Figure 22-10: Sensitivity Analysis - 12,000 tpd in 2024 217
Figure 22-11: Sensitivity NPV vs Discount Rate - 12,000 tpd in 2024 218
Figure 22-12: Sensitivity Analysis - 12,000 tpd in 2026 219
Figure 22-13: Sensitivity NPV vs Discount Rate - 12,000 tpd in 2026 220
Figure 22-14: Sensitivity Analysis - 15,000 tpd in 2024 221
Figure 22-15: Sensitivity NPV vs Discount Rate - 15,000 tpd in 2024 222
CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 1
2 Introduction

This updated PEA report is not a wholly independent report as some sections have been prepared and signed off by qualified personnel (QP) from Sierra Metals, the project owner, with the term QP used here as it is defined under Canadian Securities Administrator's National 43-101 (43-101) guidelines. The QPs responsible for this report are listed in Sections 2.1 and 2.2

This updated report is based on a Preliminary Economic Assessment (PEA) that was previously filed on the Bolivar Mine with a report date of October 19, 2020. This updated PEA report is largely unchanged from the original PEA report except to include language with regards to the potential recovery and sale of magnetite. More specifically, changes were made to relevant portions of Sections 1, 25 and 26 summarized therefrom changes to Section 2 - Introduction, and where relevant, updates regarding the recovery and sale of magnetite were made to the following sections: Section 13 - Mineral Processing and Metallurgical Testing, Section 17 - Recovery Methods, Section 18 - Infrastructure, Section 21 - Capital and Operating Costs, and Section 22 - Economic Analysis.

This report is based on indicated and inferred resources reported on May 8, 2020 by SRK and effective as of December 31, 2019. The mine plan presented in this PEA considers the resource depleted to December 31, 2019.

Sierra Metals has engaged various specialist groups to evaluate how, on a conceptual level, mining, mineral processing, and tailings management could be adapted at the Bolivar mine and Piedras Verdes processing plant (combined to form the Property) to achieve a sustainable and staged increase in mine production and mill throughput. The original PEA report provided an indication of the economic viability of operating the Property at increased rates, from 5000 tpd to 12,000 tpd.

The reader is reminded that PEA reports are indicative and not definitive, and that the resources used in the proposed mine plan include Inferred Resources that are too speculative to be used in an economic analysis except as allowed for by Canadian Securities Administrator's National 43-101 (43-101) in PEA studies.

Mineral Resources that are not mineral reserves do not have demonstrated economic viability. There is no certainty that Inferred Resources can be converted to Indicated or Measured Resources or Mineral Reserves, and as such, there is no certainty that the results of this PEA will be realised.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 2
2.1 Qualifications of Consultants (SRK)

The Consultants preparing this technical report are specialists in the fields of geology, exploration, Mineral Resource estimation and classification, underground mining, geotechnical, environmental, permitting, metallurgical testing, mineral processing, processing design, capital and operating cost estimation, and mineral economics.

None of the SRK consultants and associates employed in the preparation of this report has any beneficial interest in Sierra Metals or its subsidiaries. The Consultants are not insiders, associates, or affiliates of Sierra Metals or its subsidiaries. The results of this Technical Report are not dependent upon any prior agreements concerning the conclusions to be reached, nor are there any undisclosed understandings concerning any future business dealings between Sierra Metals and the Consultants. The Consultants are being paid a fee for their work in accordance with normal professional consulting practice.

The following individuals, by virtue of their education, experience and professional association, are considered Qualified Persons (QP) as defined in the NI 43-101 standard, for this report, and are members in good standing of appropriate professional institutions. QP certificates of authors are provided in Appendix A. The QPs are responsible for specific sections as follows:

· Cliff Revering, P. Eng., SRK Principal Consultant (Resource Geology), is the QP responsible for Sections 7 through 12, Section 14, and portions of Sections 1, 25 and 26 summarized therefrom, of this Technical Report.
· Carl Kottmeier, B.A.Sc., P. Eng., MBA, SRK Principal Consultant (Mining), is the QP responsible for Sections 2 through 6, 27, 28 and portions of Sections 1, 25 and 26 summarized therefrom, of this Technical Report.
· Daniel H. Sepulveda, BSc, SRK Associate Consultant (Metallurgy), is the QP responsible for mineral processing, metallurgical testing and recovery methods Sections 13, 17, and portions of Sections 1, 25 and 26 summarized therefrom, of this Technical Report.
· Jarek Jakubec, C. Eng. FIMMM, SRK Practice Leader/Principal Consultant (Mining, Geotechnical), is the QP responsible for portions of Sections 1, 25 and 26 summarized therefrom, of this Technical Report.
2.2 Qualifications of Consultants (Sierra Metals)

The following individuals from Sierra Metals, by virtue of their education, experience and professional association, are considered Qualified Persons (QP) as defined in the NI 43-101 standard, for this report, and are members in good standing of appropriate professional institutions. QP certificates of authors are provided in Appendix A. The QPs are responsible for specific sections as follows:

· Américo Zuzunaga, Vice-President Corporate Planning, is the QP responsible for Sections 15, 16, 18, 19, 20, 21, 22, 23 and 24, and portions of Sections 1, 25 and 26 summarized therefrom, of this Technical Report.
CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 3
2.3 Details of Inspection

Table 2-1: Site Visit Participants

Personnel Company Expertise Dates of Visit Details of Inspection
Andre Deiss SRK Resource Geology, Mineral Resources April 7 & 8, 2019 Reviewed geology, resource estimation methodology, sampling and drilling practices, and examined drill core.
Carl Kottmeier SRK Mining, Infrastructure, Economics April 7 & 8, 2019 Reviewed mining methods, UG and surface infrastructure.
Daniel Sepulveda SRK Metallurgy and Process April 7 & 8, 2019 Reviewed metallurgical test work, tailings storage, and process plant.

Source: SRK, 2020

2.4 Sources of Information

The sources of information include data and reports supplied by Sierra Metals and Dia Bras personnel, and the previous NI 43-101 technical report prepared by SRK. Documents cited throughout the report are referenced in Section 27.

2.5 Effective Date

The effective date of this report is December 31, 2019.

2.6 Units of Measure

The metric system has been used throughout this report. Tonnes (t) are metric of 1,000 kilogram (kg), or 2,204.6 pounds (lb). All currency is in U.S. dollars (US$) unless otherwise stated.

3 Reliance on Other Experts

This PEA report is not a wholly independent report as some sections have been prepared and signed off by QPs from Sierra Metals, the project owner, with the term QP used here as it is defined under NI 43-101 standards. Section 2 explains which report sections were prepared by SRK and which were prepared by Sierra Metals.

The consultants' opinions contained herein are based on information provided to the consultants by Sierra Metals throughout the course of the investigations. SRK has relied upon the work of other consultants in some areas in support of this Technical Report.

The consultants used their experience to determine if the information from previous reports was suitable for inclusion in this Technical Report and adjusted information that required amending. This report includes technical information that required subsequent calculations to derive subtotals, totals and weighted averages. Such calculations inherently involve a degree of rounding and consequently introduce a margin of error. Where these occur, the consultants do not consider them to be material.

SRK received statements of validity for mineral titles, surface ownership and permitting for various areas and aspects of the Bolivar Mine and reproduced them for this report. These items have not been independently reviewed by SRK and SRK did not seek an independent legal opinion of these items.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 4
4 Property Description and Location
4.1 Property Location

The Bolivar Property is located in the state of Chihuahua, Mexico (Figure 4-1), in the municipality of Urique. The Property is situated in the rugged, mountainous terrain of the Sierra Madre Occidental, approximately 400 km by road southwest of the city of Chihuahua and approximately 1,250 km northwest of Mexico City. The geographic center of the Property is 27°05'N Latitude and 107°59'W Longitude. It is roughly bounded to the northeast by the Copper Canyon mine (50 km from the Bolivar Mine), to the south by the El Fuerte river (18 km), to the north by the village of Piedras Verdes (5 km), and to the northwest by the town of Cieneguita (12.5 km).

Source: Sierra Metals, 2020

Figure 4-1: Map Showing the Location of the Bolivar Property in Chihuahua, Mexico

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 5
4.2 Mineral Titles

Sierra Metals wholly holds mineral concession titles allowing exploration and mining within 14 concessions (6,799.69 ha) that make up the project area. Locations of the concessions are shown in cyan in Figure 4-2. Other area concessions are shown in gray. The concessions list is provided in Table 4-1. Production from the Bolivar Mine is not subject to any royalties; however, the concessions are subject to a federal tax that varies by concession.

Table 4-1: Concessions for the Bolivar Mine

Claim Name Surface Area (ha) File Number Title Number Expiration Date
La Cascada 1,944.33 016/32259 222720 August 26, 2054
Bolivar III 48.00 321.1/1-64 180659 July 13, 2037
Bolivar IV 50.00 321.1/1-118 195920 September 22, 2042
Piedras Verdes 92.47 016/31958 220925 October 27, 2054
Mezquital 2,475.41 016/32157 223019 October 4, 2054
Mezquital Fracc. 1 4.73 016/32157 223020 October 4, 2054
Mezquital Fracc. 2 2.43 016/32157 223021 October 4, 2054
Mezquital Fracc. 3 974.57 016/32157 223022 October 4, 2054
El Gallo 251.80 016/32514 224112 April 04, 2055
Bolivar 63.56 321.1/1-100 192324 December 18, 2041
La Chaparrita 10.00 1/1.3/00882 217751 August 12, 2052
La Mesa 718.95 016/32556 223506 January 11, 2055
Moctezuma 67.43 1/1/01432 226218 December 01, 2055
San Guillermo 96.00 099/02161 196862 August 12, 2043
Total 6,799.69

Source: Sierra Metals, 2020

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 6

Source: SNL FINANCIAL LC, 2020

Figure 4-2: Land Tenure Map showing Bolivar Concessions

Figure 4-3 shows the concessions in the immediate Bolivar Mine area with the Bolivar West, Bolivar Northwest and La Sidra zones identified.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 7

Source: SNL FINANCIAL LC, 2020

Figure 4-3: Map of the Bolivar Property

4.2.1 Nature and Extent of Issuer's Interest

Sierra Metals holds an agreement for surface rights (exploration and mining) with Piedras Verdes Ejido, the village roughly 12 km from the property. Production from the Bolivar Mine is not subject to any royalties; however, the concessions are subject to a federal tax that varies by concession.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 8
4.3 Royalties, Agreements and Encumbrances
4.3.1 Purchase Agreements

The concessions listed in Table 4-1 are described in more detail as follows:

· La Cascada: In August 2004, Sierra Metals entered into an Option to Purchase Agreement with Polo y Ron Minerales, S.A. de C.V. to acquire the La Cascada claim for US$10,000;
· Bolivar III and Bolivar IV: In 2004, Sierra Metals purchased 50% of all the rights of Bolívar III and IV from Minera Senda de Plata, SA de CV. On October 2, 2007 the remaining 50% was purchased from Mr. Javier Octavio Bencomo Munoz and his wife Carmen Beatriz Chavez Marquez;
· Piedras Verdes: In December 2007, Sierra Metals entered into an Option to Purchase Agreement with Mr. Raul Tarín Melendez and Mrs. María Francisca Carrasco Valdez to purchase the Piedras Verdes concession for US$10,000;
· Mezquital, Mezquital Fracción 1 through 3, and El Gallo: On November 2005, Sierra Metals entered into an Option to Purchase Agreement with Polo y Ron Minerales, S.A. de C.V. to acquire the Mezquital, Mezquital Fracción 1, Mezquital Fracción 2, Mezquital Fracción 3, and El Gallo concessions for US$5,000;
· Bolivar: In January 2008, Sierra Metals entered into a purchase agreement with Marina Fernandez regarding the Bolívar property for US$85,000 paid between 2008 and 2009;
· La Chaparrita: In January 29, 2008, Sierra Metals entered into an Option to Purchase Agreement with Mr. Jesús Fernández Loya on behalf of Minera Senda de Plata S.A. de C.V. to purchase the La Chaparrita concession for US$85,000;
· La Mesa: In January 2005, Sierra Metals staked the La Mesa claim, at Dirección General de Minas, México;
· Moctezuma: In November 2010, Sierra Metals entered into an Option to Purchase Agreement with Mr. Juan Orduño García, Mr. Jesús Manuel Chávez González, and Mr. Armando Solano Montes purchase the Moctezuma concession. The terms of the agreement included a total cash payment of MX$3,500,000 (Mexican Pesos); and
· San Guillermo: In October 2011, Sierra Metals entered into a purchase agreement with Minera Potosi Silver, a sister company of Minera Piedras Verdes del Norte, S.A. de C.V., for the San Guillermo concession for MX$464,000.
4.3.2 Legal Contingencies

In 2009, a personal action was filed in Mexico against DBM by an individual, Ambrosio Bencomo Muñoz, as administrator of the intestate succession of Ambrosio Bencomo Casavantes y Jesus Jose Bencomo Muñoz, claiming the annulment and revocation of the purchase agreement of two mining concessions, Bolívar III and IV between Minera Senda de Plata S.A. de C.V. and Ambrosio Bencomo Casavantes, and with this, the nullity of purchase agreement between DBM and Minera Senda de Plata S.A. de C.V. In June 2011, the Sixth Civil Court of Chihuahua, Mexico, ruled that the claim was unfounded and dismissed the case, the plaintiff appealed to the State Court. On November 3, 2014, the Sixth Civil Court of Chihuahua ruled against the plaintiff, noting that the legal route by which the plaintiff presented his claim was not admissible. On February 17, 2017 the State Court issued a ruling dismissing the arguments of the plaintiff. Sierra Metals is attentive to any legal action that is generated in relation to this process.

Carlos Emilio Seijas Bencomo, a relative of Ambrosio Bencomo Casavantes and Ambrosio Bencomo Muñoz, following the steps of the Ambrosio lawsuit, filed a similar personal action to claim annulment and revocation of the purchase of the two mining concessions. In May 31, 2019, the Second Federal Civil Court issued a resolution ordering: a) the annulment and revocation of the purchase agreement of the two mining concessions, Bolívar III and IV between Minera Senda de Plata S.A. de C.V. and Ambrosio Bencomo Casavantes, and with this, the nullity of purchase agreement between DBM and Minera Senda de Plata S.A. de C.V., and b) the payment of a sum of money pending to be defined by concept of restitution of the benefits of those two mining concessions. In June 2019, a Federal Court Chihuahua granted Sierra Metals a suspension of this adverse resolution issued. At this time, the appeal (writ of amparo) presented by the Company is pending to be resolved by the Third Federal Collegiate Court of Civil and Labor Matters of the Seventeenth circuit in Chihuahua. Sierra Metals will continue to vigorously defend this action and is confident that the claim is of no merit.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 9
4.4 Environmental Liabilities and Permitting
4.4.1 Environmental Liabilities

Based on communications with representatives from Sierra Metals, and a reconnaissance of the Property in January 2018, it does not appear that there are currently any known environmental issues that could materially impact the extraction and beneficiation of Mineral Resources or Reserves. From previous assessments (Gustavson, 2013), lesser known environmental liabilities include unreclaimed exploration disturbances (i.e., roads, drill pads, etc.) and small residual waste rock piles from historical mining operations. As observed by SRK personnel during previous site visits, dust emissions generated as a result of ore haulage traffic from the mine to mill could become an issue in the future but has not yet become an issue for SEMARNAT.

4.4.2 Required Permits and Status

Required permits and the status of permits are discussed in Section 20.

4.5 Other Significant Factors and Risks

There are no other factors or risks that affect access, title or right or ability to perform work on the Property other than those stated in the above sections which SRK would expect to have a material impact on the Mineral Resource statement.

5 Accessibility, Climate, Local Resources, Infrastructure and Physiography
5.1 Topography, Elevation and Vegetation

The Bolivar Property is located in the rugged topography of the Sierra Madre Occidental mountain range. Elevation varies from 600 to 2,100 m above sea level.

Vegetative cover in the region consists of oak and eucalyptus trees at low elevations and pine trees at higher elevations. The land surrounding the mine is used to raise cattle. Wildlife in the area includes various species of insects, lizards, snakes, birds, and small mammals.

5.2 Accessibility and Transportation to the Property

From the city of Chihuahua, the Bolivar Property can be accessed via travel along paved (325 km) and unpaved (70 to 80 km) roads to the Piedras Verdes or Cieneguita villages, located 5 km and 12.5 km north of the Bolivar Mine, respectively.

Transportation from the villages to the mineral concessions is via private and company vehicles.

5.3 Climate and Length of Operating Season

Climate in the project area is semi-arid, with a mean annual temperature of 25°C and 758 mm of annual precipitation on average. The region experiences a rainy season from June to October, when monthly precipitation ranges from 83 to 188 mm; the rest of the year is relatively dry (approximately 26 mm of monthly precipitation). In the past, the Bolivar Mine has operated year-round and operations were not limited by climatic variations.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 10
5.4 Infrastructure Availability and Sources
5.4.1 Power

Electricity is currently sourced from Mexico's main grid system. Backup generators are also located at the Bolivar Mine site.

5.4.2 Water

Industrial water is sourced from the Piedras Verdes dam, a reservoir that is owned and operated by Sierra Metals. The reservoir drains to the El Fuerte River, 18 km south of the Bolivar Mine. Water from the dam is sufficient to meet mine and mill operations and exploration needs. Potable water is available from local sources.

5.4.3 Mining Personnel

Two villages, Piedras Verdes and Cieneguita, are located within 10 km of the mineral concessions. The combined population of these two villages is approximately 1,500 people and many of the mine employees live in these villages.

5.4.4 Potential Tailings Storage Areas

The site has an existing TSF. The tailings management plan at the Bolivar Mine includes placement of tailings in a number of locations. The site will be installing infrastructure to recover additional process water and reduce the water content of the final tailings. An additional thickener and filter presses will be installed by 2021.

5.4.5 Potential Waste Rock Disposal Areas

The site has existing permitted waste rock disposal areas.

5.4.6 Potential Processing Plant Sites

The site has an existing processing plant that has been in use since its commissioning in 2011.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 11
6 History

Ownership history of the mineral concessions at Bolivar is shown in Table 6-1, modified from a 2013 technical report completed by Gustavson Associates in Lakewood, Colorado, USA. No earlier records of ownership are known to exist.

Table 6-1: Ownership History and Acquisition Dates for Claims at the Bolivar Property

Claim Name Previous Owner Date Acquired
La Cascada Polo y Ron Minerales, S.A. de C.V. August 10, 2004
Bolivar III Javier Bencomo Munoz y Minera Senda de Plata, S.A. de C.V. September 14, 2004
Bolivar IV Javier Bencomo Munoz y Minera Senda de Plata, S.A. de C.V. September 14, 2004
Piedras Verdes Raul Tarin Melendez December 11, 2007
Mezquital Polo y Ron Minerales, S.A. de C.V. November 11, 2005
Mezquital Fracc. 1 Polo y Ron Minerales, S.A. de C.V. November 11, 2005
Mezquital Fracc. 2 Polo y Ron Minerales, S.A. de C.V. November 11, 2005
Mezquital Fracc. 3 Polo y Ron Minerales, S.A. de C.V. November 11, 2005
El Gallo Polo y Ron Minerales, S.A. de C.V. November 11, 2005
Bolivar Minera Senda de Plata, S.A. de C.V. January 29, 2008
La Chaparrita Minera Senda de Plata, S.A. de C.V. January 29, 2008
La Mesa Direccion General de Minas January 12, 2005
Moctezuma Juan Orduno Garcia/Jesus Chavez Gonzalez/Armando Solano Montes November 5, 2010
San Guillermo Minera Potosi, S, de R.L. de CV. October 6, 2011

Source: Gustavson, 2013

6.1 Exploration and Development Results of Previous Owners

Historic mining, prospecting and exploration for polymetallic Cu-Zn-Pb-Ag-Au deposits in the Sierra Madre precious metals belt of Northwestern Mexico have been carried out since the Spanish colonial period. Small scale mining was realized by small miners from Spanish colonial days, without historical record for the Piedras Verdes District. Between 1968 and 1970, Minera Frisco was exploring for porphyry copper deposits at the Piedras Verdes District, including mapping, sampling and drilling, however the reports are not available.

From 1980 to 2000, some 300,000 tonnes of mineralized material were mined while the Bolivar Mine was under the control of the Bencomo Family; detailed production records for this period are not available (De la Fuente, et. al., 1992)

Information provided by Sierra Metals' exploration department, September 30, 2019, suggests that from December 2003 to the present, Sierra Metals carried out an exploration program of regional geological mapping at the Bolívar Property covering 15,217 ha. The work included detailed mapping, geochemistry sampling, geophysics, topographic surveying and diamond drilling, with 274,321 m drilled in 1,414 diamond drill holes.

6.2 Historic Mineral Resource and Reserve Estimates

A QP has not done sufficient work to classify the historical estimate as a current Mineral Resource estimate or Mineral Reserve estimate and the issuer is not treating the historical estimate as a current resource estimate.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 12
6.3 Historic Production

Historic mining and exploration for polymetallic deposits in the Sierra Madres has been carried out sporadically since the Spanish colonial period. In 1632, a native silver vein was discovered at La Nevada near Batopilas. Thereafter, sporadic mining of silver deposits continued for almost one hundred years. A second phase of mining started with the Carmen Mine near the end of 18th Century but was halted due to the Mexican War of Independence from 1810 to 1821. A third phase of mining in the region occurred from 1862 to 1914 but was again halted due to the Mexican Revolution in 1910.

The Urique District is characterized by gold-rich fissure veins hosted by andesitic rocks. Since 1915, there have been sporadic attempts to develop mineral deposits in the area. Small scale mining of polymetallic deposits in this district started before 1910 by gambusinos (artisanal miners). Production records from 1929 are reported as 2,891 t of ore containing 2,686 kg of copper (Cu), 7,990 kg of lead (Pb), 1,061 kg of silver (Ag) and 44 kg of gold (Au), indicating an average grade of 0.09% Cu, 0.28% Pb, 367 g/t Ag and 15.22 g/t Au. Since 1915, some 300 M oz of silver are reported to have been produced from the Batopilas District.

Other mining activities in the area include the Cieneguita de los Trejo gold deposit located at the outskirts of the village of Cieneguita, which is situated about 1.5 km northwest of the northwestern corner of the El Cumbre Mineral License. In the 1990s, Glamis Gold Ltd. (Glamis) developed an open pit mine and produced gold by heap leaching method. The old leach pads are visible from the Bolivar property.

From 1980 to 2000, some 300,000 t of mineralized material were mined while the Bolivar Mine was under the control of the Bencomo Family. This mineralized material included:

· 195,000 t from the Fernandez trend;
· 90,000 t from the Rosario Trend; and
· 15,000 t from the Pozo del Agua Area.

Detailed production records for this period are not available but are reported to be in the order of 50 tpd, and the average grade of the mineralized material is reported to be in the range of 5% to 6% Cu and 25% to 30% Zn. Production records from 2000 to 2007 were not available to SRK.

According to Sierra Metals, production from 2008 to 2010 was as follows:

· 2008: 126,500 t processed at 1.65% copper grade and 8.00% zinc grade;
· 2009: 89,600 t processed at 1.81% copper grade, 10.06% zinc grade, and 49.5 g/t silver;
· 2010: 104,800 t processed at 1.45% copper grade, 8.59% zinc grade, and 31.6 g/t silver.
CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 13

Commercial production was declared in November 2011. Table 6-2 lists the 2011 to 2019 production as reported by Sierra Metals.

Table 6-2: 2011 to 2019 Bolivar Production

Year Plant

Tonnes Processed

(dry)

Au

(g/t)

Ag

(g/t)

Cu

(%)

2011 Mal Paso (1) 88,247 46.62 1.32
2012 Piedras Verdes 312,952 24.58 1.17
2013 Piedras Verdes 507,865 0.05 21.16 1.25
2014 Piedras Verdes 666,414 0.29 22.23 1.20
2015 Piedras Verdes 830,447 0.25 20.57 1.15
2016 Piedras Verdes 950,398 0.19 16.72 1.00
2017 Piedras Verdes 887,236 0.17 14.93 0.96
2018 Piedras Verdes 1031,750 0.17 17.69 0.95
2019 Piedras Verdes 1,269,697 0.27 19.81 0.85

Source: Sierra Metals, 2020

(1) Bolivar material was processed at the Mal Paso mill in 2011 until the Piedras Verdes mill was commissioned in November 2011.
CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 14
7 Geological Setting and Mineralization
7.1 Regional Geology

The Bolivar Property is located within the Guerrero composite terrane which makes up the bulk of western Mexico and is one of the largest accreted terranes in the North American Cordillera. The terrane is proposed to have accreted to the margin of Mexico in the Late Cretaceous and consists of submarine and lesser subaerial volcanic and sedimentary sequences ranging from Upper Jurassic to middle Upper Cretaceous in age. These sequences rest unconformably on deformed and partially metamorphosed early Mesozoic oceanic sequences.

The Bolivar deposit is one of many precious and base metal occurrences in the Sierra Madre precious metals belt, which trends north-northwest across the states of Chihuahua, Durango, and Sonora (Figure 7-1).

Source: Sierra Metals, 2020

Figure 7-1: Regional Geology Map showing the Locations of Various Mines in the Sierra Madre Occidental Precious Metals Belt

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 15
7.2 Local Geology

The Piedras Verdes District shown in Figure 7-2 consists of Cretaceous andesitic to basaltic flows and tuffs intercalated with greywacke, limestone, and shale beds commonly referred to as the Lower Volcanic Series (LVS). This volcanic-sedimentary package has been intruded by several Upper Cretaceous to Lower Cenozoic age intermediate to felsic composition plutonic bodies that range from 85 to 28.3 Ma. The LVS and intermediate to felsic intrusive bodies have in turn been overlain by a widespread cap of rhyolitic and dacitic ignimbrites and tuffs referred to as the Upper Volcanic Series (UVS) that were deposited between 30 to 26 Ma. The UVS is one of the largest continuous ignimbrite provinces in the world. All known mineralization in this region formed during the time interval between the deposition of the LVS and the deposition of the UVS (Meinert, 2007).

At the Bolivar Property, the volcanic rocks strike northwest and dip gently to moderately to the northeast. Assuming these volcanics are younger than the granodiorite, the stock must also be tilted to the northeast (Meinert, 2007). Several outcrops exhibit tight, northeast trending folds. Three major sets of faults have been recognized at the local scale: a north-northwest trending set which dip steeply northeast or southwest, an east-southeast trending set, and a north-trending set. None of the faults on the property is described as having offsets greater than 200 m (Meinert, 2007).

The structural setting and stratigraphy control the mineralization at Bolivar.

Source: Sierra Metals, 2020

Figure 7-2: Local Geology Map Showing the Location of the Bolivar Property

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 16
7.3 Property Geology
7.3.1 Skarn-hosting Sedimentary Rocks

Skarn alteration and mineralization at the Bolivar Property is hosted primarily in a package of sedimentary rocks that occur as a layer or lens within the LVS (Reynolds, 2008). All sedimentary units have undergone low grade metamorphism. The lowermost sedimentary horizon observed is a dolostone which ranges from 24 m to 40 m in thickness. The lower part of the dolostone horizon is interlayered with siltstone. To the south, progressively less of the sedimentary sequence is cut out by granodioritic intrusive rocks and the dolostone is observed to be underlain by a siltstone horizon.

The lower siltstone unconformably overlies the LVS. The dolostone is overlain by a discrete layer of siltstone. The average thickness of this siltstone unit is 12 to 30 m. Horizons of argillaceous dolostone (50 m thick) and argillaceous limestone (9 m thick) are above the siltstone marker layer. The uppermost sedimentary horizon is a limestone with local chert and argillaceous laminations. The vertical thickness of this horizon varies considerably in cross-section (108 to 173 m) and this variation is attributed to paleo-topographic relief. The upper contact of the limestone is an unconformity with the LVS. Figure 7-3 presents the stratigraphy of the property and Figure 7-4 is the geologic map.

7.3.2 Intrusive Rocks

The most important igneous rocks on the property are the Piedras Verde granodiorite and related andesite dikes and sills. All are slightly porphyritic, but none are a true porphyry. The Piedras Verde granodiorite exhibits a range of textural variations and compositions. The average composition is very similar to plutons related to Cu skarns (Meinert, 2007). There is no indication of a gold association.

The dikes locally cut the granodiorite, have planar, chilled contacts, and are generally finely crystalline. Both their texture and crosscutting relations suggest that the dikes are younger and shallower than the granodiorite. Both granodiorite and andesite dikes have alteration and locally skarn along their contacts. In addition, endoskarns, which are skarns of igneous origin that form within the granite mass itself, affect both the granodiorite and in rare cases, the andesite dikes. Thus, these rocks are older than or at best coeval with alteration/mineralization. The presence of skarn veins cutting an andesite dike is clear evidence that at least some skarn is later than at least some of the andesite dikes. A closer association of granodiorite with skarn alteration and mineralization is suggested by local K-silicate veining of the granodiorite and the zonation of skarn relative to this contact.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 17

Source: Sierra Metals, 2020

Figure 7-3: Stratigraphic Column of the Bolivar Property

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 18

Source: Sierra Metals, 2020

Figure 7-4: Geologic Map of the Bolivar Property

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 19
7.4 Significant Mineralized Zones

Mineralization at the Bolivar Property is hosted by skarn alteration in carbonate rocks adjacent to the Piedras Verde granodiorite (Meinert, 2007). Orientations of the skarn vary dramatically, although the majority are gently-dipping. Thicknesses vary from 2 m to over 20 m. Skarn mineralization is strongly zoned, with proximal Cu-rich garnet skarn in the South Bolivar area, close to igneous contacts, and more distal Zn-rich garnet+pyroxene skarn in the northern Bolivar and southern skarn zones near El Val. The presence of chalcopyrite+bornite dominant skarn (lacking sphalerite) in the South Bolivar area, along with K-silicate veins in the adjacent granodiorite suggests that this zone is close to a center of hydrothermal fluid activity. In contrast, the main Bolivar Mine is characterized by Zn>Cu and more distal skarn mineralogy such as pyroxene>garnet and pale green and brown garnets. Alteration is zoned relative to fluid flow channels. From proximal to distal, the observed sequence is red-brown garnet to brown garnet with chalcopyrite ± bornite ± magnetite to green garnet ± pyroxene with chalcopyrite + sphalerite to massive sulfide (sphalerite ± chalcopyrite ± galena) to marble with stylolites and other fluid escape structures.

Mineralization exhibits strong stratigraphic control and two stratigraphic horizons host the majority: an upper calcic horizon, which predominantly hosts Zn-rich mineralization, and a lower dolomitic horizon, which predominantly hosts Cu-rich mineralization. Figure 7-5 presents an example of a mineralized skarn with propylitic alteration in a core sample of El Gallo area. In both cases, the highest grades are developed where fault or vein structures and associated breccia zones cross these favorable horizons near skarn-marble contacts. Meinert (2007) suggested that hydrothermal fluids moved up along the Piedras Verde granodiorite contact, forming skarn and periodically undergoing phase separation that caused brecciation. Zones of breccia follow faults like the Rosario, Fernandez, and Breccia Linda trends as well as nearly vertical breccia pipes such as La Increible.

Source: Sierra Metals, 2020

Figure 7-5: Mineralized Andradite Garnet Skarn - El Gallo Area Core Sample

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 20
8 Deposit Types
8.1 Mineral Deposit

The Bolivar deposit is classified as a high-grade Cu-Zn skarn and exhibits many characteristics common to this type of deposit (Meinert, 2007). The term 'skarn' refers to coarse-grained calcium or magnesian silicate alteration formed at relatively high temperatures by the replacement of the original rock, which is often carbonate-rich.

The majority of the world's economic skarn deposits formed by infiltration of magmatic-hydrothermal fluids, resulting in alteration that overprints the genetically related intrusion as well as the adjacent sedimentary country rocks (Ray and Webster, 1991). While alteration commonly develops close to the related intrusion, fluids may also migrate considerable distances along structures, lithologic contacts, or bedding planes.

Based on the alteration assemblages present, skarn deposits are generally described as either calcic (garnet, clinopyroxene, and wollastonite) or magnesian (olivine, phlogopite, serpentine, spinel, magnesium-rich clinopyroxene). Both the alteration and the mineralization in skarn deposits are considered to be magmatic-hydrothermal in origin.

8.2 Geological Model

The geological model of the Bolivar deposit is well-understood and has been verified through multiple expert opinions as well as a history of mining. SRK is of the opinion that the model is appropriate and will serve Sierra Metals going forward.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 21
9 Exploration
9.1 Relevant Exploration Work

The following information has been modified and updated from a 2009 Technical Report prepared by SGS Geostat.

Exploration conducted by Sierra Metals, 2003-2012:

· 2003 to 2005. During this period, Sierra Metals carried out an exploration program of geological mapping, outcrop sampling, topographic survey, at 1:250 and 1:500 scale, including detailed 2 m x 2 m panel sampling perpendicular to the mineralized structures. Sierra Metals completed semi-regional prospecting, reconnaissance and representative sampling of the Bolivar District at the La Montura and La Narizona prospects. Pilot mining started at the Bolivar Mine. Development drifting conducted led to the Brecha Linda orebody discovery.
· 2006. Sierra Metals performed detailed 1:500 scale geologic mapping in the Bolivar and Bolivar South areas, including 2 m x 2 m panel sampling. Sierra Metals did some prospecting in other mineralized areas to the south, including El Gallo. This work was accompanied by a rock panel geochemical survey. The results of the El Gallo prospecting supported the drilling program.
· 2007. Detailed underground, 1:250 scale geological mapping was completed on the El Gallo and La Narizona areas, including detailed 2 m x 2 m panel sampling. This exploration work identified two mineralized stratiform horizons in the El Gallo area, El Gallo Superior (EGS) and El Gallo Inferior (EGI), similar to the stratiform orebody at La Narizona. Preliminary geologic mapping to support the drilling was completed on three other mineralized areas to the south, La Montura, La Pequeña and El Val.
· 2008. Detailed 1:500 scale surface geology mapping was done at the Bolivar North zone, including representative chips sampling, yielding a geochemical anomaly consistent with the NW structural trend. Mining was mainly concentrated in the Titanic, Selena and San Francisco areas on and under level 6 (Rosario), Guadalupe, Rebeca and San Angel, which were high grade, individual orebodies, geologically related to the calcareous upper stratigraphic favorable horizon.
· 2009. Detailed 1:250 scale geologic mapping was done at San Francisco and Los Americanos North, including detailed 2 m x 2 m panel sampling. Regional 1:25,000 scale geology and detailed stream sediment sampling was done over the entire Bolivar Property, yielding the new targets of Los Americanos - Lilly Skarn (Cu-Zn), La Cascada - Sidra (Au) and El Mezquite (Au). Underground 1:250 scale detailed mapping was done at San Francisco and La Increible Mines, including detailed 2 m x 2 m panel sampling. Mining was mainly concentrated at the Bolivar Mine in the high-grade orebodies (Rosario, La Foto, Fernandez, Rosario Magnetita, and San Angel areas). Sierra Metals announced the construction of the new Piedras Verdes Mill with capacity of 1,000 tpd.
· 2010. 1:1000 scale geologic mapping was done at La Cascada - La Sidra areas, including chips channel sampling, and a TITAN IP geophysical survey was conducted by QUANTEC Geoscience. A drilling program was completed, indicating low grade gold. Regional 1:25,000 scale geologic mapping was completed over the entire Bolivar Property, including lithology units, regional faulting and dikes, and alteration, confirming the previous geochemical anomalies on Los Americanos - Lilly Skarn (Cu-Zn), La Cascada - La Sidra (Au) and El Mezquite (Au) targets. Underground 1:250 scale detailed mapping, including detailed 2 m x 2 m panel sampling was done at El Gallo, La Increible and La Narizona Mines. Mining during this time was mainly concentrated at La Narizona, El Gallo, and Rosario areas, while Sierra Metals continued with the construction of the new Piedras Verdes Mill.
CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 22
· 2011. New geological interpretations indicated the continuity of El Gallo trends to the southeast toward La Montura, and northeast toward La Increible, discovering the El Salto and El Gallo step out areas respectively. Underground development and production drifting allowed detailed 1:250 scale mapping at Bolivar, El Gallo, and La Narizona Mines. Mining of 360 tpd was terminated during late October and the new Piedras Verdes Mill started with commercial production of 1,000 tpd operation, mainly from El Gallo Mine.
· 2012. Underground development and production drifting and detailed 1:250 scale mapping was done at Bolivar, El Gallo, and La Narizona Mines. Production of 1,000 tpd processing at Piedras Verdes Mill began by receiving ore principally from the upper stratigraphic horizon from El Gallo Mine. Exploration drilling on the El Gallo step out and El Salto areas continued. Preliminary drilling started at La Montura and La Pequeña areas, located in between El Gallo and La Narizona Mines.
· 2013 to 2016. New geological interpretations were completed at Bolivar for the Bolivar W and Bolivar NW areas. Underground production and development in El Gallo Superior (EGS) and El Gallo Inferior (EGI) were ongoing during this time period, along with new development of the Chimeneas areas. Interpretation and drilling of the La Sidra vein to the west of the main Bolivar Mine area yielded exploration drilling results which included mineralized intervals ranging from 0.3 to 2.1 m, with grades ranging from 0.01 to 9.1 g/t Au and 0.01 to 1,850 g/t Ag.
· 2017. Additional drilling was focused in the Bolivar W and Bolivar NW areas. Three drill holes were completed in the El Gallo area. A TITAN IP geophysical survey was conducted by QUANTEC Geoscience in order to determine the possible extensions of known zones of mineralization.
· 2018. Additional drilling and new geological interpretations were completed based on the 2017 geophysical survey, resulting in a considerable increase in Mineral Resources in the Bolivar W and Bolivar NW areas.
· 2019. Drilling of geophysical anomalies continued, resulting in identification of mineralization west of Bolivar W.
9.2 Sampling Methods and Sample Quality

Sampling supporting Mineral Resource estimation consists of drill core and underground channel types. SRK reviewed in general the methods and the quality assurance protocol carried out by trained geologists or geologic technicians. SRK is of the opinion that the methodology and QA/QC protocol used during drilling campaigns since 2016 follows industry standard practices, although some improvements can be implemented.

9.3 Significant Results and Interpretation

The exploration results at Bolivar, and in the nearby area, are used to develop detailed exploration plans and to support Mineral Resource estimation.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 23
10 Drilling
10.1 Type and Extent

Between 1968 and 1970, Minera Frisco drilled short diamond drill holes, but existing records do not provide a reliable register of the number of holes, meters drilled, or the results of the drilling.

Between 2003 and 2019, Sierra Metals drilled 994 drill holes totaling to 259,748 meters as listed in Table 10-1 and shown in Figure 10-1. The objective of drilling completed during this period was to explore for mapped and projected polymetallic sulfide mineralization in calc-silicate rocks with moderate east-northeast dips. These efforts identified Cu-rich skarn mineralization within the Bolivar III, Bolivar IV, Piedras Verdes, and El Gallo concessions.

Table 10-1: Summary of Drilling by Sierra Metals on the Bolivar Property, 2003 to 2019

Year Count Meters % of Total Meters
2003 1 202 0.1%
2004 93 15,770 6.1%
2005 70 12,360 4.8%
2006 61 9,959 3.8%
2007 96 21,841 8.4%
2008 95 20,826 8.0%
2009 43 5,643 2.2%
2010 28 3,736 1.4%
2011 26 6,574 2.5%
2012 40 13,032 5.0%
2013 27 11,402 4.4%
2014 30 5,830 2.2%
2015 75 18,342 7.1%
2016 51 16,585 6.4%
2017 102 40,244 15.5%
2018 70 28,022 10.8%
2019 86 29,382 11.3%
Total 994 259,748 100.0%

Source: SRK, 2020

Note: Totals may not match due to rounding.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 24

Source: SRK, 2020

Figure 10-1: Location Map of Drill Hole Collars (green) and Traces (grey)

10.2 Procedures

The Bolivar Mine uses a local coordinate grid which is based on meters from a central control point. Nearby exploration is registered in a standard UTM coordinate grid, and thus it is necessary to consider the exploration data separately from the mine data.

The primary drilling method at Bolivar has been diamond drill core. To date, 994 drill holes have been completed with an average length of approximately 260 m. The drill holes have been drilled predominantly from surface, and to a lesser degree from underground, in a wide variety of orientations. Near the mining operations, the average drill hole spacing ranges between 25 and 50 m. In the deeper or less explored areas, the average drill hole spacing ranges between 75 and 150 m. Overall, the majority of the drilling completed by Sierra Metals has been relatively closely spaced and appears to have been directed at Mineral Resource delineation. Approximately 30% of the drill holes have had downhole deviation surveys completed. A significant number of the drill holes are relatively long, and their precise location is considered uncertain due to the lack of downhole surveys. Since 2015, approximately 75% of drill holes have been downhole surveyed using the Deviflex survey tool (non-magnetic electronic multi-shot). Prior to 2015, the practice of surveying exploration drilling was not carried out, which poses a significant risk as to the confidence regarding the location of the results and interpretation of exploration efforts. The drilling also intersects the mineralization at a wide range of orientations and therefore drill intercept lengths do not necessarily reflect the true thickness of mineralization.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 25

The drilling has been conducted with Sierra Metals-owned drills and outside contractors. All drill core has been logged by Sierra Metals geologists. Sample intervals are determined by the geologist and the core is then cut in half (hydraulic splitter) and bagged by Sierra Metals technicians. SRK is of the opinion that the core processing area and logging facilities are all appropriately organized and consistent with industry standard practices.

10.3 Interpretation and Relevant Results

The drilling results are used to guide ongoing exploration efforts and to support Mineral Resource estimation. Most of the individual deposits have been drilled as perpendicular to the deposit as possible, but some areas feature drilling that is nearly parallel to the trend of mineralization. This has been accounted for in the Mineral Resource classification, and SRK strongly recommends drilling these areas from different positions to improve the angle of intersection between the drilling and true thickness of mineralization.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 26
11 Sample Preparation, Analyses, and Security
11.1 Security Measures

After logging and splitting, all exploration drilling samples are laid out in order and recorded into a digital database prior to shipping. Samples are placed into larger plastic bags, and these bags are marked with the hole ID and sample numbers, then sealed with a security seal. All samples are kept behind gated access-controlled areas on the Bolivar Mine site, then transported by Sierra Metals personnel to a shipping facilitator. Hard copies and electronic forms are kept for all sample transactions, detailing shipping, receipt, and types of analyses to be conducted.

11.2 Sample Preparation for Analysis

Historically, samples have been crushed at Sierra Metals facilities at either the Malpaso Mill or the Piedras Verdes Mill. The Sierra Metals labs carry out a chemical analysis to define the mineralized intercepts. Once the mineralized intercepts are defined, the remaining crushed material of the samples is sent to ALS Chemex (ALS), an ISO-certified independent commercial laboratory. The rest of the sample preparation procedure is completed at the ALS Chemex Hermosillo, Mexico facility, and final analysis is conducted at the ALS Chemex primary laboratory in North Vancouver, BC, Canada. The crushing and splitting procedures in Sierra Metals labs should be appropriately controlled to avoid contamination of samples.

11.3 Sample Analysis

The analytical history of Bolivar sampling is complex and includes various sources of analyses from the nearby Malpaso Mill Lab or Piedras Verdes Mill Lab and ALS. Previous reports have noted inconsistencies between the internal and external laboratories in terms of analytical precision and accuracy, with the Malpaso Mill historically featuring relatively poor results from submitted QA/QC samples. A significant effort has been made over the past several years to improve the equipment and methodology for the Sierra Metals internal laboratory. Results of the current QA/QC program indicate that performance has drastically improved and is consistent with industry standards. The QA/QC program includes check samples between the Piedras Verdes (PV) Lab and ALS which show reasonable duplicate performance.

Currently, all samples are initially analyzed internally at the PV Lab, and selected intervals with identified mineralization are re-submitted to ALS. This step ensures that only intervals identified to have significant mineralization by the PV Lab are sent for analysis to ALS, thereby reducing analytical costs. The duplicates are selected from coarse rejects from the initial preparation. The ALS results are incorporated into the database as the final analytical result for the duplicated intervals. This is a reasonable practice, but a study should be conducted to formally document and establish the validity of the internal assays. Results from 2016 the QA/QC program suggest that the Piedras Verdes Mill may now be suitable as a primary lab, if monitoring of the performance continues.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 27
11.4 Quality Assurance/Quality Control Procedures

Samples supporting the Mineral Resource estimate have been analyzed almost exclusively by ALS in Vancouver. However, the preparation of samples has been completed at other facilities and historically conducted by the nearby PV Lab, with crushing rejects or pulps provided to ALS for analysis. Inconsistencies in the preparation methodology and the size-fraction of the received pulp have been noted over the history of the project, but the results of recent duplicate comparisons show reasonable agreement between samples prepared entirely by ALS and those prepared by the PV Lab.

One purpose of a QA/QC program is to submit samples with known or expected values, in the sequence of normal analyses, to "test" the internal or third-party laboratory's accuracy. These samples with known values are blind to the laboratory, so analyses that are not within expected tolerances represent failure criteria which are flagged upon receipt and action is taken to rectify with the lab the potential source of the failure and take corrective action.

Prior to 2013, the drill sampling QA/QC program only featured duplicate sampling which evaluates analytical precision. This program was not consistent with industry best practices and was modified to align with current industry standards. From 2013 to late 2015, a very basic QA/QC program included continued submission of duplicate samples to ALS, as well as insertion of Certified Reference Material (CRM). However, this program was not properly monitored, and the results were not tracked in detail. The current QA/QC procedures (established late 2015) include: insertion of CRMs, blanks, and duplicates, at rates consistent with industry best practices. The results are monitored and tracked by Sierra Metals personnel. The results of the QA/QC show reasonable performance for the laboratory and SRK is of the opinion that the current analytical methods and QA/QC procedures are consistent with industry standards.

In order to provide additional support to the data used for the MRE, Sierra Metals conducted a thorough review of the historic sample data in the unmined areas which were analyzed without modern QA/QC. They selected 315 (~307 m) samples from several areas and submitted these intervals for reanalysis with appropriate QA/QC measures to ALS. This process served to validate some historic drilling (dating back to 2012), specifically in areas that are critical to the MRE, as well as test the historic performance of the PV Lab against the new ALS results.

11.4.1 Certified Reference Materials

Sierra Metals currently inserts CRMs into the sample stream at a rate of about 1:20 samples, although the insertion rate is adjusted locally to account for particular observations in the core. Initially starting in 2015, three CRMs were procured and certified via round robin analysis for the exploration programs. These CRMs were homogenized and packaged by Target Rocks Peru (S.A.) and the round robin was conducted by Smee & Associates Consulting Ltd., a consultancy specializing in provision of CRMs to clients in the mining industry.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 28

Each CRM underwent a rigorous process of homogenization and analysis using aqua regia digestion and AA or ICP finish, from a random selection of 10 packets of blended pulverized material. None of these CRMs were certified for Au, a lesser contributor to the Mineral Resources at Bolivar. The six laboratories which participated in the round robin for the initial three Target Rocks CRM are:

· ALS Minerals, Lima;
· Inspectorate, Lima;
· Acme, Santiago;
· Certimin, Lima;
· SGS, Lima; and
· LAS, Peru.

The mean values and between-lab standard deviations (SD) were calculated from the received results of the round robin analyses, and the certified means and tolerances were provided in certificates from Smee & Associates. The certified means and expected tolerances for the initial three CRMs used from 2015 to 2017 are shown in Table 11-1.

Table 11-1: 2015 to 2017 CRM Expected Means and Tolerances

CRM Identifier Certified Mean Two Standard Deviations (between labs)
Ag (g/t) Pb % Cu% Zn% Ag (g/t) Pb % Cu% Zn%
MCL-01 26.4 0.326 0.896 0.988 1.90 0.03 0.05 0.07
MCL-02 40.8 0.653 1.581 2.49 3.4 0.05 0.084 0.09
Mat. PLSUL N° 03 192.0 3.094 1.033 3.15 4.0 0.084 0.036 0.13

Source: Sierra Metals, 2017

In 2018, six new CRMs were introduced into the QA/QC program and have been primarily used throughout the 2018 and 2019 drilling campaigns. Three of the new CRMs are certified for Au. The certified means and expected tolerances of these new CRMs are provided in Table 11-2.

Table 11-2: 2018-2019 CRM Expected Means and Tolerances

CRM Identifier Certified Mean Two Standard Deviations (between labs)
Au (g/t) Ag (g/t) Cu% Zn% Au (g/t) Ag (g/t) Cu% Zn%
MCL-03 19.8 0.794 5.22 2.40 0.042 0.25
SKRN-05 0.435 4.40 1.783 0.034 0.30 0.058
PLSUL-08 248.0 0.983 12.54 14.0 0.042 0.55
OXHYO-03 92.3 1.025 0.426 6.9 0.046 0.018
PLSUL-11 0.234 113.0 1.05 10.78 0.014 8.0 0.07 0.54
STRT-01 0.328 11.0 0.849 0.146 0.010 0.8 0.024 0.0091

Source: Sierra Metals, 2020

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 29

The QA/QC data provided to SRK included a total of 377 CRM analysis from the 2016 to 2019 drilling campaigns. The performance of CRMs is evaluated over time using a simple plot of the expected mean vs the reported analysis, and a ±3 standard deviation failure criteria. This is consistent with industry standard practices. SRK has noted some failures of CRMs submitted throughout the drilling campaigns. Examples of CRM analysis plots for Cu are provided in Figure 11-1 through Figure 11-3 .

Source: Sierra Metals, 2020

Figure 11-1: CRM Performance for MCL-01, MCL-02 and PLSUL-03 for Cu

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 30

Source: Sierra Metals, 2020

Figure 11-2: CRM Performance for SKRN-05, OXHYO-03 and STRT-01 for Cu

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 31

Source: Sierra Metals, 2020

Figure 11-3: CRM Performance for MCL-03, PLSUL-08 and PLSUL-11 for Cu

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 32
11.4.2 Blanks

Pulverized blank material is used in the QA/QC program to monitor for potential contamination in the pulverizing process of ALS and consists of barren limestone selected by Bolivar geologists prepared and certified by Target Rocks. Results submitted to SRK included 309 samples which were inserted into the sample stream for drill holes drilled between 2016 and 2019. The failure criteria for blanks is five (5) times the detection limit of the ALS lab. SRK reviewed the performance of the blank samples submitted and noted some failures for the blanks, occurring in seven (7) of the 309 samples, for Cu. An example of the blank performance chart is shown in Figure 11-4. The failures indicate contamination in the pulverizing and splitting process in the lab.

Source: Sierra Metals, 2020

Figure 11-4: Fine Blank Performance - Cu

Coarse blanks are not being used and the contamination in the crushing and splitting process is not being controlled.

11.4.3 Duplicates

Prior to 2013, the drill sampling QA/QC featured duplicate sampling only. The 2005 report by Roscoe Postle Associates (RPA) noted that Sierra Metals geologists collected field duplicate samples from split drill core after every tenth sample and submitted the samples to ALS, in lieu of a standard QA/QC program.

Currently, all duplicate samples are initially analyzed by the PV Lab, and selected mineralized intervals are then re-submitted to ALS; duplicates are selected from coarse rejects from the internal laboratory preparation.

The performance of duplicate splits show good correlation for Cu analysis as shown in Figure 11-5, as well as for Ag as shown in Figure 11-6. However, more variability for Au duplicate analysis is observed as shown in Figure 11-7.

It is recommended that Sierra Metals start the use of field duplicates, fine duplicates and coarse duplicates to evaluate the error in the core crushing and pulverizing sampling processes. Although the second lab used is PV Lab, SRK recommends using a certified laboratory as a second lab control to evaluate the analytical error.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 33

Source: Sierra Metals, 2020

Figure 11-5: Duplicate Sample Analysis for Cu (2018 and 2019 campaigns)

Source: Sierra Metals, 2020

Figure 11-6: Duplicate Sample Analysis for Ag (2018 and 2019 campaigns)

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 34

Source: Sierra Metals, 2020

Figure 11-7: Duplicate Sample Analysis for Au (2018 and 2019 campaigns)

11.4.4 Results

SRK is of the opinion that the results from the duplicate analyses suggest the PV Lab and ALS results show excellent overall comparisons and, despite a relatively high percent difference on a sample by sample basis, any bias between the two labs is negligible in terms of Mineral Resource estimation.

11.4.5 Actions

Although some failures of blanks and CRMs were found, no actions have been taken. The procedures and processes for definition of actions upon detection of failures have been improved but there is no well-documented information about the actions taken when failures in blanks and CRMs are found. The general procedure is described as follows:

· Upon receipt of laboratory analytical reports, QA/QC samples are copied and merged into a master spreadsheet which displays them on a graph, as well as designating whether they are a failure per the above criteria.
· In the event of a failure, the database technicians communicate internally with geologists to ensure that the correct sample was submitted.
· If this is the case, the laboratory is notified, and the batch is re-analyzed and re-reported. If no failures are noted, these analyses are transferred into the QA/QC sheets and the final drilling database is updated with the non-QA/QC samples.
CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 35
11.5 Opinion on Adequacy

Sierra Metals completed a very limited QA/QC program consisting of field duplicate sampling during the first few years of its exploration drilling programs. Previous Technical Reports deemed the level of QA/QC consistent with industry best practices, but SRK cautions, based on its extensive experience, that this is not the case.

SRK is of the opinion, given the recent QA/QC results and comparison to the PV Lab, as well as the fact that Bolivar is a producing mine with a robust production history, that the quality of the analytical data is sufficient to report Mineral Resources in the Indicated and Inferred categories.

SRK strongly advises Sierra Metals to continue supporting ongoing QA/QC monitoring and to implement the use of additional controls including coarse blanks, twin samples, fine and coarse duplicates, and a second lab control using a certified laboratory. It is necessary to clearly document the procedures and methods for actions taken in the event of failures.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 36
12 Data Verification
12.1 Procedures

SRK was provided with analytical certificates from ALS to facilitate validation of the assay database used for this MRE. SRK reviewed and cross-checked a subset of the total number of certificates (approximately 15%) and found no inconsistencies with the database. SRK has conducted similar validation exercises for previous MRE updates conducted since 2017.

In addition, SRK, Gustavson and RPA have conducted other means of data validation in previous reports and found the data to be sufficient in terms of accuracy for use at those times.

12.2 Limitations

SRK did not review 100% of the analyses from the analytical certificates during data validation for the MRE used in this report. In addition, SRK reviewed analyses from certificates that may have been previously vetted as part of past audits.

12.3 Opinion on Data Adequacy

SRK is of the opinion that the data provided are adequate for estimation of Mineral Resources.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 37
13 Mineral Processing and Metallurgical Testing

Bolivar's Piedras Verdes copper processing plant has been in operation since late 2011. Prior to late 2011, no processing facilities were available on site, and the ore was trucked to the Cusi Mine's Malpaso Mill located 270 km by road.

Bolivar's Piedras Verdes processing facilities started operating in October 2011 at 1,000 tpd of nominal throughput. The ore processing capacity was expanded to 2,000 tpd in mid-2013. The mill has been upgraded since and the current actual throughput is approaching 3,800 tpd.

Piedras Verdes Copper Plant operates a conventional crushing, ball mill grinding, flotation, thickening of concentrates, filtration of concentrates, and tailings disposal. The flotation area can be seen in Figure 13-1 and the current process flowsheet for copper is shown in Figure 13-2.

Bolivar is also planning to install a magnetic separation circuit to recover magnetite from both flotation tailings and existing old tailings. Piedras Verdes is consistently producing copper concentrate of commercial quality. The copper concentrate's average assays for 2019 Q4 were 25% Cu, 570 g/t Ag, and 6.8 g/t Au.

Source: SRK, 2020

Figure 13-1: The Piedras Verdes Processing Plant's Flotation Area

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 38

Source: Sierra Metals, 2020

Figure 13-2: Piedras Verdes Flowsheet

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 39
13.1 Testing and Procedures

The Bolivar Mine's facilities include a metallurgical laboratory at the site. Sampling and testing of samples for copper and magnetite are performed on an as-needed basis, considering current and future mining areas. The main mining areas are:

· El Gallo Inferior
· El Salto (continuation of El Gallo Inferior)
· Bolivar West
· Bolivar North West

Additionally, a metallurgical testing campaign was started approximately in 2017 to assess the commercial viability of producing iron ore concentrates. The magnetite recovery project is proposing to reprocess old tailings simultaneously with fresh flotation tailings on a multi-stage magnetic drum recovery plant to produce a magnetite concentrate of commercial quality. Samples for metallurgical testing were obtained from the existing tailings storage facility, the current flotation tails stream, and from future minable zones of the deposit.

The metallurgical testing campaign evaluated multiple slurry conditions and magnetic concentration stages at Bolivar's onsite laboratory and pilot plant built for this purpose, and by third-party vendors at their own facilities. A summary of all test results available (disregarding the actual scale or testing conditions) is presented in terms of metallurgical recovery and concentrate grades in Figure 13-3.

Source: SRK, 2021

Figure 13-3: Magnetite Testing - All Results

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 40

The initial results for the magnetite testing included Fe head grade ranging from approximately 5% to 28% and show a positive correlation with Fe recovery to concentrate which ranged from 40% to 85% approximately. The final magnetite concentrate's Fe grade ranged approximately from 25% to 70%.

13.2 Recovery Estimate Assumptions

Metal recovery for copper and silver showed a consistent improvement in the period July 2018 to December 2019 (18-months). Over the same period, gold recovery showed a minor downward trend. Recovery of solids into a concentrate (mass-pull) appears consistent ranging between 2.5% and 3.6%.

A comparison of the plant's performance shows that between 2018 Q4 and 2019 Q4:

· Copper recovery increased by 7%
· Silver recovery increased by 2%
· Gold recovery decreased by 3%
· Concentrate mass-pull increased to 3%

During 2019, Piedras Verdes consistently produced copper concentrate of commercial quality with copper grade ranging between 21.7% Cu to 28% Cu, silver content in concentrate ranging from 392 g/t Ag to 677 g/t Ag, and gold content in concentrate ranging from 3.2 g/t Au to 7.9 g/t Au. Average monthly metal recovery for copper, silver, and gold was 82.9%, 78.3% and 62.3%, respectively.

An additional correlation analysis between the key metallurgical variables suggests that recovery of copper correlates positively with ore throughput, and recovery of silver correlates positively with that of copper. All other correlations analysis between head grades, recoveries, and mass-pull showed no relationship among the parameters. Monthly production data for the Piedras Verdes processing plant in 2019 is shown in Figure 13-4.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 41

Source: SRK, 2020

Figure 13-4: Piedras Verdes Monthly Average Performance in 2019

Note: Totals may not match due to rounding.

These findings suggest potential substandard operational practices in the concentrator in the beginning of the period in question. Based on the more positive outcome towards the end of 2019, SRK is of the opinion that the Piedras Verdes processing plant has made major improvements that are reflected in the improved metallurgical performance shown in Figure 13-5.

Source: SRK, 2020

Figure 13-5: Copper Concentrate and Metal Recoveries

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 42
13.3 Analysis of Magnetite Testing

Sierra Metals requested SRK to produce a PEA level metallurgical recovery estimate for the Magnetite Recovery Plant Project being developed by its Bolivar mine. The Magnetite Recovery Plant Project is proposing to reprocess old tailings simultaneously with fresh flotation tailings on a multi-stage magnetic drum recovery plant to produce a magnetite concentrate of commercial quality.

Sierra Metals made available to SRK multiple sets of testwork data produced over a period of approximately 16 months starting March 2020. SRK identified a total of 106 distinctive valid data points, this is, those sets of data that allowed calculating iron recovery to a final concentrate, among those four outliers (Figure 13-3).

Samples for testing were obtained from the following:

· old tailings from the tailings storage facility
· flotation tails from the current operation
· samples from future minable zones of the deposit

The samples were tested under one or more of the following locations:

· in-house laboratory scale
· third party vendors at their own facilities
· a pilot plant installed on Bolivar's site

Conclusion from the analysis:

3. This analysis is valid within the head grade range of the available data which ranges from approximately a minimum of 5-28% Fe.
4. The recovery of iron to final concentrate shows a positive correlation with Fe head grade. A logarithmic curve can be approximated reasonably well with a correlation coefficient of R2=0.6 (Figure 13-3). On the lower end of the head grade, the logarithmic expression predicts iron recovery of 50% iron when the head grade is 5% Fe. In the upper end of the grade scale, the mathematical expression predicts 85% iron recovery when the head grade is 27.5% Fe.

Metal recovery of Fe can be reasonably estimated (at a PEA level) to be an average of 70% based on the following conditions:

1. It is necessary to evaluate the installation of regrinding mill ahead of the magnetic concentration stage. The regrind mill would likely improve liberation of the iron, as well as impurities, therefore allowing the multi-stage magnetic separation to produce a commercial quality iron concentrates in terms of iron grade and impurities content.
CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 43
2. Additional testwork is necessary to narrow down the target regrind P80. The available data suggests that achieving a grind size of 100% less than 100 micrometres should achieve the desired iron recovery and impurities content.
3. The magnetic concentration plant needs a multi-stage circuit with a minimum of three stages: a rougher stage followed by two cleaning stages, with tails from the cleaning stages being recirculated back to the rougher stage.
4. Bolivar needs to execute further magnetic separation tests on head grade variability for old tailings and "new" tailings from the future processing of ore. All these tests need to be carried out under a standard flowsheet as described previously.
CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 44

Table 13-1: Metallurgical Data Set

Data Source Date1 Operating
time, hours
Operating Shift Executed by Test type Feed, tms Feed Cu% Feed Zn% Feed Fe% Feed Metal Cu% Feed Metal Zn% Feed Metal Fe% Concentrate tms Concentrate Cu% Concentrate Zn% Concentrate Fe% Concentraate Metal Cu% Concentrate Metal Zn% Concentrate Metal Fe% Recovery Cu% Recovery Zn% Recovery Fe% Recovery Fe% (outliers)
Balance Concentracion Magnetica 01-03-20 1 Dia Bras Mexicana Piloto 152.15 0.123 0.33 11.28 0 1 17 18.18 0.07 0.072 53 0.01 0.01 9.63 7% 3% 56.1 %
Balance Concentracion Magnetica 02-03-20 1 Dia Bras Mexicana Piloto 173.89 0.221 0.249 17.4 0 0 30 38.38 0.22 0.103 55.3 0.08 0.04 21.22 22% 9% 70.2 %
Balance Concentracion Magnetica 03-03-20 1 Dia Bras Mexicana Piloto 0 0 0 0 0 0 0 0 0 0 0 0 0 0% 0% 0.0 %
Balance Concentracion Magnetica 04-03-20 1 Dia Bras Mexicana Piloto 0 0 0 0 0 0 0 0 0 0 0 0 0 0% 0% 0.0 %
Balance Concentracion Magnetica 05-03-20 1 Dia Bras Mexicana Piloto 86.94 0.119 0.128 15.09 0 0 13 16.28 0.22 0.066 57.2 0.04 0.01 9.31 35% 10% 71.0 %
Balance Concentracion Magnetica 06-03-20 1 Dia Bras Mexicana Piloto 195.62 0.105 0.267 12.05 0 1 24 22.51 0.05 0.081 60.11 0.01 0.02 13.53 6% 3% 57.4 %
Balance Concentracion Magnetica 07-03-20 1 Dia Bras Mexicana Piloto 130.42 0.08 0.49 11.64 0 1 15 11.62 0.1 0.2 58.88 0.01 0.02 6.84 11% 4% 45.1 %
Balance Concentracion Magnetica 08-03-20 1 Dia Bras Mexicana Piloto 0 0 0 0 0 0 0 0 0 0 0 0 0 0% 0% 0.0 %
Balance Concentracion Magnetica 09-03-20 1 Dia Bras Mexicana Piloto 0 0 0 0 0 0 0 0 0 0 0 0 0 0% 0% 0.0 %
Balance Concentracion Magnetica 10-03-20 1 Dia Bras Mexicana Piloto 173.89 0.138 0.084 11.68 0 0 20 15.59 0.07 0.067 60.3 0.01 0.01 9.4 4% 7% 46.3 %
Balance Concentracion Magnetica 11-03-20 1 Dia Bras Mexicana Piloto 217.36 0.26 0.1 16.32 1 0 35 44.23 0.18 0.07 59.65 0.08 0.03 26.38 14% 14% 74.4 %
Balance Concentracion Magnetica 12-03-20 1 Dia Bras Mexicana Piloto 0 0 0 0 0 0 0 0 0 0 0 0 0 0% 0% 0.0 %
Balance Concentracion Magnetica 13-03-20 1 Dia Bras Mexicana Piloto 0 0 0 0 0 0 0 0 0 0 0 0 0 0% 0% 0.0 %
Balance Concentracion Magnetica 14-03-20 1 Dia Bras Mexicana Piloto 0 0 0 0 0 0 0 0 0 0 0 0 0 0% 0% 0.0 %
Balance Concentracion Magnetica 15-03-20 1 Dia Bras Mexicana Piloto 0 0 0 0 0 0 0 0 0 0 0 0 0 0% 0% 0.0 %
Balance Concentracion Magnetica 16-03-20 1 Dia Bras Mexicana Piloto 0 0 0 0 0 0 0 0 0 0 0 0 0 0% 0% 0.0 %
Balance Concentracion Magnetica 17-03-20 1 Dia Bras Mexicana Piloto 0 0 0 0 0 0 0 0 0 0 0 0 0 0% 0% 0.0 %
Balance Concentracion Magnetica 18-03-20 1 Dia Bras Mexicana Piloto 0 0 0 0 0 0 0 0 0 0 0 0 0 0% 0% 0.0 %
Balance Concentracion Magnetica 19-03-20 1 Dia Bras Mexicana Piloto 152.15 0.247 0 13.05 0 0 20 21.52 0.14 0 63 0.03 0 13.56 8% 0% 68.3 %
Balance Concentracion Magnetica 20-03-20 1 Dia Bras Mexicana Piloto 239.09 0.14 0 10.31 0 0 25 25.03 0.67 0 61.72 0.17 0 15.45 50% 0% 62.7 %
Balance Concentracion Magnetica 21-03-20 1 Dia Bras Mexicana Piloto 195.62 0.33 0 10.44 1 0 20 16.79 0.22 0 60.92 0.04 0 10.23 6% 0% 50.1 %
Balance Concentracion Magnetica 22-03-20 1 Dia Bras Mexicana Piloto 260.83 0.34 0 15.08 1 0 39 43.92 0.28 0 59.92 0.12 0 26.32 14% 0% 66.9 %
Balance Concentracion Magnetica 23-03-20 1 Dia Bras Mexicana Piloto 0 0 0 0 0 0 0 0 0 0 0 0 0 0% 0% 0.0 %
Balance Concentracion Magnetica 24-03-20 1 Dia Bras Mexicana Piloto 217.36 0.19 0 10.22 0 0 22 22.8 0.22 0 55.61 0.05 0 12.68 12% 0% 57.1 %
Balance Concentracion Magnetica 25-03-20 1 Dia Bras Mexicana Piloto 0 0 0 0 0 0 0 0 0 0 0 0 0 0% 0% 0.0 %
CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 45
Data Source Date1 Operating
time, hours
Operating Shift Executed by Test type Feed, tms Feed Cu% Feed Zn% Feed Fe% Feed Metal Cu% Feed Metal Zn% Feed Metal Fe% Concentrate tms Concentrate Cu% Concentrate Zn% Concentrate Fe% Concentraate Metal Cu% Concentrate Metal Zn% Concentrate Metal Fe% Recovery Cu% Recovery Zn% Recovery Fe% Recovery Fe% (outliers)
Balance Concentracion Magnetica 26-03-20 1 Dia Bras Mexicana Piloto 195.62 0.26 0 7.86 1 0 15 14.63 0.18 0 55.61 0.03 0 8.14 5% 0% 52.9 %
Balance Concentracion Magnetica 27-03-20 1 Dia Bras Mexicana Piloto 108.68 0.12 0 13.46 0 0 15 12.02 0.1 0 61.4 0.01 0 7.38 9% 0% 50.4 %
Balance Concentracion Magnetica 28-03-20 1 Dia Bras Mexicana Piloto 195.62 0.16 0 8.23 0 0 16 11.28 0.12 0 61 0.01 0 6.88 4% 0% 42.8 %
Balance Concentracion Magnetica 29-03-20 1 Dia Bras Mexicana Piloto 130.42 0.154 0 8.2 0 0 11 9.8 0.18 0 58.64 0.02 0 5.75 9% 0% 53.8 %
Balance Concentracion Magnetica 30-03-20 1 Dia Bras Mexicana Piloto 152.15 0.038 0 11.16 0 0 17 9.76 0.1 0 59.67 0.01 0 5.83 16% 0% 34.3 %
Balance Concentracion Magnetica 31-03-20 1 Dia Bras Mexicana Piloto 173.89 0.115 0 12.19 0 0 21 25.35 0.29 0 54.25 0.07 0 13.75 37% 0% 64.9 %
Balance Concentracion Magnetica 01-03-20 2 Dia Bras Mexicana Piloto 0 0 0 0 0 0 0 0 0 0 0 0 0 0% 0% 0.0 %
Balance Concentracion Magnetica 02-03-20 2 Dia Bras Mexicana Piloto 0 0 0 0 0 0 0 0 0 0 0 0 0 0% 0% 0.0 %
Balance Concentracion Magnetica 03-03-20 2 Dia Bras Mexicana Piloto 0 0 0 0 0 0 0 0 0 0 0 0 0 0% 0% 0.0 %
Balance Concentracion Magnetica 04-03-20 2 Dia Bras Mexicana Piloto 0 0 0 0 0 0 0 0 0 0 0 0 0 0% 0% 0.0 %
Balance Concentracion Magnetica 05-03-20 2 Dia Bras Mexicana Piloto 0 0 0 0 0 0 0 0 0 0 0 0 0 0% 0% 0.0 %
Balance Concentracion Magnetica 06-03-20 2 Dia Bras Mexicana Piloto 0 0 0 0 0 0 0 0 0 0 0 0 0 0% 0% 0.0 %
Balance Concentracion Magnetica 07-03-20 2 Dia Bras Mexicana Piloto 108.68 0.15 0.13 11.23 0 0 12 9.86 0.17 0.1 58.32 0.02 0.01 5.75 10% 7% 47.1 %
Balance Concentracion Magnetica 08-03-20 2 Dia Bras Mexicana Piloto 173.89 0.1 0.39 11.43 0 1 20 18.86 0.15 0.2 58.03 0.03 0.04 10.95 16% 6% 55.1 %
Balance Concentracion Magnetica 09-03-20 2 Dia Bras Mexicana Piloto 130.42 0.12 0.3 12.18 0 0 16 17.65 0.08 0.1 58.89 0.01 0.02 10.39 9% 5% 65.4 %
Balance Concentracion Magnetica 10-03-20 2 Dia Bras Mexicana Piloto 0 0 0 0 0 0 0 0 0 0 0 0 0 0% 0% 0.0 %
Balance Concentracion Magnetica 11-03-20 2 Dia Bras Mexicana Piloto 130.42 0.24 0.15 18.9 0 0 25 32.92 0.15 0.09 60.01 0.05 0.03 19.75 16% 15% 80.1 %
Balance Concentracion Magnetica 12-03-20 2 Dia Bras Mexicana Piloto 0 0 0 0 0 0 0 0 0 0 0 0 0 0% 0% 0.0 %
Balance Concentracion Magnetica 13-03-20 2 Dia Bras Mexicana Piloto 0 0 0 0 0 0 0 0 0 0 0 0 0 0% 0% 0.0 %
Balance Concentracion Magnetica 14-03-20 2 Dia Bras Mexicana Piloto 0 0 0 0 0 0 0 0 0 0 0 0 0 0% 0% 0.0 %
Balance Concentracion Magnetica 15-03-20 2 Dia Bras Mexicana Piloto 0 0 0 0 0 0 0 0 0 0 0 0 0 0% 0% 0.0 %
Balance Concentracion Magnetica 16-03-20 2 Dia Bras Mexicana Piloto 0 0 0 0 0 0 0 0 0 0 0 0 0 0% 0% 0.0 %
Balance Concentracion Magnetica 17-03-20 2 Dia Bras Mexicana Piloto 0 0 0 0 0 0 0 0 0 0 0 0 0 0% 0% 0.0 %
Balance Concentracion Magnetica 18-03-20 2 Dia Bras Mexicana Piloto 0 0 0 0 0 0 0 0 0 0 0 0 0 0% 0% 0.0 %
Balance Concentracion Magnetica 19-03-20 2 Dia Bras Mexicana Piloto 195.62 0.15 0 12 0 0 23 27.04 0.1 0 60 0.03 0 16.23 9% 0% 69.1 %
CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 46
Data Source Date1 Operating
time, hours
Operating Shift Executed by Test type Feed, tms Feed Cu% Feed Zn% Feed Fe% Feed Metal Cu% Feed Metal Zn% Feed Metal Fe% Concentrate tms Concentrate Cu% Concentrate Zn% Concentrate Fe% Concentraate Metal Cu% Concentrate Metal Zn% Concentrate Metal Fe% Recovery Cu% Recovery Zn% Recovery Fe% Recovery Fe% (outliers)
Balance Concentracion Magnetica 20-03-20 2 Dia Bras Mexicana Piloto 239.09 0.19 0 12.11 0 0 29 31.13 0.16 0 60.47 0.05 0 18.83 11% 0% 65.0 %
Balance Concentracion Magnetica 21-03-20 2 Dia Bras Mexicana Piloto 217.36 0.29 0 13.32 1 0 29 36.35 0.26 0 56.14 0.09 0 20.41 15% 0% 70.5 %
Balance Concentracion Magnetica 22-03-20 2 Dia Bras Mexicana Piloto 108.68 0.31 0 12.36 0 0 13 15.53 0.24 0 58.2 0.04 0 9.04 11% 0% 67.3 %
Balance Concentracion Magnetica 23-03-20 2 Dia Bras Mexicana Piloto 0 0 0 0 0 0 0 0 0 0 0 0 0 0% 0% 0.0 %
Balance Concentracion Magnetica 24-03-20 2 Dia Bras Mexicana Piloto 0 0 0 0 0 0 0 0 0 0 0 0 0 0% 0% 0.0 %
Balance Concentracion Magnetica 25-03-20 2 Dia Bras Mexicana Piloto 0 0 0 0 0 0 0 0 0 0 0 0 0 0% 0% 0.0 %
Balance Concentracion Magnetica 26-03-20 2 Dia Bras Mexicana Piloto 152.15 0.19 0 9.81 0 0 15 14.19 0.11 0 61.4 0.02 0 8.71 5% 0% 58.4 %
Balance Concentracion Magnetica 27-03-20 2 Dia Bras Mexicana Piloto 86.94 0.22 0 12.68 0 0 11 11.65 0.13 0 57.14 0.02 0 6.66 8% 0% 60.4 %
Balance Concentracion Magnetica 28-03-20 2 Dia Bras Mexicana Piloto 152.15 0.212 0 8.26 0 0 13 10.31 0.11 0 60 0.01 0 6.18 4% 0% 49.2 %
Balance Concentracion Magnetica 29-03-20 2 Dia Bras Mexicana Piloto 173.89 0.197 0 9.58 0 0 17 15.09 0.3 0 57.78 0.04 0 8.72 13% 0% 52.3 %
Balance Concentracion Magnetica 30-03-20 2 Dia Bras Mexicana Piloto 207.85 0.107 0 11.71 0 0 24 25.56 0.18 0 59 0.05 0 15.08 21% 0% 62.0 %
Balance Concentracion Magnetica 31-03-20 2 Dia Bras Mexicana Piloto 166.11 0.115 0 11.19 0 0 19 20.84 0.36 0 54.25 0.07 0 11.31 39% 0% 60.8 %
Balance Planta Fe al 31-Jul 01-07-21 4.5 Dia Bras Mexicana Piloto 53.38 0.039 0.066 15.27 0 0 8 9.64 0.024 0.04 63.6 0 0 6.13 11% 11% 75.2 %
Balance Planta Fe al 31-Jul 02-07-21 6 Dia Bras Mexicana Piloto 65.54 0.209 0.038 16.15 0 0 11 13.26 0.017 0.123 59 0 0.02 7.83 2% 66% 73.9 %
Balance Planta Fe al 31-Jul 02-07-21 10.5 Dia Bras Mexicana Piloto 119.08 0.124 0.041 13.82 0 0 16 18.99 0.026 0.07 65.09 0 0.01 12.36 3% 27% 75.1 %
Balance Planta Fe al 31-Jul 04-07-21 7.5 Dia Bras Mexicana Piloto 84.71 0.224 0.063 18.46 0 0 16 18.3 0.029 0.073 64.17 0.01 0.01 11.74 3% 25% 75.1 %
Balance Planta Fe al 31-Jul 05-07-21 10.5 Dia Bras Mexicana Piloto 140.27 0.142 0.102 18.26 0 0 26 30.75 0.028 0.038 64.06 0.01 0.01 19.7 4% 8% 76.9 %
Balance Planta Fe al 31-Jul 06-07-21 10.5 Dia Bras Mexicana Piloto 131.89 0.164 0.07 15.36 0 0 20 24.07 0.036 0.059 65.31 0.01 0.01 15.72 4% 15% 77.6 %
Balance Planta Fe al 31-Jul 07-07-21 10.5 Dia Bras Mexicana Piloto 131.89 0.124 0.052 16.19 0 0 21 20.71 0.039 0.051 67.96 0.01 0.01 14.07 5% 15% 65.9 %
Balance Planta Fe al 31-Jul 08-07-21 9.5 Dia Bras Mexicana Piloto 119.33 0.171 0.054 10.21 0 0 12 15.06 0.035 0.069 56.38 0.01 0.01 8.49 3% 16% 69.7 %
Balance Planta Fe al 31-Jul 09-07-21 6.5 Dia Bras Mexicana Piloto 90.72 0.28 0.053 13.86 0 0 13 14.14 0.035 0.075 60.4 0 0.01 8.54 2% 22% 67.9 %
Balance Planta Fe al 31-Jul 10-07-21 10.5 Dia Bras Mexicana Piloto 131.89 0.27 0.126 18.01 0 0 24 30.29 0.044 0.117 64.14 0.01 0.04 19.43 4% 21% 81.8 %
Balance Planta Fe al 31-Jul 11-07-21 9 Dia Bras Mexicana Piloto 133 0.211 0.095 13.54 0 0 18 21.33 0.037 0.097 62.54 0.01 0.02 13.34 3% 16% 74.1 %
Balance Planta Fe al 31-Jul 12-07-21 9 Dia Bras Mexicana Piloto 119 0.181 0.082 16.45 0 0 20 22.4 0.039 0.1 63.63 0.01 0.02 14.25 4% 23% 72.8 %
Balance Planta Fe al 31-Jul 13-07-21 10 Dia Bras Mexicana Piloto 130.85 0.292 0.075 14.38 0 0 19 21.66 0.049 0.092 60.91 0.01 0.02 13.19 3% 20% 70.1 %
CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 47
Data Source Date1 Operating
time, hours
Operating Shift Executed by Test type Feed, tms Feed Cu% Feed Zn% Feed Fe% Feed Metal Cu% Feed Metal Zn% Feed Metal Fe% Concentrate tms Concentrate Cu% Concentrate Zn% Concentrate Fe% Concentraate Metal Cu% Concentrate Metal Zn% Concentrate Metal Fe% Recovery Cu% Recovery Zn% Recovery Fe% Recovery Fe% (outliers)
Balance Planta Fe al 31-Jul 14-07-21 10 Dia Bras Mexicana Piloto 119.73 0.275 0.081 16.08 0 0 19 20.58 0.042 0.076 66.56 0.01 0.02 13.7 3% 16% 71.2 %
Balance Planta Fe al 31-Jul 15-07-21 10 Dia Bras Mexicana Piloto 108.16 0.178 0.093 21.75 0 0 24 30.3 0.044 0.066 63.71 0.01 0.02 19.31 7% 20% 82.1 %
Balance Planta Fe al 31-Jul 16-07-21 6.5 Dia Bras Mexicana Piloto 70.31 0.131 0.066 20.45 0 0 14 18.66 0.051 0.097 60 0.01 0.02 11.2 10% 39% 77.9 %
Balance Planta Fe al 31-Jul 17-07-21 7.5 Dia Bras Mexicana Piloto 99.15 0.115 0.05 12.71 0 0 13 10.25 0.031 0.043 66.23 0 0 6.79 3% 9% 53.9 %
Balance Planta Fe al 31-Jul 19-07-21 10 Dia Bras Mexicana Piloto 98.61 0.099 0.128 15.09 0 0 15 14.53 0.051 0.025 66.46 0.01 0 9.66 8% 3% 64.9 %
Balance Planta Fe al 31-Jul 20-07-21 10.5 Dia Bras Mexicana Piloto 124.93 0.09 0.186 14.17 0 0 18 18.52 0.065 0.064 66.68 0.01 0.01 12.35 11% 5% 69.7 %
Balance Planta Fe al 31-Jul 21-07-21 10.5 Dia Bras Mexicana Piloto 118.98 0.178 0.127 15.73 0 0 19 20.26 0.028 0.097 67.31 0.01 0.02 13.64 3% 13% 72.9 %
Balance Planta Fe al 31-Jul 22-07-21 6.5 Dia Bras Mexicana Piloto 77.34 0.302 0.267 9.9 0 0 8 6.18 0.04 0.048 69.51 0 0 4.3 1% 1% 56.1 %
Balance Planta Fe al 31-Jul 23-07-21 10.5 Dia Bras Mexicana Piloto 146.11 0.283 0.188 14.16 0 0 21 21.81 0.06 0.094 64.2 0.01 0.02 14 3% 7% 67.7 %
Balance Planta Fe al 31-Jul 24-07-21 4 Dia Bras Mexicana Piloto 50.63 0.288 0.092 12.1 0 0 6 5.58 0.056 0.082 66.27 0 0 3.7 2% 10% 60.4 %
Balance Planta Fe al 31-Jul 25-07-21 10.5 Dia Bras Mexicana Piloto 118.98 0.149 0.09 11.61 0 0 14 13.46 0.03 0.014 63.62 0 0 8.56 2% 2% 62.0 %
Balance Planta Fe al 31-Jul 26-07-21 9.5 Dia Bras Mexicana Piloto 113.03 0.118 0.07 15.26 0 0 17 19.76 0.03 0.071 64.73 0.01 0.01 12.79 4% 18% 74.1 %
Balance Planta Fe al 31-Jul 27-07-21 8.5 Dia Bras Mexicana Piloto 107.59 0.127 0.13 12.45 0 0 13 14.31 0.034 0.023 67.13 0 0 9.61 4% 2% 71.7 %
Balance Planta Fe al 31-Jul 28-07-21 9 Dia Bras Mexicana Piloto 131.18 0.135 0.063 15.49 0 0 20 25.12 0.019 0.016 63.47 0 0 15.94 3% 5% 78.5 %
Balance Planta Fe al 31-Jul 29-07-21 10 Dia Bras Mexicana Piloto 140.8 0.14 0.054 12.17 0 0 17 17.75 0.02 0.037 65.15 0 0.01 11.56 2% 9% 67.5 %
Balance Planta Fe al 31-Jul 30-07-21 5 Dia Bras Mexicana Piloto 73.12 0.114 0.063 18.01 0 0 13 16.2 0.028 0.019 65.7 0 0 10.64 5% 7% 80.8 %
Balance Planta Fe al 31-Jul 31-07-21 9 Dia Bras Mexicana Piloto 122.27 0.116 0.054 16.27 0 0 20 23.22 0.027 0.02 64.65 0.01 0 15.01 4% 7% 75.5 %
Analisis Granulometricos Valorados 12-03-20 Dia Bras Mexicana Laboratorio 0.2 0.173 6.174 0.584 0.191 26.57 37.1 %
Analisis Granulometricos Valorados 12-03-20 Dia Bras Mexicana Laboratorio 0.377 0.327 9.411 0.519 0.166 41.77 57.3 %
Analisis Granulometricos Valorados 12-03-20 Dia Bras Mexicana Laboratorio 0.246 0.374 12.77 0.375 0.141 54.22 58.0 %
Analisis Granulometricos Valorados 12-03-20 Dia Bras Mexicana Laboratorio 0.145 0.38 16.46 0.127 0.094 59.54 60.6 %
Analisis Granulometricos Valorados 12-03-20 Dia Bras Mexicana Laboratorio 0.076 0.347 13.7 0.099 0.065 54.24 84.3 %
Analisis Granulometricos Valorados 12-03-20 Dia Bras Mexicana Laboratorio 0.046 0.289 14.64 0.065 0.041 46.89 85.4 %
Analisis Granulometricos Valorados 12-03-20 Dia Bras Mexicana Laboratorio 0.038 0.245 16.44 0.055 0.047 66.42 83.2 %
Analisis Granulometricos Valorados 12-03-20 Dia Bras Mexicana Laboratorio 0.06 0.174 17.77 0.036 0.034 66.37 71.8 %
CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 48
Data Source Date1 Operating
time, hours
Operating Shift Executed by Test type Feed, tms Feed Cu% Feed Zn% Feed Fe% Feed Metal Cu% Feed Metal Zn% Feed Metal Fe% Concentrate tms Concentrate Cu% Concentrate Zn% Concentrate Fe% Concentraate Metal Cu% Concentrate Metal Zn% Concentrate Metal Fe% Recovery Cu% Recovery Zn% Recovery Fe% Recovery Fe% (outliers)
Balance de Planta de Hierro abril 2021 09-04-21 Dia Bras Mexicana Piloto 6.59 0 0.03 17.47 0 0 1 1.14 0 0.054 66.15 0 0 0.76 0% 30% 65.6 %
Balance de Planta de Hierro abril 2021 15-04-21 Dia Bras Mexicana Piloto 6.59 0.08 0.05 16.23 0 0 1 1.12 0.077 0.05 64.12 0 0 0.72 17% 17% 66.8 %
Balance de Planta de Hierro abril 2021 19-04-21 Dia Bras Mexicana Piloto 9.89 0.23 0.12 10.35 0 0 1 0.89 0.022 0.045 61.36 0 0 0.55 1% 3% 53.4 %
Balance de Planta de Hierro abril 2021 22-04-21 Dia Bras Mexicana Piloto 9.89 0.26 0.15 18.67 0 0 2 1.85 0.26 0.02 69.67 0 0 1.29 19% 2% 69.9 %
Balance de Planta de Hierro abril 2021 23-04-21 Dia Bras Mexicana Piloto 9.89 0.16 0.15 17.75 0 0 2 1.79 0.256 0.026 70.18 0 0 1.26 29% 3% 71.5 %
Balance de Planta de Hierro abril 2021 24-04-21 Dia Bras Mexicana Piloto 9.89 0.82 0.07 19.42 0 0 2 2.02 0.26 0.016 65.55 0.01 0 1.32 6% 5% 68.8 %
Balance de Planta de Hierro abril 2021 26-04-21 Dia Bras Mexicana Piloto 9.89 0.14 0.03 21.25 0 0 2 2.56 0.099 0.012 66.4 0 0 1.7 18% 10% 80.9 %
Balance de Planta de Hierro abril 2021 28-04-21 Dia Bras Mexicana Piloto 9.89 0.59 0.04 19.97 0 0 2 1.08 0.378 0.029 70.4 0 0 0.76 7% 8% 38.7 %
DT Results Summary-Davis 30-06-21 SGS Lakefield Laboratorio
DT Results Summary-Davis 30-06-21 SGS Lakefield Laboratorio
DT Results Summary-Davis 30-06-21 SGS Lakefield Laboratorio
DT Results Summary-Davis 30-06-21 SGS Lakefield Laboratorio
DT Results Summary-Davis 30-06-21 SGS Lakefield Laboratorio
DT Results Summary-Davis 30-06-21 SGS Lakefield Laboratorio 21.8 65.4 76.2 %
DT Results Summary-Davis 30-06-21 SGS Lakefield Laboratorio 22.3 65 72.2 %
DT Results Summary-Davis 30-06-21 SGS Lakefield Laboratorio 23.53 65 78.8 %
DT Results Summary-Davis 30-06-21 SGS Lakefield Laboratorio 22.18 65.6 76.8 %
DT Results Summary-Davis 30-06-21 SGS Lakefield Laboratorio 20.83 64.6 74.7 %
DT Results Summary-Davis 30-06-21 SGS Lakefield Laboratorio 27.34 65.6 80.1 %
DT Results Summary-Davis 30-06-21 SGS Lakefield Laboratorio 26.56 64.8 79.8 %
DT Results Summary-Davis 30-06-21 SGS Lakefield Laboratorio 27.13 65.3 80.8 %
DT Results Summary-Davis 30-06-21 SGS Lakefield Laboratorio 27.56 64.3 80.0 %
DT Results Summary-Davis 30-06-21 SGS Lakefield Laboratorio 26.8 65 80.1 %
Sierra Metals, Magnetite Projects, Metallurgical Support (by Augusto Chang) 09-04-21 Eriez Piloto 17.47 66.15 65.8 %
Sierra Metals, Magnetite Projects, Metallurgical Support (by Augusto Chang) 15-04-21 Eriez Piloto 16.23 64.12 67.0 %
CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 49
Data Source Date1 Operating
time, hours
Operating Shift Executed by Test type Feed, tms Feed Cu% Feed Zn% Feed Fe% Feed Metal Cu% Feed Metal Zn% Feed Metal Fe% Concentrate tms Concentrate Cu% Concentrate Zn% Concentrate Fe% Concentraate Metal Cu% Concentrate Metal Zn% Concentrate Metal Fe% Recovery Cu% Recovery Zn% Recovery Fe% Recovery Fe% (outliers)
Sierra Metals, Magnetite Projects, Metallurgical Support (by Augusto Chang) 19-04-21 Eriez Piloto 10.35 61.36 57.0 %
Sierra Metals, Magnetite Projects, Metallurgical Support (by Augusto Chang) 22-04-21 Eriez Piloto 18.67 69.67 70.6 %
Sierra Metals, Magnetite Projects, Metallurgical Support (by Augusto Chang) 23-04-21 Eriez Piloto 17.75 70.18 72.2 %
Sierra Metals, Magnetite Projects, Metallurgical Support (by Augusto Chang) 24-04-21 Eriez Piloto 19.42 65.55 71.7 %
Sierra Metals, Magnetite Projects, Metallurgical Support (by Augusto Chang) 26-04-21 Eriez Piloto 21.25 66.4 81.4 %
Sierra Metals, Magnetite Projects, Metallurgical Support (by Augusto Chang) 08-04-21 Eriez Piloto 19.97 70.4 44.24% 44.2 %
Sierra Metals, Magnetite Projects, Metallurgical Support (by Augusto Chang) na Eriez Laboratorio 0.26 0.13 19.25
SierraMetals-Bolivar-SIERRA METALS_DIABRAS MEXICO_Report MTR 20 182_2020_Sample 527118 30-10-20 Eriez Laboratorio 61.5 84.8 %
SierraMetals-Bolivar-SIERRA METALS_DIABRAS MEXICO_Report MTR 20 182_2020_Sample 527119 30-10-20 Eriez Laboratorio 59.7 82.4 %
SierraMetals-Bolivar-SIERRA METALS_DIABRAS MEXICO_Report MTR 19-023_2019_ Samples 19445 30-10-20 Eriez Laboratorio 24.93 33.6 %
Sierra Metals, Magnetite Projects, Metallurgical Support (by Augusto Chang) na Eriez Piloto 13.28 60.23 71.3 %
Sierra Metals, Magnetite Projects, Metallurgical Support (by Augusto Chang) na Eriez Piloto 12.14 62.64 81.1 %
Sierra Metals, Magnetite Projects, Metallurgical Support (by Augusto Chang) na Eriez Piloto 11.69 60.79 61.3 %
Sierra Metals, Magnetite Projects, Metallurgical Support (by Augusto Chang) na Eriez Piloto 11.48 60.27 69.4 %
Sierra Metals, Magnetite Projects, Metallurgical Support (by Augusto Chang) na Eriez Piloto 11.5 56.4 69.3 %
Sierra Metals, Magnetite Projects, Metallurgical Support (by Augusto Chang) na Eriez Piloto 12.02 60.07 71.3 %
Sierra Metals, Magnetite Projects, Metallurgical Support (by Augusto Chang) na Sierra Metals Piloto 12.905 66 95.86% 95.86%
Sierra Metals, Magnetite Projects, Metallurgical Support (by Augusto Chang) na Sierra Metals Piloto 9.28 60.05
Sierra Metals, Magnetite Projects, Metallurgical Support (by Augusto Chang) na Sierra Metals Piloto 60.84
CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 50
14 Mineral Resource Estimates

Cliff Revering, PEng, of SRK (Canada) has conducted the Mineral Resource Estimate (MRE) as described herein, and Glen Cole, PGeo, of SRK (Canada) has reviewed the mineral resource estimation process. Findlay Craig and Ron Uken of SRK (Canada) developed the geological and mineralization domain interpretation used within this MRE, SRK has relied on the general geological knowledge and interpretation of the Bolivar area provided by Sierra Metals to guide the model development for this Mineral Resource Estimate.

14.1 Drill hole and Channel Sample Database

Information supporting the MRE is derived from data obtained from exploration drilling and underground mine production supplied by Sierra Metals.

14.1.1 Drilling Database

The resource database is comprised of 994 diamond holes, totaling 259,748 m of drilling. The drilling data consists of approximately 25,920 copper, silver, gold, zinc and lead assays. Decisions as to whether an interval is sampled is made by site geological staff during logging of the drill core. Drilling history for the project has been documented since 2003. Drilling information from some older holes has either been lost or the type of drilling is not known. These holes have been removed from the database.

The database is maintained in Microsoft® Access and was provided as Microsoft® Excel files with collar information, hole orientation, geology logging, sample assay data and geotechnical data. A summary of drill holes completed by year is provided in Table 14-1 and drill hole size is provided in Table 14-2. Descriptive statistics for all drill hole sample assays are presented in Table 14-3.

Table 14-1: Bolivar Drilling History

Year Count Meters % of Total Meters
2003 1 202 0.1%
2004 93 15,770 6.1%
2005 70 12,360 4.8%
2006 61 9,959 3.8%
2007 96 21,841 8.4%
2008 95 20,826 8.0%
2009 43 5,643 2.2%
2010 28 3,736 1.4%
2011 26 6,574 2.5%
2012 40 13,032 5.0%
2013 27 11,402 4.4%
2014 30 5,830 2.2%
2015 75 18,342 7.1%
2016 51 16,585 6.4%
2017 102 40,244 15.5%
2018 70 28,022 10.8%
2019 86 29,382 11.3%
Total 994 259,748 100.0%

Source: SRK, 2020

Note: Totals may not match due to rounding.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 51

Table 14-2: Drilling Types

Hole Type Count Meters
Unknown 42 7,489
NQ 133 27,148
BTW 23 1,818
HQ_NQ 423 152,696
HQ 55 27,768
BQ 318 42,830
Total 994 259,748

Source: SRK 2020

Note: Totals may not match due to rounding.

Table 14-3: Sample Assay Descriptive Statistics - All Drilling (length weighted)

Column Count Min Max Mean Variance St. Dev. Coefficient of Variation
Au 22,435 0.0025 24.90 0.12 0.27 .52 4.33
Ag 25,920 0.0000 4,720.00 12.44 3323.34 57.65 4.63
Cu 25,920 0.0000 42.07 0.47 2.04 1.42 3.01
Pb 25,803 0.0001 8.05 0.02 0.01 0.11 6.72
Zn 25,920 0.0001 52.09 0.95 18.44 4.29 4.53

Source: SRK, 2020

14.1.2 Downhole Deviation

Of the 994 drill holes in the database, 295 have downhole deviation measurements. Almost all drill holes drilled since 2017 have been surveyed with downhole instruments including Deviflex and Reflex tools. Table 14-4 provides details on drill holes with downhole surveys per drilling campaign.

The deviation surveys show that the initial angle of the drill setup is frequently five or more degrees off the intended azimuth for holes drilled before 2016, and that subsequent surveys taken downhole vary significantly from the first, indicating substantial deviation. The survey deviations are not consistent within the measurement data and the results indicate that un-surveyed drill holes could be materially off the planned azimuth which is recorded into the database.

As previously observed by SRK, the average azimuth downhole deviation for these surveyed holes is highly variable, with some holes exhibiting very little deviation and others more than 15° over the course of the hole. Thus, SRK is of the opinion that downhole surveys should continue to be collected with the Deviflex equipment on a regular basis and used as a matter of course during all drilling campaigns.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 52

Table 14-4: Drill Hole Downhole Survey Details

Drilling Campaign Year Number of Holes Drilled Number of Holes Surveyed
2003 1 0
2004 93 0
2005 70 0
2006 61 0
2007 96 0
2008 95 0
2009 43 0
2010 28 0
2011 26 0
2012 40 0
2013 27 8
2014 30 0
2015 75 20
2016 51 30
2017 102 91
2018 70 66
2019 86 80
Total 994 295

Source: SRK, 2020

14.1.3 Missing and Unsampled Intervals

The handling of missing and unsampled intervals for the Bolivar data is critical for mineral resource estimation. There are many cases where samples are not present in the database for significant thicknesses, or for the entire drill hole. In most cases this is because the geologist logging the drill hole did not note mineralization or material of interest, and therefore did not sample the interval. However, there were other factors that may have contributed to intervals not having assay results. Some assays have been lost or deemed of too low confidence by Dia Bras to include in the MRE; others are partial analyses, meaning that Cu was analyzed but not Au. For example, there are approximately 3,500 less Au analyses compared to Cu, which is a function of the analytical capability of the Piedras Verdes lab prior to installation of a fire assay circuit. SRK is of the opinion that for areas where Au was not analyzed or is missing, there may be additional upside potential within the mineral resource.

In a select few obvious cases, SRK advised Dia Bras (prior to this work) that they should sample those intervals that clearly should cross the mineralized body based on other nearby drilling or sampling. Dia Bras did this and submitted modern QA/QC along with the selection of samples to effectively "infill" most of these areas.

In general, due to uncertainties associated with missing or unsampled intervals, SRK has assigned a value of "0" to all missing or unsampled intervals.

14.2 Geological Model

Geology and mineralization models were constructed in 3D to serve as limits and guides for interpolation of grades for the MRE.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 53
14.2.1 Bolivar Area Mineralization

An initial mineralization model for the Bolivar deposit was provided by Sierra Metals in September 2019. This was subsequently revised by SRK to incorporate additional exploration drilling conducted in Q4 2019, as well as incorporate revisions to the geological model and the cut-off grade used to define the extents of mineralization.

The revised mineralization model developed to support the 2019 year-end mineral resource estimate is comprised of four main areas of mineralization and thirty distinct zones of mineralization as depicted in Figure 14-1 and summarized in Table 14-5. Volumetrically, the EGI area is the most significant and has been the main source of mine production since 2007. All volumes reported in Table 14-5 reflect the total volume of the interpreted models and have not been adjusted for mine depletion.

As discussed in Section 7 of this report, the dominant lithological contact controlling mineralization at Bolivar is the Piedras Verde Granodiorite with the majority of mineralization located in close proximity to this lithological unit (Figure 14-2). A cut-off grade of approximately 0.42% equivalent copper (Cu-Eq) has been used to define the mineralized zones at Bolivar, based on a metal value cut-off of US$24.25/t. Further details of cut-off criteria for mineral resource estimation are provided in Section 14.10.

Source: SRK, 2020

Figure 14-1: December 2019 Mineralization Model for Bolivar

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 54

Table 14-5: Bolivar Mineralization Domains and Codes

Domain Domain Code Volume (m3)
EGI 110 8,207,490
EGI_2 120 31,315
EGI_3 130 577,516
EGI_4 140 35,349
EGI_5 150 119,861
EGI_6 160 95,453
CHIMINEA_1 210 326,742
CHIMINEA_2 220 856,948
BNW_1 310 398,728
BNW_2 320 275,464
BNW_3 330 13,815
BNW_4 340 2,492,726
BNW_5 350 67,961
BNW_6 360 78,155
BNW_7 370 480,318
BNW_8 380 12,238
BNW_9 390 1,061,601
SKARN_1 410 185,808
SKARN_2 420 94,434
SKARN_3 430 187,316
SKARN_4 440 448,826
B_W_A 510 246,577
B_W_B 520 164,667
B_W_C 530 862,355
B_W_D 540 458,584
B_W_E 550 308,282
BWW1 610 40,330
BWW2 620 115,476
BWW3 630 138,045
BWW4 640 140,641

Source: SRK, 2020

Note: volumes are not adjusted for mine depletion.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 55

Source: SRK, 2020

Figure 14-2: 3D View of Piedras Verde Granodiorite Relative to Mineralization Zones

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 56
14.3 Assay Sample Summary
14.3.1 Assay Sample Length

A total of 10,052 assay samples are located within the interpreted mineralized domains at Bolivar. Sample interval lengths are variable but were predominately sampled using 1.0 m to 1.5 m sample interval lengths. Further details are provided in Figure 14-3.

Source: SRK, 2020

Figure 14-3: Assay Sample Interval Summary Statistics

14.3.2 Assay Grade Summary

Sample analysis has typically consisted of assaying for Cu, Ag, Au, Zn, Pb, and Fe (total), however inclusion of Au, Fe and Pb was more inconsistent during historical drilling campaigns. The primary metals of economic interest currently incorporated into the MRE include Cu, Ag and Au, although total Fe content has also been estimated within the MRE. Summary assay statistics for the three primary metals, segregated by mineralized domain, are provided in Table 14-6 to Table 14-8.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 57

Table 14-6: Summary Assay Statistics for Cu (%)

Domain Domain
Code
# of Samples Avg. Sample Length (m) Cu_pct
(Mean)
Cu_pct
(StDev)
Cu_pct
(Min)
Cu_pct
(Max)
Cu_pct
(CV)
EGI 110 2656 1.13 0.73 568.01 0.00 8.79 778
EGI_2 120 53 1.12 1.43 596.42 0.06 3.78 417
EGI_3 130 486 1.17 1.17 845.38 0.00 12.70 724
EGI_4 140 66 0.98 0.58 347.12 0.01 7.20 601
EGI_5 150 125 1.05 1.81 1067.96 0.00 8.01 592
EGI_6 160 66 1.06 1.01 882.05 0.00 7.13 876
CHIMINEA_1 210 678 1.16 1.68 2042.93 0.00 27.50 1,217
CHIMINEA_2 220 802 1.20 0.67 885.27 0.00 19.90 1,316
BNW_1 310 140 1.17 1.16 986.90 0.00 4.24 853
BNW_2 320 121 1.21 0.90 666.25 0.00 12.15 742
BNW_3 330 12 1.22 0.55 200.62 0.00 3.27 365
BNW_4 340 546 1.19 0.57 421.72 0.00 5.78 737
BNW_5 350 17 1.01 1.31 525.68 0.14 2.85 401
BNW_6 360 21 1.16 0.84 638.52 0.00 3.35 758
BNW_7 370 116 1.14 0.60 348.08 0.00 3.55 584
BNW_8 380 5 1.42 0.57 152.22 0.35 0.77 267
BNW_9 390 113 1.31 1.06 511.63 0.00 5.56 483
SKARN_1 410 369 1.04 0.61 482.78 0.00 6.65 785
SKARN_2 420 366 1.27 0.65 2459.90 0.00 9.29 3,788
SKARN_3 430 533 1.17 1.20 1947.64 0.00 19.50 1,626
SKARN_4 440 1922 1.16 1.14 1465.53 0.00 28.30 1,289
B_W_A 510 107 1.36 1.05 484.72 0.00 7.60 460
B_W_B 520 97 1.30 0.65 365.17 0.00 6.75 561
B_W_C 530 374 1.30 1.37 1692.30 0.00 8.93 1,236
B_W_D 540 95 1.29 0.69 261.47 0.00 5.55 378
B_W_E 550 50 1.33 0.70 260.75 0.00 5.39 372
BWW1 610 12 1.42 0.83 149.61 0.34 1.34 181
BWW2 620 26 1.36 0.70 256.00 0.07 2.40 364
BWW3 630 35 1.42 1.36 492.37 0.36 4.35 361
BWW4 640 43 1.45 0.67 190.81 0.09 1.66 285

Source: SRK, 2020

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 58

Table 14-7: Summary Assay Statistics for Ag (g/t)

Domain Domain
Code
# of Samples Avg. Sample Length (m) Ag_g/t
(Mean)
Ag_g/t
(StDev)
Ag_g/t
(Min)
Ag_g/t
(Max)
Ag_g/t
(CV)
EGI 110 2656 1.13 12.70 12093.93 0.00 355.00 952
EGI_2 120 53 1.12 24.78 10883.03 0.50 88.00 439
EGI_3 130 486 1.17 31.70 35295.25 0.00 1850.00 1,113
EGI_4 140 66 0.98 8.34 3620.42 0.10 44.40 434
EGI_5 150 125 1.05 32.19 19352.23 0.10 184.00 601
EGI_6 160 66 1.06 25.84 24325.38 0.10 158.00 941
CHIMINEA_1 210 678 1.16 37.23 44419.30 0.00 582.00 1,193
CHIMINEA_2 220 802 1.20 25.95 129896.42 0.30 4720.00 5,006
BNW_1 310 140 1.17 66.79 69283.86 0.00 388.00 1,037
BNW_2 320 121 1.21 33.07 22682.78 0.00 285.00 686
BNW_3 330 12 1.22 20.24 9501.51 0.00 59.70 469
BNW_4 340 546 1.19 5.01 6321.40 0.00 90.00 1,261
BNW_5 350 17 1.01 31.52 13615.32 1.00 77.00 432
BNW_6 360 21 1.16 18.68 13225.66 0.50 82.00 708
BNW_7 370 116 1.14 9.21 5902.40 0.10 54.00 641
BNW_8 380 5 1.42 8.89 4545.70 1.60 15.90 511
BNW_9 390 113 1.31 14.85 7473.17 0.50 116.00 503
SKARN_1 410 369 1.04 23.85 17531.30 0.00 420.00 735
SKARN_2 420 366 1.27 40.11 248259.39 0.00 578.00 6,190
SKARN_3 430 533 1.17 18.56 22888.27 0.10 270.00 1,233
SKARN_4 440 1922 1.16 21.73 26516.55 0.00 1050.00 1,220
B_W_A 510 107 1.36 8.91 4597.73 0.00 166.00 516
B_W_B 520 97 1.30 15.30 10250.71 0.00 226.00 670
B_W_C 530 374 1.30 44.54 72269.99 0.00 669.00 1,623
B_W_D 540 95 1.29 9.78 4112.19 0.50 81.00 420
B_W_E 550 50 1.33 13.28 7212.01 0.00 272.00 543
BWW1 610 12 1.42 14.56 8836.72 1.00 47.00 607
BWW2 620 26 1.36 9.93 4409.94 1.00 27.00 444
BWW3 630 35 1.42 27.28 26013.89 2.00 291.00 954
BWW4 640 43 1.45 6.24 4682.54 0.50 39.00 750

Source: SRK, 2020

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 59

Table 14-8: Summary Assay Statistics for Au (g/t)

Domain Domain
Code
# of Samples Avg. Sample Length (m) Au_g/t
(Mean)
Au_g/t
(StDev)
Au_g/t
(Min)
Au_g/t
(Max)
Au_g/t
(CV)
EGI 110 2656 1.13 0.203 356.005 0.000 11.850 1,756
EGI_2 120 53 1.12 0.408 366.783 0.000 2.660 899
EGI_3 130 486 1.17 0.193 561.429 0.000 10.350 2,909
EGI_4 140 66 0.98 0.038 32.932 0.003 0.588 868
EGI_5 150 125 1.05 0.199 330.980 0.003 3.520 1,663
EGI_6 160 66 1.06 0.247 336.595 0.003 2.060 1,364
CHIMINEA_1 210 678 1.16 0.021 64.821 0.000 4.310 3,138
CHIMINEA_2 220 802 1.20 0.023 84.896 0.000 2.270 3,759
BNW_1 310 140 1.17 9.084 12821.545 0.000 24.900 1,412
BNW_2 320 121 1.21 0.832 1035.307 0.000 9.300 1,244
BNW_3 330 12 1.22 0.691 215.380 0.000 1.225 312
BNW_4 340 546 1.19 0.352 676.237 0.000 10.000 1,921
BNW_5 350 17 1.01 0.303 194.514 0.019 1.275 642
BNW_6 360 21 1.16 0.089 108.430 0.000 0.511 1,212
BNW_7 370 116 1.14 0.364 379.917 0.000 4.710 1,045
BNW_8 380 5 1.42 0.194 83.860 0.000 0.343 433
BNW_9 390 113 1.31 0.009 41.364 0.000 1.625 4,671
SKARN_1 410 369 1.04 0.198 172.367 0.000 5.870 871
SKARN_2 420 366 1.27 0.593 4171.019 0.000 9.610 7,038
SKARN_3 430 533 1.17 0.061 90.312 0.000 0.989 1,470
SKARN_4 440 1922 1.16 0.110 235.970 0.000 8.700 2,152
B_W_A 510 107 1.36 0.000 0.422 0.000 0.025 3,226
B_W_B 520 97 1.30 0.002 5.327 0.000 0.210 2,461
B_W_C 530 374 1.30 0.000 28.925 0.000 1.810 70,026
B_W_D 540 95 1.29 0.104 128.774 0.000 5.130 1,235
B_W_E 550 50 1.33 0.016 41.011 0.000 1.740 2,635
BWW1 610 12 1.42 0.127 63.990 0.000 0.349 504
BWW2 620 26 1.36 0.313 252.655 0.000 1.660 807
BWW3 630 35 1.42 0.670 631.892 0.000 5.140 942
BWW4 640 43 1.45 0.263 154.936 0.005 1.660 590

Source: SRK, 2020

14.3.3 Compositing

Assay sample intervals are composited to provide common support for statistical and geostatistical analysis, and for estimation of mineral resources. Sample intervals of 1.5 m and 2.0 m represent 90% and 98% of all sample lengths (Figure 14-3), therefore a composite length of 2.0 m was selected as an optimal compositing interval. Although larger compositing intervals may reduce the variability of the composited dataset, a smaller composite length may allow finer definition of the bedding parallel mineralization.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 60

Compositing was conducted within each domain independently. Composite intervals located along the margins of the mineralized domains smaller than 1.0m in length were incorporated into the adjacent composite intervals to remove any small residuals from the final composite data set. A summary of composite sample statistics is provided in Table 14-9 to Table 14-11.

Table 14-9: Composited Assay Summary Statistics for Cu (%)

Domain Domain
Code
# of Comps Cu_pct
(Mean)
Cu_pct
(StDev)
Cu_pct
(Min)
Cu_pct
(Max)
Cu_pct
(CV)
EGI 110 1736 0.65 0.72 0.00 5.90 1.11
EGI_2 120 37 1.22 0.83 0.00 3.78 0.68
EGI_3 130 311 1.07 1.28 0.00 7.40 1.20
EGI_4 140 36 0.48 0.38 0.00 1.75 0.81
EGI_5 150 66 1.56 1.17 0.00 5.40 0.75
EGI_6 160 39 0.75 1.05 0.00 5.91 1.41
CHIMINEA_1 210 459 1.28 2.66 0.00 23.20 2.08
CHIMINEA_2 220 506 0.54 0.69 0.00 5.03 1.28
BNW_1 310 90 0.81 0.66 0.00 3.41 0.82
BNW_2 320 91 0.76 1.08 0.00 7.68 1.43
BNW_3 330 11 0.55 0.51 0.00 1.74 0.93
BNW_4 340 318 0.63 0.53 0.00 2.75 0.84
BNW_5 350 15 0.69 0.62 0.00 1.75 0.89
BNW_6 360 13 0.71 0.72 0.00 2.59 1.02
BNW_7 370 69 0.61 0.51 0.01 2.23 0.84
BNW_8 380 5 0.60 0.16 0.40 0.77 0.27
BNW_9 390 74 1.02 0.94 0.00 4.63 0.92
SKARN_1 410 207 0.49 0.63 0.00 3.88 1.29
SKARN_2 420 208 0.62 0.87 0.00 6.25 1.40
SKARN_3 430 363 0.89 1.52 0.00 11.88 1.72
SKARN_4 440 1230 0.86 1.67 0.00 24.28 1.93
B_W_A 510 68 0.65 0.74 0.00 2.97 1.13
B_W_B 520 63 0.68 0.87 0.00 3.76 1.28
B_W_C 530 241 1.11 1.01 0.00 5.90 0.91
B_W_D 540 75 0.81 0.89 0.00 3.77 1.10
B_W_E 550 32 0.79 0.83 0.00 2.75 1.05
BWW1 610 9 0.85 0.27 0.39 1.33 0.32
BWW2 620 17 0.72 0.41 0.24 1.70 0.57
BWW3 630 25 1.37 0.73 0.46 3.33 0.54
BWW4 640 30 0.67 0.31 0.13 1.51 0.46

Source: SRK, 2020

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 61

Table 14-10: Composited Assay Summary Statistics for Ag (g/t)

Domain Domain
Code
# of Comps Ag_g/t
(Mean)
Ag_g/t
(StDev)
Ag_g/t
(Min)
Ag_g/t
(Max)
Ag_g/t
(CV)
EGI 110 1736 11.52 16.46 0.00 266.75 1.43
EGI_2 120 37 19.82 12.43 0.00 51.90 0.63
EGI_3 130 311 28.80 69.46 0.00 1089.00 2.41
EGI_4 140 36 7.67 5.23 0.00 19.74 0.68
EGI_5 150 66 29.51 19.60 0.23 92.41 0.66
EGI_6 160 39 19.04 26.74 0.00 103.34 1.40
CHIMINEA_1 210 459 28.64 57.00 0.00 512.05 1.99
CHIMINEA_2 220 506 20.41 139.24 0.00 2960.99 6.82
BNW_1 310 90 35.26 48.77 0.00 311.28 1.38
BNW_2 320 91 27.57 37.15 0.00 183.47 1.35
BNW_3 330 11 18.22 18.59 0.00 59.70 1.02
BNW_4 340 318 7.52 9.35 0.00 50.15 1.24
BNW_5 350 15 15.78 15.88 0.00 48.26 1.01
BNW_6 360 13 14.84 12.19 0.00 41.98 0.82
BNW_7 370 69 7.49 8.12 0.40 39.65 1.09
BNW_8 380 5 10.37 4.88 4.55 15.90 0.47
BNW_9 390 74 16.19 15.79 0.00 77.86 0.98
SKARN_1 410 207 19.18 28.59 0.00 210.10 1.49
SKARN_2 420 208 21.04 37.16 0.00 380.07 1.77
SKARN_3 430 363 15.16 19.94 0.00 206.55 1.32
SKARN_4 440 1230 18.24 33.33 0.00 610.58 1.83
B_W_A 510 68 10.32 14.11 0.00 84.46 1.37
B_W_B 520 63 19.01 27.18 0.00 113.89 1.43
B_W_C 530 241 34.93 52.21 0.00 425.64 1.49
B_W_D 540 75 10.58 12.28 0.00 52.10 1.16
B_W_E 550 32 15.89 19.34 0.00 75.88 1.22
BWW1 610 9 16.96 19.05 2.65 46.99 1.12
BWW2 620 17 10.11 7.32 1.27 26.59 0.72
BWW3 630 25 26.59 37.80 2.25 156.97 1.42
BWW4 640 30 5.80 6.88 0.50 25.19 1.19

Source: SRK, 2020

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 62

Table 14-11: Composited Assay Summary Statistics for Au (g/t)

Domain Domain
Code
# of Comps Au_g/t
(Mean)
Au_g/t
(StDev)
Au_g/t
(Min)
Au_g/t
(Max)
Au_g/t
(CV)
EGI 110 1736 0.169 0.385 0.000 6.005 2.28
EGI_2 120 37 0.327 0.432 0.000 1.647 1.32
EGI_3 130 311 0.178 0.810 0.000 10.300 4.56
EGI_4 140 36 0.037 0.060 0.000 0.308 1.63
EGI_5 150 66 0.163 0.311 0.003 1.929 1.90
EGI_6 160 39 0.167 0.316 0.000 1.231 1.89
CHIMINEA_1 210 459 0.024 0.120 0.000 2.210 4.99
CHIMINEA_2 220 506 0.022 0.106 0.000 1.667 4.86
BNW_1 310 90 0.638 1.288 0.000 8.977 2.02
BNW_2 320 91 0.485 1.116 0.000 7.114 2.30
BNW_3 330 11 0.479 0.513 0.000 1.225 1.07
BNW_4 340 318 0.460 0.635 0.000 4.894 1.38
BNW_5 350 15 0.166 0.207 0.000 0.814 1.25
BNW_6 360 13 0.090 0.178 0.000 0.511 1.98
BNW_7 370 69 0.349 0.627 0.000 4.230 1.80
BNW_8 380 5 0.151 0.141 0.000 0.343 0.94
BNW_9 390 74 0.067 0.212 0.000 1.102 3.18
SKARN_1 410 207 0.194 0.357 0.000 2.976 1.84
SKARN_2 420 208 0.240 0.573 0.000 6.203 2.39
SKARN_3 430 363 0.051 0.078 0.000 0.552 1.51
SKARN_4 440 1230 0.104 0.325 0.000 8.700 3.12
B_W_A 510 68 0.001 0.003 0.000 0.025 4.94
B_W_B 520 63 0.014 0.030 0.000 0.176 2.23
B_W_C 530 241 0.042 0.162 0.000 1.131 3.81
B_W_D 540 75 0.372 0.673 0.000 3.945 1.81
B_W_E 550 32 0.015 0.079 0.000 0.448 5.19
BWW1 610 9 0.116 0.116 0.000 0.336 1.00
BWW2 620 17 0.338 0.502 0.000 1.415 1.48
BWW3 630 25 0.669 1.087 0.000 3.525 1.62
BWW4 640 30 0.277 0.246 0.006 1.164 0.89

Source: SRK, 2020

14.3.4 Outlier Analysis and Grade Capping

Grade capping is a technique used to mitigate the effect that a small population of high-grade sample outliers can have during grade estimation. These high-grade samples are considered to not be representative of the general sample population and are therefore "capped" to a level that is more representative of the general data population. Although subjective, grade capping is a common industry practice when performing grade estimation for deposits that have significant grade variability.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 63

Outlier analysis for Bolivar was conducted on the 2m composited dataset and assessed separately for each individual domain. Histograms and normal quantile plots were generated for each mineralized domain, and appropriate capping levels were selected where required. Composites were capped prior to grade estimation. A summary of grade capping levels is provided in Table 14-12 to Table 14-14.

Table 14-12: Capped Composite Summary Statistics for Cu (%)

Domain Domain
Code
# of Comps Cu_pct
(Cap Value)
Cu_pct
(#'s capped)
Cu_pct
(Mean)
Cu_pct
(StDev)
Cu_pct
(CV)
EGI 110 1736 4.5 3 0.65 0.71 1.1
EGI_2 120 37 2.2 3 1.16 0.69 0.6
EGI_3 130 311 4.8 6 1.05 1.21 1.2
EGI_4 140 36 0.95 4 0.44 0.31 0.7
EGI_5 150 66 2.8 6 1.44 0.88 0.6
EGI_6 160 39 1.5 4 0.57 0.49 0.9
CHIMINEA_1 210 459 11 7 1.18 2.14 1.8
CHIMINEA_2 220 506 2.2 10 0.51 0.57 1.1
BNW_1 310 90 1.9 5 0.78 0.57 0.7
BNW_2 320 91 2.8 3 0.68 0.73 1.1
BNW_3 330 11 N/A N/A 0.55 0.51 0.9
BNW_4 340 318 2.2 7 0.63 0.51 0.8
BNW_5 350 15 N/A N/A 0.69 0.62 0.9
BNW_6 360 13 N/A N/A 0.71 0.72 1.0
BNW_7 370 69 1.1 7 0.54 0.34 0.6
BNW_8 380 5 N/A N/A 0.60 0.16 0.3
BNW_9 390 74 2.8 4 0.99 0.84 0.8
SKARN_1 410 207 1.9 7 0.46 0.52 1.1
SKARN_2 420 208 1.8 9 0.52 0.51 1.0
SKARN_3 430 363 6 7 0.84 1.27 1.5
SKARN_4 440 1230 7.3 15 0.81 1.30 1.6
B_W_A 510 68 1.3 8 0.53 0.46 0.9
B_W_B 520 63 1.8 6 0.57 0.56 1.0
B_W_C 530 241 3.8 5 1.09 0.93 0.9
B_W_D 540 75 2.8 2 0.79 0.83 1.1
B_W_E 550 32 2 3 0.76 0.77 1.0
BWW1 610 9 N/A N/A 0.85 0.27 0.3
BWW2 620 17 N/A N/A 0.72 0.41 0.6
BWW3 630 25 2 3 1.26 0.52 0.4
BWW4 640 30 1.1 2 0.65 0.26 0.4

Source: SRK, 2020

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 64

Table 14-13: Capped Composite Summary Statistics for Ag (g/t)

Domain Domain
Code
# of Comps Ag_g/t
(Cap Value)
Ag_g/t
(#'s capped)
Ag_g/t
(Mean)
Ag_g/t
(StDev)
Ag_g/t
(CV)
EGI 110 1736 115 5 11.33 14.69 1.3
EGI_2 120 37 30 5 18.16 9.36 0.5
EGI_3 130 311 120 4 24.37 26.18 1.1
EGI_4 140 36 15 3 7.37 4.63 0.6
EGI_5 150 66 55 6 27.73 15.46 0.6
EGI_6 160 39 35 6 13.20 12.15 0.9
CHIMINEA_1 210 459 300 1 28.18 53.81 1.9
CHIMINEA_2 220 506 300 3 14.00 36.11 2.6
BNW_1 310 90 135 3 32.11 36.28 1.1
BNW_2 320 91 70 8 22.55 23.22 1.0
BNW_3 330 11 N/A N/A 18.22 18.59 1.0
BNW_4 340 318 38 5 7.39 8.87 1.2
BNW_5 350 15 N/A N/A 15.78 15.88 1.0
BNW_6 360 13 N/A N/A 14.84 12.19 0.8
BNW_7 370 69 27 3 7.24 7.33 1.0
BNW_8 380 5 N/A N/A 10.37 4.88 0.5
BNW_9 390 74 35 6 14.43 11.22 0.8
SKARN_1 410 207 115 3 18.43 24.74 1.3
SKARN_2 420 208 155 1 19.96 29.04 1.5
SKARN_3 430 363 70 6 14.46 16.13 1.1
SKARN_4 440 1230 180 3 17.68 27.23 1.5
B_W_A 510 68 28 5 8.76 8.92 1.0
B_W_B 520 63 50 8 15.24 17.92 1.2
B_W_C 530 241 205 4 32.86 41.07 1.3
B_W_D 540 75 29 7 9.47 9.51 1.0
B_W_E 550 32 53 2 15.16 17.34 1.1
BWW1 610 9 N/A N/A 16.97 19.05 1.1
BWW2 620 17 N/A N/A 10.11 7.32 0.7
BWW3 630 25 60 2 20.24 19.88 1.0
BWW4 640 30 10 5 4.27 3.57 0.8

Source: SRK, 2020

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 65

Table 14-14: Capped Composite Summary Statistics for Au (g/t)

Domain Domain
Code
# of Comps Au_g/t
(Cap Value)
Au_g/t
(#'s capped)
Au_g/t
(Mean)
Au_g/t
(StDev)
Au_g/t
(CV)
EGI 110 1736 2.3 7 0.162 0.325 2.0
EGI_2 120 37 0.95 3 0.286 0.329 1.1
EGI_3 130 311 1.25 7 0.113 0.235 2.1
EGI_4 140 36 0.08 3 0.026 0.022 0.8
EGI_5 150 66 0.5 4 0.124 0.145 1.2
EGI_6 160 39 N/A N/A 0.167 0.316 1.9
CHIMINEA_1 210 459 0.21 5 0.017 0.033 2.0
CHIMINEA_2 220 506 0.19 8 0.014 0.034 2.4
BNW_1 310 90 1.7 5 0.450 0.516 1.1
BNW_2 320 91 1.9 5 0.329 0.497 1.5
BNW_3 330 11 N/A N/A 0.479 0.513 1.1
BNW_4 340 318 2.25 10 0.434 0.520 1.2
BNW_5 350 15 N/A N/A 0.166 0.207 1.2
BNW_6 360 13 N/A N/A 0.090 0.178 2.0
BNW_7 370 69 1.6 2 0.301 0.398 1.3
BNW_8 380 5 N/A N/A 0.151 0.141 0.9
BNW_9 390 74 N/A N/A 0.067 0.212 3.2
SKARN_1 410 207 1.14 4 0.172 0.242 1.4
SKARN_2 420 208 1.6 4 0.210 0.363 1.7
SKARN_3 430 363 0.3 9 0.049 0.064 1.3
SKARN_4 440 1230 1.7 4 0.097 0.207 2.1
B_W_A 510 68 N/A N/A 0.001 0.003 4.9
B_W_B 520 63 0.06 3 0.010 0.018 1.7
B_W_C 530 241 0.08 3 0.008 0.023 2.9
B_W_D 540 75 1.66 3 0.318 0.464 1.5
B_W_E 550 32 0.03 1 0.002 0.007 3.3
BWW1 610 9 N/A N/A 0.116 0.116 1.0
BWW2 620 17 N/A N/A 0.338 0.502 1.5
BWW3 630 25 0.65 5 0.274 0.281 1.0
BWW4 640 30 0.36 6 0.214 0.118 0.6

Source: SRK, 2020

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 66
14.4 Density

Density measurements have been taken at Bolivar from both drill core and hand samples from the underground workings.

For both sample types, density has been assessed via the standard immersion method, measuring the mass of the sample in air and then water, and taking the difference between the two. In addition, Bolivar has data from ongoing production which provides an average density of material through the plant that generally fluctuates around 3.7 g/cm3.

A total of 559 density samples have been collected from drill core within the various mineralized domains at Bolivar. However, as noted in Table 14-5, many of the interpreted mineralized domains contain few density measurements. Insufficient density measurements are available to estimate density locally and therefore an average density has been assigned to the various mineralized domains.

As noted in Section 7.4, mineralization at Bolivar is locally associated with magnetite dependent on proximity to fluid flow channels. Analysis of the density measurements for Bolivar, relative to sulphide (i.e., Cu and Zn) and magnetite mineralization suggests that density is affected by both the extent of sulphide and magnetite mineralization present. To date, Bolivar has not specifically analyzed samples for magnetite content, therefore total Fe content has been used to correlate against density. Figure 14-4 provides plots of density relative to Cu, total Fe and combined Cu, total Fe and Zn content.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 67

Table 14-15: Assigned Average Density Values for Mineralized Domains

Domain Domain Code Domain Group # of Density Samples Average Assigned Density (t/m3)
EGI 110 100 175 3.6
EGI_2 120 100 11 3.6
EGI_3 130 100 30 3.6
EGI_4 140 100 14 3.6
EGI_5 150 100 0 3.6
EGI_6 160 100 4 3.6
CHIMINEA_1 210 200 7 3.2
CHIMINEA_2 220 200 7 3.2
BNW_1 310 300 5 3.45
BNW_2 320 300 5 3.45
BNW_3 330 300 0 3.45
BNW_4 340 300 9 3.45
BNW_5 350 300 0 3.45
BNW_6 360 300 3 3.45
BNW_7 370 300 2 3.45
BNW_8 380 300 1 3.45
BNW_9 390 300 3 3.45
SKARN_1 410 400 9 3.6
SKARN_2 420 400 6 3.6
SKARN_3 430 400 63 3.6
SKARN_4 440 400 79 3.6
B_W_A 510 500 8 3.45
B_W_B 520 500 7 3.45
B_W_C 530 500 43 3.45
B_W_D 540 500 31 3.45
B_W_E 550 500 5 3.45
BWW1 610 600 1 3.2
BWW2 620 600 9 3.2
BWW3 630 600 12 3.2
BWW4 640 600 10 3.2

Source: SRK, 2020

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 68

Source: SRK, 2020

Figure 14-4: Scatter Plots of Density (t/m3) Relative to Cu (%), Fe (%) and Combined Cu + Fe + Zn (%) Mineralization

It is recommended to implement a systematic density measurement program of different rock types and mineralization styles within Bolivar. Drill core samples collected for density measurement should also be submitted for geochemical analysis to allow for correlation of density to sulphide and magnetite content within the various mineralization domains.

14.5 Variography

Due to limited composites within most individual mineralized domains, variogram analysis was conducted only on the larger domains (i.e. EGI, Chiminea_1, Chiminea_2, BNW_4 and B_W_C) Directional variograms for copper, silver and gold were produced for each of these domains, with the exception of B_W_C where no variogram was produced for gold. Variogram parameters are provided in Table 14-16 to Table 14-18.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 69

Table 14-16: Variogram Parameters for Copper

Domain Domain
Code
Nugget Struct1 Struct2
Sill Major Semi
Major
Minor Sill Major Semi
Major
Minor Bearing Plunge Dip
EGI 110 0.25 0.6 40 25 8 0.15 140 65 15 98 -8 22
CHIMINEA_1 210 0.05 0.58 15 6 8 0.37 55 16 10 115 11 -60
CHIMINEA_2 220 0.25 0.35 78 8 20 0.4 150 60 55 110 5 -62
BNW_4 340 0.2 0.56 85 37 10 0.24 155 70 15 144 12 32
B_W_C 530 0.2 0.53 6 6 6 0.27 70 70 14 -15 10 -10

Source: SRK, 2020

Table 14-17: Variogram Parameters for Silver

Domain Domain
Code
Nugget Struct1 Struct2
Sill Major Semi
Major
Minor Sill Major Semi
Major
Minor Bearing Plunge Dip
EGI 110 0.25 0.6 40 25 8 0.15 140 65 15 98 -8 22
CHIMINEA_1 210 0.05 0.46 15 8 8 0.49 60 20 12 115 11 -60
CHIMINEA_2 220 0.15 0.55 28 8 6 0.3 117 40 20 110 5 -62
BNW_4 340 0.15 0.62 55 45 10 0.23 200 100 20 144 12 32
B_W_C 530 0.2 0.64 6 6 6 0.16 70 70 14 -15 10 -10

Source: SRK, 2020

Table 14-18: Variogram Parameters for Gold

Domain Domain
Code
Nugget Struct1 Struct2
Sill Major Semi
Major
Minor Sill Major Semi
Major
Minor Bearing Plunge Dip
EGI 110 0.3 0.53 50 36 4 0.17 112 78 12 92 -8 22
CHIMINEA_1 210 0.05 0.7 8 9 8 0.25 38 27 17 82 49 -66
CHIMINEA_2 220 0.15 0.64 17 17 20 0.21 55 55 35 90 30 -56
BNW_4 340 0.15 0.59 70 38 6 0.26 195 60 13 144 12 32

Source: SRK, 2020

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 70
14.6 Block Model Configuration

Two block models were constructed in MAPTEK® Vulcan software for the 2020 Bolivar MRE, with details provided in Table 14-19 and shown in Figure 14-5.

Table 14-19: Block Model Configuration Parameters

Origin Bolivar East Bolivar West
X Coordinate 10,900 8,600
Y Coordinate 8,250 9,100
Z Coordinate 1300 1100
Rotation
Bearing 50° 90°
Block Size
X 5m 5m
Y 5m 5m
Z 5m 5m
Sub-Block Size
X 1m 1m
Y 1m 1m
Z 1m 1m
Distance offsets
X 1,400 1100
Y 3,000 900
Z 700 600

Source: SRK, 2020

Source: SRK, 2020

Figure 14-5: 2020 Bolivar MRE Block Models

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 71
14.7 Estimation Parameters

Block estimation of copper, silver and gold was conducted using both Ordinary Kriging and Inverse Distance (ID2). Ordinary Kriging was used for domains which contained sufficient sample density to develop variogram models. All other domain block grades were estimated using ID2. Estimation was conducted using multiple passes, using the following generalized approach:

· Pass 1 search ellipse range used 60% of the variogram range
· Pass 2 search ellipse range used 100% of the variogram range
· Pass 3 search ellipse used approximately 150% of the variogram range
· Pass 4 search ellipse used approximately 200% of the variogram range

Generally, the majority of blocks within each domain were estimated within the first two estimation passes, with passes 3 and 4 used to estimate blocks along the peripheries of the mineralized domains. Search ellipse and estimation parameters are summarized in Table 14-20 and Table 14-21.

For mineralized domains with significant undulating geometry, the technique of locally varying anisotropy (LVA) was used to locally adjust search orientations to better align with the geometry of the mineralized zone contacts. The LVA option in MAPTEK® Vulcan uses HW and FW surfaces to determine block scale orientation parameters to use during grade estimation. Domains where LVA was used are indicated in Table 14-20.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 72

Table 14-20: Search Ellipse Orientation Parameters

Domain Domain
Code
Estimation Technique Bearing Plunge Dip LVA
EGI 110 OK Variogram Y
EGI_2 120 ID2 112 -9 36
EGI_3 130 ID2 45 -30 27
EGI_4 140 ID2 51 -27 15 Y
EGI_5 150 ID2 50 -31 10
EGI_6 160 ID2 23 -20 -15
CHIMINEA_1 210 OK Variogram
CHIMINEA_2 220 OK Variogram
BNW_1 310 ID2 55 10 0 Y
BNW_2 320 ID2 117 55 15
BNW_3 330 ID2 122 -22 0
BNW_4 340 OK Variogram Y
BNW_5 350 ID2 30 -20 0
BNW_6 360 ID2 6 -10 0
BNW_7 370 ID2 12 -28 0
BNW_8 380 ID2 124 -12 0
BNW_9 390 ID2 130 0 23 Y
SKARN_1 410 ID2 Omni-directional
SKARN_2 420 ID2 140 0 0
SKARN_3 430 ID2 213 0 -85
SKARN_4 440 ID2 44 0 -85
B_W_A 510 ID2 90 5 0
B_W_B 520 ID2 20 0 0 Y
B_W_C 530 OK Variogram Y
B_W_D 540 ID2 30 38 20
B_W_E 550 ID2 0 9 0
BWW1 610 ID2 128 -10 -11

Source: SRK, 2020

Table 14-21: Summary of Estimation Parameters

Estimation
Pass
Min # of
Composites
Max # of
Composites
Max Comps
per DDH
Range
Major Semi-Major Minor
Pass 1 5 10 3 50 50 10
Pass 2 5 10 3 75 75 15
Pass 3 5 10 3 100 100 20
Pass 4 1 10 3 150 150 30

Source: SRK, 2020

Note: Search ellipse range parameters used for ID2 estimation.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 73
14.8 Model Validation

Block model validation was conducted using multiple techniques including:

1. Swath plot analysis of grade profiles between the block model, a nearest neighbour (declustered) block model and assay composites.
2. Comparison of block model mean grades to a nearest neighbour (declustered) model produced on a 1m by 1m by 1m grid.
3. Visual inspection of estimated block grades relative to assay composites.

Examples for each of the model validation techniques are provided in Figure 14-6 to Figure 14-11. In general, there is good correlation between the drill hole composite data, nearest neighbor (declustered) model and estimated block grades.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 74

Source: SRK, 2020

Figure 14-6: Swath Plot of Cu (%) Grade for the EGI Domain

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 75

Source: SRK, 2020

Figure 14-7: Swath Plot of Ag (g/t) Grade for the EGI Domain

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 76

Source: SRK, 2020

Figure 14-8: Comparison of Average Cu (%) Grade Between Block Model Estimate and Declustered Nearest Neighbour Model for Each Mineralized Domain (Note: Grey Bars Represent Volume of Individual Domains)

Source: SRK, 2020

Figure 14-9: Comparison of Average Ag (g/t) Grade Between Block Model Estimate and Declustered Nearest Neighbour Model for Each Mineralized Domain (Note: Grey Bars Represent Volume of Individual Domains)

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 77

Source: SRK, 2020

Figure 14-10: EGI Domain Cross-section Comparison of Estimated Block Cu (%) Grades Relative to Drill Hole Assay Composites

Source: SRK, 2020

Figure 14-11: BNW4 Domain Cross-section Comparison of Estimated Block Cu (%) Grades Relative to Drill Hole Assay Composites

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 78
14.9 Mineral Resource Classification

Mineral resource classification is a subjective concept and industry best practices suggest that mineral resource classification should consider both the confidence in the geological continuity of the mineralized structures, the quality and quantity of exploration data supporting the estimates and the geostatistical confidence in the tonnage and grade estimates. Appropriate classification criteria should aim at integrating all of these concepts to delineate regular areas of similar resource classification.

Mineral resources for Bolivar have been classified as either Indicated or Inferred mineral resources. No Measured mineral resource has been defined for this deposit. CIM Definition Standards for Mineral Resources and Mineral Reserves (CIM, 2014) define Indicated and Inferred mineral resources as follows:

Indicated Mineral Resource

An Indicated Mineral Resource is that part of a Mineral Resource for which quantity, grade or quality, densities, shape and physical characteristics are estimated with sufficient confidence to allow the application of Modifying Factors in sufficient detail to support mine planning and evaluation of the economic viability of the deposit. Geological evidence is derived from adequately detailed and reliable exploration, sampling and testing and is sufficient to assume geological and grade or quality continuity between points of observation.

Inferred Mineral Resource

An Inferred Mineral Resource is that part of a Mineral Resource for which quantity and grade or quality are estimated on the basis of limited geological evidence and sampling. Geological evidence is sufficient to imply but not verify geological and grade or quality continuity. An Inferred Mineral Resource has a lower level of confidence than that applying to an Indicated Mineral Resource and must not be converted to a Mineral Reserve. It is reasonably expected that the majority of Inferred Mineral Resources could be upgraded to Indicated Mineral Resources with continued exploration.

Significant factors affecting the classification include:

· Lack of historic and consistent QA/QC program
· Lack of downhole surveys for most drillholes and measured deviations from planned and actual azimuths
· Lack of density tests of the different mineralization and rock types for all the areas
· Geological understanding of mineralization controls
· Spacing of drilling compared to observed geologic continuity
· Geostatistical factors suggesting ranges of reasonable influence between sampling
· Bolivar is a producing mine with a successful operating history dating more than 10 years

The classification is generally based on the confidence in geological interpretation of the mineralization controls and block estimation passes, which are then used to guide a manually digitized polygon to assign the final classification. Generally, blocks estimated within the first two estimation passes with sufficient confidence in the drill hole data and geological model were classified as Indicated.

14.10 Depletion for Mining

Bolivar has been actively mined since 2007. As of the end of 2019, most mine production has been generated from the EGI area of the deposit with lesser historical production coming from the Skarn area (Figure 14-12); however, UG development to support mine production in the Bolivar West area (i.e., B_W) has been established during 2018 and 2019. Wireframes of all UG development and mine stopes were provided to SRK by Sierra Metals and were used to deplete the updated mineral resource model prior to the reporting of mineral resources.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 79

Source: Sierra Metals, 2020

Figure 14-12: Areas of Mine Production as of December 31, 2019

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 80
14.11 Mineral Resource Statement

CIM Definition Standards for Mineral Resources and Mineral Reserves (May 2014) defines a mineral resource as:

"A Mineral Resource is a concentration or occurrence of solid material of economic interest in or on the Earth's crust in such form, grade or quality and quantity that there are reasonable prospects for eventual economic extraction. The location, quantity, grade or quality, continuity and other geological characteristics of a Mineral Resource are known, estimated or interpreted from specific geological evidence and knowledge, including sampling".

The "reasonable prospects for economic extraction" requirement generally implies that the quantity and grade estimates meet certain economic thresholds and that the Mineral Resources are reported at an appropriate cut-off grade (CoG) taking into account extraction scenarios and processing recoveries. To assess this at Bolivar, SRK has calculated an economic value for each block in terms of US dollars based on the grade of contained metal in the block, multiplied by the assumed recovery for each metal, multiplied by pricing established by Sierra Metals for each commodity. Costs for mining and processing are taken from data provided by Dia Bras for their current underground mining operation.

The December 31, 2019, consolidated mineral resource statement for the Bolivar Mine area is presented in Table 14-22.

Table 14-22: Consolidated Bolivar Mine Mineral Resource Statement as of December 31, 2019(1)(2)(3)(4)(5)

Category Tonnes (Mt) Ag (g/t) Au (g/t) Fe (%) Cu (%)

Ag

(M oz)

Au

(k oz)

Cu (t)
Indicated 19.4 15.1 0.21 13.8 0.77 9.4 127.8 149,116
Inferred 21.4 14.2 0.21 13.5 0.78 9.8 145.6 167,077

Source: SRK, 2020

(1) Mineral resources are reported inclusive of mineable inventory

(2) Mineral Resources are not Mineral Reserves and do not have demonstrated economic viability.

(3) All figures are rounded to reflect the relative accuracy of the estimates.

(4) Mineral Resources are reported at a value per tonne cut-off of US$24.25/t using the following metal prices and recoveries; Cu at US$3.08/t and 88% recovery; Ag at US$17.82/oz and 78.6% recovery, Au at US$1,354/oz and 62.9% recovery.

(5) Total Fe does not represent an estimate of magnetite content nor should be used as a proxy for a recoverable magnetite product.

14.12 Mineral Resource Sensitivity

To demonstrate the sensitivity of the Bolivar mineral resource to metal value cut-off, a grade-tonnage curve was developed to show changes in mineral resource tonnage and equivalent copper grade (Cu-Eq) to changes in the metal value cut-off. The grade-tonnage curve for the December 31, 2019 Bolivar MRE is provided in Figure 14-13. Cu-Eq grades are calculated incorporating recovery factors for gold and silver, and metal prices for copper, gold and silver as defined in Table 14-22.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 81

Source: SRK, 2020

Figure 14-13: Grade-Tonnage Curve for Indicated and Inferred Mineral Resources

14.13 Previous Resource Estimates

A resource estimate for the Bolivar Mine was reported in October 2017 by SRK Consulting (U.S.), Inc. The MRE is summarized in Table 14-23.

Table 14-23: Consolidated Bolivar Mine Mineral Resource Statement as of October 31, 2017-SRK Consulting (U.S.), Inc.

Category

Tonnes

(000's)

Ag

(g/t)

Au

(g/t)

Cu

(%)

Ag

(koz)

Au

(koz)

Cu

(t)

Indicated 13,267 22.5 0.29 1.04 9,616 124 137,537
Inferred 8,012 22.4 0.42 0.96 5,779 109 76,774

Source: SRK, 2017

Compared to the previous 2017 estimated mineral resources, the current Indicated resource tonnage has increased by 46% (6.1Mt), with an associated reduction in average copper grade of 26% and, reduction in silver and gold grades of 33% and 29%, respectively. Overall metal content increased by 10,430 t of equivalent copper.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 82

These changes are attributed to several factors, including:

· Incorporation of lower-grade mineralization above a metal value cut-off of US$24.25 which previously was excluded from the interpreted mineralization domains.
· Incorporation of new zones of mineralization previously excluded from the geological model.
· Upgrading of previous inferred resources to indicated resources based on additional drilling and a refined geological model.

Inferred mineral resources have increased by approximately 167% (13.4 Mt), with as associated reduction in copper grade of 19%, and reduction in silver and gold grades of 37% and 50%, respectively. Overall metal content has increased by 102,632 t of equivalent copper.

Changes to the Inferred mineral resource are attributed to the following factors:

· Incorporation of lower-grade mineralization above a metal value cut-off of US$24.25 which previously was excluded from the interpreted mineralization domains.
· Incorporation of new zones of mineralization previously excluded from the geological model.
· Incorporation of newly discovered zones of mineralization based on additional exploration drilling conducted during 2017 to 2019.
14.14 Relevant Factors

There are no other factors pertinent to the Mineral Resource statement other than those stated in the above sections which SRK would expect to have a material impact on the statement.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 83
15 Mineral Reserve Estimates

A Mineral Reserve is the economically mineable part of a Measured and/or Indicated Resource. It includes diluting material and allowances for losses, which may occur when the material is mined or extracted and is defined by studies at Pre-feasibility or Feasibility level as appropriate that include the application of Modifying Factors.

A Mineral Reserve has not been estimated for the Project as part of this PEA.

The PEA includes Inferred Mineral Resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as Mineral Reserves.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 84
16 Mining Methods

The conceptual mine plan considered in this PEA includes Inferred Mineral Resources that are considered too speculative geologically to have economic considerations applied to them that would enable them to be categorized as Mineral Reserves, and there is no certainty that the results of the PEA will be realized.

16.1 Introduction

The Mineral Resources reported by SRK (as of December 31, 2019) are estimated at 19.4 Mt of Indicated and 21.4 Mt of Inferred based on a cut-off value of US$24.24/t. These resources form the basis of the mine plan considered in this PEA.

Sub-level stoping and room and pillar mining methods are currently used in the main areas of the mine to obtain a production rate of 5,000 tpd. The method used varies depending on geotechnical constraints, mineralization trends, dimensions, and mine production targets.

Using the resources estimated by SRK through December 2019, Sierra Metals performed a growth analysis to determine how the Bolívar Mine could achieve sustainable production of 7,000 tpd - 15,000 tpd. The analysis indicates that the production objectives are achievable through the expansion of the sub-level stoping mining method in the new production areas, which will allow the sustainability of the operation.

A new configuration of the mining method will allow greater recovery of resources and production rates. The mine design is shown in Figure 16-1 and Figure 16-2.

Source: Sierra Metals, 2020

Figure 16-1: Overview of Bolivar Mine Design - Plan View

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 85

Source: SRK, 2020

Figure 16-2: Bolivar Overview - Plan View

16.2 Current Mining Methods

Current production at Bolivar comes from the El Gallo Inferior, Chimenea 1 and 2 and the Bolivar West mineralized zones. Mineralized material is currently hauled to the surface using one of several adits or declines accessing the mineralized zones and is then dumped onto small pads outside the portals. The mineralized material is then loaded into rigid-frame, over-the-road trucks and hauled on a gravel road approximately 5.1 km south to the Piedras Verdes Mill. As explained in more detail in Section 18, the mine is constructing an underground tunnel that will enable mineralized material to be delivered via underground truck transport to a portal adjacent to the Mill. This development will eliminate the impact of bad weather on the current surface truck haulage system and will provide a lower cost and more reliable method of delivering mineralized material to the plant.

Future production will include mineralized material from Bolivar Northwest (BNW). The Bolivar NW mineralized zone is further broken down into BNW 1, BNW 2, BNW 4, BNW 6, BNW 7, BNW8 and BNW 9.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 86

Figure 16-3 shows a plan view of the Bolivar Mine, the geology shapes, and the mined out areas.

Source: Sierra Metals, 2020

Figure 16-3: Plan View of Bolivar Mineralized Zone Location and Mined Out Areas

Figure 16-4 shows an isometric view of the El Gallo Inferior area and the Chimenea 1 and Chimenea 2 mineralized zones.

Source: Sierra Metals, 2020

Figure 16-4: Isometric View of El Gallo Inferior, Chimenea 1 and Chimenea 2

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 87

Figure 16-5 shows a rotated view, looking southwest, of Bolivar NW domains BNW4, 1, 2, 6, 7,8 and 9, and the as-built (mined out) shapes from previous mining.

Source: Sierra Metals, 2020

Figure 16-5: Isometric View of Bolivar W, Bolivar NW and Mined Out Areas

The Bolivar Mine is currently mined by the sub-level stoping and room and pillar methods and the specific method applied to a particular area of the mine is determined by geotechnical constraints, mineralization trends, dimensions and mine production targets.

The current distribution of mining method by area is summarized in Table 16-1.

Table 16-1: Rock Mass Characteristics of El Gallo Inferior, Chimenea 1 and Chimenea 2 and Bolivar West

Domain Code Name Zone Mining Method
110 EGI 1 Gallo Inferior Sub Level Stoping
210 Chimenea 1 Chimenea1 Sub Level Stoping
220 Chimenea 2 Chimenea2 Sub Level Stoping
510 Bolivar West A Bolivar W Sub Level Stoping
520 Bolivar West B Sub Level Stoping
530 Bolivar West C Sub Level Stoping
540 Bolivar West D Sub Level Stoping

Source: Sierra Metals, 2020

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 88
16.2.1 Sub-Level Stoping - Bolivar West

The longhole method is applied in the shallow dipping mineralized bodies in Bolivar West. Excavation for longholes with openings of 9.0 m and pillars of 7.0 m x 7.0 m for stope heights between 12.0 m and 15.0 m. From the access ramp, access to the mineralized material is established in the central part of the chamber and the mineral cut begins. A drive is developed within the mineralized material, then the drilling of long holes is carried out and extraction begins. Ramps are established in some cases in mineralized material to minimize waste extraction.

Figure 16-6 shows a typical section of the method.

Source: Sierra Metals, 2020

Figure 16-6: Typical Section Showing Sub-Level Stoping

16.2.2 Sub-Level Stoping - El Gallo Inferior

The longhole method is applied to the mineralized structures at the El Gallo Inferior deposit. Each level has 20.0 m of vertical stope height and is accessed through a ramp to the central part of the level. A mineralized material drive is developed to the floor of the structure and then the cutting of the mineralized mineral begins through the mineralized material drive and continues with the drilling of longholes. Then, the mineralized material is extracted through the second ore drive made in the lower part of the level. After every 45.0 m of advance in the mineralized material drive, a perpendicular support pillar of 10.0 m is left.

Figure 16-7 shows a typical sub-level stoping section in both sectional and plan views.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 89

Source: Sierra Metals, 2020

Figure 16-7: Typical Section Showing Sub-Level Stoping

The primary access is made via ramps of 5.0 m x 5.0 m and then the accesses to the stopes and ore drives are developed with a section of 4.0 m x 4.0 m. The ramps are designed with a maximum gradient of 12%.

16.2.3 Drilling, Blasting, Loading and Hauling

The electrohydraulic jumbos conduct the lateral development of the main tasks such as ramps, crossings or bypasses. The ramps have a section of 5.0 m x 5.0 m (width / height) and the accesses to the stopes and mineralized material drive have a section of 4.0 m x 4.0 m (width / height).

Raptor radial drilling jumbos are used for the production of the stopes. The drilling and blasting designs are developed by the technicians at the mine.

Two layouts for typical 4.0 m x 4.0 m development blast patterns are shown in Figure 16-8 and Figure 16-9. Blasting designs for longholes in Bolivar West and El Gallo Inferior are shown in Figure 16-10 and Figure 16-11 respectively. A drill jumbo is shown drilling a production blast pattern in El Gallo Inferior in Figure 16-12.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 90

Source: Sierra Metals, 2020

Figure 16-8: Typical 4 m x 4 m Development Blast Pattern 1

Source: Sierra Metals, 2020

Figure 16-9: Typical 4 m x 4 m Development Blast Pattern 2

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 91

Source: Sierra Metals, 2020

Figure 16-10: Blasting Design for Longholes in Bolivar West

Source: Sierra Metals, 2020

Figure 16-11: Blasting Design for Longholes in El Gallo Inferior

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 92

Source: SRK, 2017

Figure 16-12: Drill Jumbo Drilling a Blast Pattern in an El Gallo Inferior Production Stope

After blasting, the face is mucked by scoops, and mineralized material is loaded into trucks and hauled to the ramp portal on surface. Historically, approximately 10% of total production is waste. This percentage is estimated to increase slightly to 20% as the mine advances into areas outside of El Gallo Inferior. Waste rock is either placed in the stopes underground or hauled to the surface, and it is sometimes used as construction material.

16.2.4 Mineralized Material and Waste Handling

The mineralized material and waste handling strategy in El Gallo Inferior is well established and has been applied to the future production mining areas of Bolivar W and Bolivar NW. It is recommended to perform a haulage simulation to validate the mineralized material and waste handling assumptions made for underground truck haulage from each of the three main mining areas (El Gallo Inferior, Bolivar W, Bolivar NW) to surface, as well as the surface truck haulage from surface dumps to the mill. Haulage simulation can confirm that the production targets are achievable and can identify possible traffic interference and bottlenecks.

The mine is in the process of developing a new tunnel mineralized material delivery system that will deliver mineralized material directly to the Piedras Verdes processing plant. This new system is described in Section 18.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 93
16.3 Geomechanical Parameters
16.3.1 Stability Design Criteria

The MATHEWS method (Stability graph) is the most used worldwide for large excavations (long holes), being necessary to know the Hydraulic Radius (RH = Area / Perimeter) and the Number of stability (N' = Q 'x A x B x C).

The design procedure is based on the calculation of two factors, N', which is the modified stability number, which represents the ability of the rock mass to remain stable under a given stress condition, and RH, which is the form factor or hydraulic radius, which takes into account the size and shape of the stope.

Q': Tunnel Quality Index Q Modified

A: Stress factor in the rock

B: Adjustment factor for joint orientation

C: Gravitational adjustment factor

Induced Stress Adjustment = A

Factor "A" reflects the forces acting on the free faces of the open stope at depth. This factor is determined from the unconfined compressive strength of the intact rock and the acting stress parallel to the exposed face of the stope under consideration. The strength of intact rock can be determined by laboratory testing of the rock or by mapping estimates. Induced compressive stress is established from numerical modeling or estimated from published stress distributions such as those in Hoek & Brown (1980a), using measured or assumed in situ stress values. The stress factor in the rock, A, is therefore determined from the ratio σc / σ1, resistance of the intact rock to induced compressive stress, on the edge of the opening.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 94

Source: Sierra Metals, 2020

Figure 16-13: Stress Factor in Rock A, for Different Values of σc / σ1

Joint orientation adjustment = B

Factor B considers the influence of the joints on the stability of the stope faces. Many cases of structurally controlled failure occur along critical joints, which form a small angle with the free surface. The smaller the angle between the joint and the surface, the easier it is for the intact rock bridge, shown in Figure 16-14, to break due to blasting, stress, or another joint system. When the angle θ approaches 0, a slight increase in resistance occurs, since the blocks of jointed rock act as a beam. The influence of critical joints on the stability of the excavation surface is highest when the strike is parallel to the free surface and is smallest when the planes are perpendicular to each other. Factor B, which depends on the difference between the orientation of the critical joint and each face of the stope, can be determined from the diagram reproduced in Figure 16-15.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 95

Source: Sierra Metals, 2020

Figure 16-14: Orientation of the Critical Joint with Respect to the Excavation Surface (Potvin, 1988)

Source: Sierra Metals, 2020

Figure 16-15: Adjustment Factor B (Potvin, 1988)

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 96

Gravitational Adjustment = C

Factor C is an adjustment for the effect of gravity. Failure can occur from the roof due to gravity-induced falls or from the pit walls due to landslides. Potvin (1988) suggested that both gravity-induced and shear-induced falls depend on the slope of the pit surface α. The factor C for these cases can be calculated from the relation C = 8 - 6 Cos α or determined from the diagram shown in Figure 16-16. This factor has a maximum value of 8 for vertical walls and a minimum value of 2 for horizontal chopping ceilings. The slip failure will depend on the inclination β of the critical joint, and the adjustment factor C is given in Figure 16-17.

Source: Sierra Metals, 2020

Stability graph according to Potvin (1988), modified by Nickson (1992): Stability graph showing areas of stable ground, sinking ground, and ground with support requirement. According to Potvin (1988), modified by Nickson (1992).

Figure 16-16: Gravity Adjustment Factor C, for Gravity Falls and Slumps (Potvin, 1988)

Using the values of N', the stability number, and the hydraulic radius RH, the pit stability can be estimated from Figure 16-18. This figure represents the open stope performance observed in various Canadian mines, which were tabulated and analyzed by Potvin (1988) and updated by Nickson (1992).

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 97

Source: Sierra Metals, 2020

Figure 16-17: Gravity Adjustment Factor C, for Slip Failure Modes (Potvin, 1988)

Source: Sierra Metals, 2020

Figure 16-18: Stope Stability Graph for Large Excavations (Potvin, 1988)

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 98
16.3.2 Excavation Design for El Gallo Inferior

Excavation for longholes with a gap of 20.0 m (difference in sublevel elevations) x 40.0 m long as shown in Figure 16-19. For the calculation of the excavations and its stability, all the geomechanical parameters described above will be used.

σv = 8.92 Mpa

K = 0.60 (2.7 will be considered as the maximum value)

σH = 4.46 Mpa (It will be considered 24.08 Mpa, product of 2.7 = K)

σc = 170 Mpa, but 120 Mpa will be used (lithostatic average)

Source: Sierra Metals, 2020

Figure 16-19: El Gallo Inferior Cross-section

Table 16-2 to Table 16-6, and Figure 16-20, Figure 16-21 and Figure 16-22, show how some of the important geotechnical design criteria were determined.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 99

Table 16-2: Determination of Stope Stability - El Gallo Inferior

Determination of stability of the Stope Gallo Inferior
depth 350.00 M
Specific weight 2.60 kn/m3 0.26 tn/m3
Vertical stress sv 8.92 Mpa
k=kmin=kmax 0.60
Horizontal stress 5.35 Mpa
UCS 120.00 Mpa
Hydraulic radius calculation
HeightLengthAreaPermiterRadius Hydrauli
Surface m m m2 m m
North 20 20 400 80 5.00
South 20 20 400 80 5.00
Recumbent 20 40 800 120 6.70
Hanging 20 40 800 120 6.70
Roof 20 40 800 120 6.70
Determine Q, using characteristic values of Gallo Inferior
Q
Roof - Skarn 11.28 28.20
Wall - Ore 13.60 34.00
Source: Sierra Metals, 2020

Source: Sierra Metals, 2020

Table 16-3: Factor B and Factor C - El Gallo Inferior

Factor B Discontinuity Orientation Correction Factor Wall
Difference Direction Difference DiP B Manteo Wall C
Surface m m Surface m
North 0.00 90.00 1.00 North 90 8.00
South 0.00 90.00 1.00 South 90 8.00
Recumbent 4.00 4.00 0.30 Recumbent 32 2.06
Hanging 4.00 4.00 0.30 Hanging 32 2.06
Roof 68.00 66.00 0.95 Roof 0 1.00

Source: Sierra Metals, 2020

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 100

Table 16-4: Estimation of Induced Stresses (Part 1) - El Gallo Inferior

Source: Sierra Metals, 2020

Table 16-5: Estimation of Induced Stresses (Part 2) - El Gallo Inferior

Source: Sierra Metals, 2020

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 101

Table 16-6: Stability Number - El Gallo Inferior

Surface RH (m) A B C Est N Z Logit Value P % Est y/o Falla ELOS Caving
North 5 34 0.3 1 8 93 4.2 0.99 98% stable y 2% Unstable 3% Dil
South 5 28.2 0.3 1 8 77 4.1 0.98 98% stable y 2% Unstable 3% Dil
Recumbent 6.7 34 1 0.3 2.1 21 2.6 0.93 93% stable y 7% Unstable 3% Dil
Hanging 6.7 34 1 0.3 2.1 21 2.6 0.93 93% stable y 7% Unstable 3% Dil
Roof 6.7 28.2 0.4 1 1 12 2.2 0.9 80% stable y 20% Unstable 5% Dil

Source: Sierra Metals, 2020

Source: Sierra Metals, 2020

Figure 16-20: Hydraulic Radii - El Gallo Inferior

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 102

Source: Sierra Metals, 2020

Figure 16-21: Maximum Spans - El Gallo Inferior

For the finite-element analysis (Rocscience Software), all the geomechanical parameters described above were used.

Source: Sierra Metals, 2020

Figure 16-22: Stability Factor of Excavations in El Gallo Inferior with Maximum Openings of 40 m (Stable, lower dilution) and 65 m (Unstable, higher dilution).

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 103

Technical criteria were considered for the design of excavations in El Gallo Inferior. The results of geomechanical calculations are shown in Table 16-7.

Table 16-7: Geomechanical Calculation Results

Parameters Unid Wall Roof observations
Dip 32
34 28 Andesite / Skarn roof
21 12
Critical HR m 7.5 6.7 Potvin
Stope depth m 350 Mine deepening
Density t/m3 3.7 2.6
Mpa 8.92
K 0.5 Maximum Tectonic Curve
MPa 4.46 Maximum
Stope length for digging m 45 Maximum
Open stope ceiling length m 40 Maximum
Max height Sub-level body m 20 Lower Dil (%) due to irregularity

Source: Sierra Metals, 2020

Estimation of the wall pillars to separate the work areas, the maximum opening of 45 m is obtained for the stopes.

Source: Sierra Metals, 2020

Figure 16-23: Column Stability

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 104

From the graph in Figure 16-23, Wp / h = 0.50. As the height is known (h = 20.0 m), therefore Wp = 10.0 m. In summary, the pillar wall thickness between stopes (Wp) = 10.0 m. See Figure 16-24.

Source: Sierra Metals, 2020

Figure 16-24: El Gallo Inferior - Plan Section

16.3.3 Geomechanical Characterization of Bolivar West

Geomechanical mapping was carried out on a total of 5,864 m of exploration drill core (Cores de Bolívar W - 2017). This work enabled the geomechanical zoning (RMR) of the rocky massif for Bolivar West as shown in Figure 16-25.

Source: Sierra Metals, 2020

Figure 16-25: Geomechanical Zoning of Bolivar West

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 105

RMR values in the range of 60 - 70 (Avg = 64) were obtained for the intact rocks in both upper and lower of the mineralized area as indicated in Figure 16-26 and Figure 16-27 from the logging of a total of 4,771.57 m of core.

Source: Sierra Metals, 2020

Figure 16-26: Drilling Logging - Bolivar West

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 106

RMR values in the range of 40 - 60 (Avg = 58) were obtained for the mineralized zones, including the ceiling and floor contacts, as a result of logging 1,092.43 m of core.

Source: Sierra Metals, 2020

Figure 16-27: Drilling Logging - Bolivar West

A preliminary geomechanical model was made which will be adjusted with more exploration and the development of Bolivar West.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 107

Source: Sierra Metals, 2020

Figure 16-28: Geomechanical Model of Bolivar West Along the Mineralized Structure (RMR 20 - 40, poor quality)

The Bolivar West zone is divided into two sectors, the upper part being represented with red color (Figure 16-28) where the RMR values range 40 - 60 (regular) and the lower part represented with yellow color where the RMR values range 20 - 40 (poor).

16.3.4 Excavation Design for Bolivar West

Excavation for longholes with a 9.0 m span with 7.0 m x 7.0 m pillars for 12.0 m stems and 8.0 m x 8.0 m for 15.0 m stems. For the calculation of the excavations and its stability, all the geomechanical parameters described above will be used.

σv = 6.88 Mpa

K = 0.5

σH = 3.44 Mpa

σc = 80 Mpa, but 70 Mpa (lithostatic average) will be used.

Table 16-8 to Table 16-12, and Figure 16-29 to Figure 16-32, show how some of the important geotechnical design criteria were determined.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 108

Table 16-8: Determination of Stope Stability - Bolivar West

Source: Sierra Metals, 2020

Table 16-9: Factor B and Factor C - Bolivar West

Factor B Orientación de Discontinuidades Factor de Corección Pared
Diferencia en Rumbo Diferencia en DIP B Manteo Pared C
Surface Surface m
North 0.80 North 90 8.00
South 0.80 South 90 8.00
Recumbent 1.00 Recumbent 32 2.06
Hanging 0.30 Hanging 32 2.06
Roof 0.80 Roof 0 1.00

Source: Sierra Metals, 2020

Table 16-10: Estimation of Induced Stresses (Part 1) - Bolivar West

Source: Sierra Metals, 2020

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 109

Table 16-11: Estimation of Induced Stresses (Part 2) - Bolivar West

Source: Sierra Metals, 2020

Table 16-12: Stability Number - Bolivar West

Surface RH (m) A B C Est N Z Logit Value P % Est y/o Falla ELOS Caving
North 2.6 5 1 0.8 6.8 27 4.2 0.99 99% stable y 1% Unstable 1% Dil
South 2.6 5 1 0.8 6.8 27 4.2 0.99 99% stable y 1% Unstable 1% Dil
Recumbent 2.6 5 1 1 8 40 4.5 0.99 99% stable y 1% Unstable 1% Dil
Hanging 2.96 5 1 0.3 1.1 2 2 0.88 88% stable y 12% Unstable 1% Dil
Roof 2.3 5 0.3 0.8 1.9 2 2.5 0.92 92% stable y 8% Unstable 8% Dil

Source: Sierra Metals, 2020

Source: Sierra Metals, 2020

Figure 16-29: Hydraulic Radii - Bolivar West

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 110

Source: Sierra Metals, 2020

Figure 16-30: Stability and Failure Probabilities - Bolivar West

Source: Sierra Metals, 2020

Figure 16-31: Maximum Spans - Bolivar West

Technical criteria were considered for the design of excavations in Bolivar West. The results of geomechanical calculations are shown in Table 16-13.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 111

Table 16-13: Geomechanical Calculation Results

Parameters Unid Wall Roof observations
Dip 10
5 5 Andesite / Skarn roof
2 2
Critical HR m 2.3 2.6 Potvin
Stope depth m 270 Mine deepening
Density t/m3 3.7 2.6
Mpa 6.88
K 0.5 Maximum Tectonic Curve
MPa 3.44
Stope length for digging m 9 Maximum
Open stope ceiling length m 9 Maximum
Max height Sub-level body m 12 - 15 Lower Dil (%) due to irregularity

Source: Sierra Metals, 2020

Comparison of empirical calculations with finite element modeling

Excavation for longholes with a 9.0 m span with 7.0 m x 7.0 m pillars for 12.0 m height and 8.0 m x 8.0 m for 15.0 m height. For the calculation of the excavations and its stability, all the geomechanical parameters described above will be used.

Source: Sierra Metals, 2020

Figure 16-32: Stability Factor of the Excavations in Bolivar West with maximum openings of 9.0 m (stable and less dilution) and vertical pillars of 7.0 x7.0 m for heights of 12 m

The maximum openings for Bolivar West (upper area) are 9.0 m with vertical pillars of 7.0 m x 7.0 m for stope heights not greater than 12.0 m. For stope heights from 12.0 m to 15.0 m, the pillars should be 9.0 m x 9.0 m, restricting the openings to a maximum of 9.0 m.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 112
16.3.5 Pillar Recovery Potential and Mining Method Alternatives

Pillar recovery operations are some of the most dangerous of all mining activities because of the potential for sudden rockfall and adjacent pillar collapse when removing the pillars. The strategic use of artificial active or passive ground support (e.g., bolting, timber sets, grout cans, tight backfilling, etc.) can reduce the rock fall risk. A slender vertical pillar is shown in Figure 16-33.

Source: SRK, 2019

Figure 16-33: Example of Slender Pillar

Although the Bolivar Mine has no immediate plans to recover any pillars, the future recovery of pillars remains a potential option that warrants further investigation and it is recommended that before any pillars are recovered, a formal stability analysis should be completed. Sierra Metals personnel have indicated their intention to develop methods for the safe extraction of pillars, as well as optimizing or modifying the current room and pillar mining method to improve the overall operation. These initiatives have the potential for increasing reserves and mine life in future resource updates. Recommendations are made below to initiate the study of pillar recovery.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 113

There is uncertainty in the tonnage and grade of material remaining in pillars. There are two primary causes for this uncertainty. First, while mined out areas are surveyed on a regular basis, some of the mined-out volume models are not updated with the latest information, or they are not in the correct position. This is especially true in El Gallo Superior where there is a low degree of confidence in the accuracy of the as-built models. The second cause of uncertainty is in the grade of the material left in pillars. Channel samples have been collected, but much of the information is stored in 2D AutoCAD® drawings and not in a usable form for reserve estimation purposes.

Sierra Metals completed a project to perform a whole mine survey using Light Detection and Ranging (LiDAR) technology in 2017. The site is planning to evaluate their existing channel samples database and, where necessary, collect new samples in order to increase the confidence in the grade estimation of the pillar material. Improving the mine as-built model and the channel samples database will allow the site to review, quantify, and prioritize pillar material for extraction.

Several potential mining options exist for pillar extraction. In the 2017 technical report, SRK recommended that a trade-off study be done to determine the feasibility of the pillar recovery scenarios listed below. At the time that this report was being prepared in 2020, the Bolivar Mine had not yet performed the trade-off study.

· Scenario 1: Pillar recovery with no backfill
o Focus on recovering pillars without additional support generated by backfilling mined out areas.
o Requirements:
- Site visit and geotechnical characterization of existing pillars;
- Pillar rating assessment;
- Numerical modelling to characterize pillar stress conditions;
- Pillar extraction sequence and impact on stability of other pillars; and
- Assessment of pillar extraction.
· Scenario 2: Post pillar cut-and-fill with rock fill
o Potentially utilize rock fill to provide additional ground support for pillar recovery. May result in updated pillar dimensions for new areas.
o Requirements:
- All as shown for Scenario 1; and
- Empirical pillar design criteria.
- Pillar design by mining levels including access (an update to the long-term mine layout);
- Numerical simulation to assess impact of rock fill on pillar stability.
CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 114
- Pillar optimization: grid location and orientation; and
- Numerical simulation of optimized pillars with rock fill.
· Scenario 3: Post pillar cut-and-fill with compacted tailings
o Will result in confirmation or updates to pillar dimension recommendations, a backfill specification for the compacted tailings, and an updated mine layout and sequence;
o Requirements:
- All under Scenario 1; and
- Compacted tailings specifications;
- Numerical simulation optimized pillars with tailing; and
- Mine sequence evaluation.
· Scenario 4: Pillar-less cut-and-fill mining with cemented paste fill
o A new mining method for the operation where cut-and-fill mining occurs with ground support provided by cemented paste backfill;
· Requirements:
- All under Scenario 1; and
- Paste specifications;
- Numerical modelling of support;
- Trade-off for method implementation; and
- Mine planning including new required infrastructure.

The mine does not produce enough waste rock to backfill all areas previously mined and recover the remaining pillars. The ability to utilize existing and future tailings as backfill may be an attractive option for both the handling of mine tailings and obtaining fill material for pillar recovery.

An additional pillar recovery scenario identified would not require backfill. The scenario is to develop a recovery sublevel in waste directly underneath the vertical pillars as shown in Figure 16-34. The proposed method would serve to undercut the remaining pillars with a recovery sublevel then to drill upholes into the pillars and blast to induce pillar caving. As pillars are recovered, all structural support would be removed, allowing the ground to collapse.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 115

Source: Sierra Metals, 2020

Figure 16-34: Proposed Pillar Recovery Program Scheme

Sierra Metals will carry out a study to determine the feasibility of recovering pillars with the options proposed by SRK, in addition to conducting geomechanical studies for the new and existing areas to change and / or improve the configuration of the mining method that allows us to use paste or other filling, and to not leave pillars during the operation.

16.3.6 Hydrological

A hydrogeological review has not been undertaken by SRK. The mine is currently considered "dry" and has been historically dry with periodic water inflows into the portals due to seasonal rains. Currently, the mine does not require any large-scale dewatering.

16.4 Proposed Mine Plan
16.4.1 Proposed Mine Plan

The conceptual mine plan developed by Sierra Metals is based on the implementation of sub-level stoping throughout the Bolivar Mine. Sierra Metals evaluated the relative advantages of longhole stoping and determined that this method improved mine production in the Bolivar NW and Bolivar West (Lower Area) zones where the dip angle is greater than 30 degrees.

The longhole design was applied to the Bolivar NW mineralized structures. Each level has a vertical height of 20.0 m, a crown pillar of 5.0 m, and is accessed through a ramp to the central part of the level. A stope is then excavated to the floor elevation and initial cutting of the mineralized material begins into the stope and continues with longhole drilling. Mineralized material is extracted and every 45.0 m of advance in the gallery will leave 10.0 m of perpendicular pillar. Figure 16-35 shows a typical section through two stopes.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 116

Source: Sierra Metals, 2020

Figure 16-35: Typical Section Bolivar NW

In Bolivar West, the longhole method will be applied in mineralized bodies with dips greater than 30 degrees. In shallower mineralized bodies, room and pillar methods will be used. For the room and pillar stopes, the mineralized bodies will be extracted with 8.0 m high stopes using 4.0 m high initial drifts, and sill pillars will be left every 16.0 m as shown in Figure 16-36.

Source: Sierra Metals, 2020

Figure 16-36: Typical Room and Pillar Section Bolivar West (Lower Area)

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 117

Drilling

· Drilling is conducted from the mineralized material drive using radial drilling with rod extensions.

Blasting

· ANFO (ammonium nitrate fuel oil), detonating cord, non-electric detonators, and electric delay detonators are used in blasting.

Loading and Hauling

· LHD equipment is used for the extraction, loading and hauling of mineralized material where it is loaded onto trucks for transport to the processing plant.

Ventilation

· Good ventilation conditions are required at the production level to extract diesel fumes and blasting gases. The conceptual ventilation modeling considers the entry of clean air into the mine through ramps that are distributed along the levels and are extracted through ramps.

Ground Support

· The longhole extraction method requires good rock mass conditions in hanging walls and zones of mineralization.
· Crosscut drives at the extraction level are supported with case hardened bolts or bolts and steel mesh.
· When developing in mineralized material, ground supports (bolts, screen, mesh) are used as required.
16.4.2 Dilution and Recovery Factor

Sierra Metals estimated the historic unplanned dilution and mine recovery factors from longhole stoping at Bolivar mine (8% and 95% respectively). Sierra Metals applied these factors to the Indicated and Inferred Resources to determine potential mill feed for consideration in the mine plan.

Mill feed grades (including unplanned dilution and mine recovery) were reported with densities extracted from the SRK model to determine tonnages (dry tonnes). The SRK model considers an average density of 3.4 t/m3 for mineralized material and 2.7 t/m3 for waste.

Planned mining dilution is obtained directly from the optimization exercise and is not applied to the results of the software, unlike the mining recovery, which is applied to the results obtained from the optimization exercise.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 118

Dilution

External dilution (unplanned dilution) is derived from low grade or waste grade material outside the stope design boundaries. This dilution is the result of over-break arising from poor drilling and blasting techniques, adverse geological structures, and failure within zones of adjacent weak rock.

External dilution is expected, even under the best of circumstances, and an allowance was always made for it during the mine planning process.

An external dilution factor of 8% for sub-level stoping at Bolivar was provided by Sierra Metals and is based on historical production information. However, it is recommended that Bolivar develop a robust reconciliation program to better understand the amount of external dilution, and to evaluate mining practices that could be used to reduce dilution

Mining Recovery

Mining recovery can also be described as potential mineralized material loss during the mining process. The principal causes of mineralized material loss are:

· Mineralized material left behind in the form of permanent crown pillars, sill pillars, rib pillars and post pillars;
· Underbreak - the mineralized material is not broken during blasting and remains intact;
· Mineralized material loss within stope - the blasted material is left in the stope due to poor access for the LHD, entrapped by falls of waste rock from walls, left on the floor, or broken material that hangs up on flatter footwalls (footwalls with a shallower dip angle). When using modern software, the permanent pillars are removed from the mineable stope shapes prior to evaluating the in-situ Mineral Resources that may be converted to Mineral Reserves.

Underbreak and material loss within the stope are referred to as mining recovery. Given the selective nature of the sub-level stoping mining method with good LHD access, a mining recovery factor of 95% has been used.

Net Smelter Return (NSR)

The mineral deposits at Bolivar are polymetallic with copper, silver and gold metals contributing to the total value of mineralized material. A net smelter return (NSR) calculation was performed on each block model block considering the grade, metal price, metallurgical recovery and smelter terms. The smelter terms summarized for this report include the applicable concentrate treatment charges, refining charges, deductions, price participation, and penalty element payments.

Metal Prices and Exchange Rate: The metal price assumptions are shown in

Table 16-14 and are based on long-term consensus pricing. The metal price assumptions have been derived from CIBC Global Mining Group Consensus Commodity prices dated September 30, 2020, as provided by Sierra Metals.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 119

Table 16-14: Unit Value Metal Price Assumptions

Cu (US$/lb) Ag (US$/oz) Au (US$/oz)
3.05 20.0 1,541

Source: Sierra Metals, 2020

Metallurgical Recoveries: Metallurgical recoveries were provided by Sierra Metals and are based on projected recoveries resulting from an ongoing mill upgrade program. Table 16-15 summarizes the metallurgical recoveries used in calculating the NSR factors.

Table 16-15: Metallurgical Recoveries

Process Recovery Cu % Ag % Au %
Copper Concentrate 88 78.7 62.43

Source: Sierra Metals, 2020

Net Smelter Return (NSR) Calculation

The parameters used in the NSR calculation are summarized in Table 16-16. An NSR value was calculated for each cell in the block models using these parameters.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 120

Table 16-16: NSR Calculation Parameters

NSR
Parameter Unit Value
Metal Prices
Cu Price US$/lb 3.05
Ag Price US$/oz 20.0
Au Price US$/oz 1,541
Process Recoveries
Cu % 88
Ag % 78.7
Au % 62.43
Concentrate Grades
Cu % 25
Ag g/t 570
Au g/t 6.8
Moisture content % 8
Freight, Insurance and Marketing
Transport losses % 0.5
Transportation US$/wmt 42
Port US$/wmt 9
Load US$/wmt 40
Marketing US$/dmt 10
Insurances US$/wmt 10
Total US$/dmt 102.92
Smelter Terms
Cu payable % 96
Ag payable % 90
Au payable % 92
Cu minimum deduction % 1
Ag minimum deduction oz/t 0
Au minimum deduction oz/t 0
Treatment Charges/Refining Charges (TC/RC)
Cu Concentrate TC US$/dmt 69.00
Cu Refining charge US$/lb Cu 0.069
Cu Refining cost US$/t Cu 152.12
Cu Price Participation US$/dmt 0
Average Penalties US$/dmt 10
Ag Refining charge US$/oz 0.35
Au Refining charge US$/oz 6
Total treatment cost US$/t Cu 727.68
Total cost of sales US$/t Cu 879.80
Net Smelter Return Factors
Cu US$/t/% 48.8171
Ag US$/t/g/t 0.4444
Au US$/t/g/t 28.1940

Source: Sierra Metals, 2020

The resulting NSR equation coded into the block model was:

NSR = 48.8171 X Copper Grade + 0.4444 X Silver Grade + 28.1940 X Gold Grade

The cut-off value calculation used by Sierra Metals in the proposed mine plan is based on historical information and considers reducing production costs associated with increased production (Table 16-17). Conceptual economic envelopes vary according to direct and indirect mining costs, processing costs, concentrate shipment, and general and administration (G&A) costs.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 121

Non-isolated mining blocks with an average NSR value above the economic cut-off value ($20.35/t) and with existing access are classified as economic and included in the conceptually economic envelope. Mining blocks that do not meet the criteria described above are classified as waste. A cost breakdown used for the cut-off calculation, including mining, processing plant and G&A costs, is given in Table 16-17

Table 16-17: NSR Calculation Parameters - Site Operating Costs Per Tonne

Cost Element Cost per Tonne
Mine Cost ($/t) $ 12.27
Plant Cost ($/t) $ 6.22
G & A $ 1.87
Economic Cut-Off ($/t) $ 20.35

Source: Sierra Metals, 2020

Stope Evaluation

Sierra Metals utilized design-based resource estimation of the stopes using geological block models and Deswik™ software. The SO Stope Optimization tool (Deswik.SO) was used for production stopes and for sequencing production and mine development, Deswik.Sched was used. Table 16-18 shows the parameters for sub-level stoping.

Table 16-18: Parameters for Sub-Level Stoping Mining Method

Mining Method Parameter Sub-Level Stoping Unit
Minimum Stope Length (m) 3 m
Stope Height (m) According to each OB m
Stope Width (m) According to each OB m
Pillar Width (m) According to each OB m
Minimum Stope Dip (°) 40 °
Maximum Stope Dip (°) 90 °
Span (m) According to each OB m
Stope Orientation Perpendicular to mineralized zones °
Marginal Cut Off 20.35 $/t

Source: Sierra Metals, 2020

16.5 Mineable Inventory

The mineable inventory provides the basis for the various life of mine (LOM) production scenarios described in this PEA report which range from 5,000 tpd (base case) up to 12,000 tpd. The mineable inventory consists of the Mineral Resource Estimate (Table 16-19) and tonnes and grade for each stope shape were further processed in spreadsheets to apply the mining recovery (95%) and external dilution (8% at 0 grade) as shown in Table 16-20.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 122

Table 16-19: Resource Report

Source: Sierra Metals, 2020

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 123

Table 16-20: Mineable Inventory

Source: Sierra Metals, 2020

The combined total for the mineable inventory is the sum of the mineralized material in Table 16-20 which is approximately 41.8 M tonnes.

16.6 Mine Design

The mine design is formulated to integrate the main mining areas. Currently there are two mine openings for access to trucks, one in the Bolivar Mine accessing the Bolivar West and Bolivar NW areas and a second in the Fierro Mine accessing the El Gallo, Skarn, and Chimeneas areas.

The main dimensions are:

· Ramps will have a cross-section of 5.0 m x 5.0 m (width x height);
CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 124
· Access to mining areas will have cross-sectional dimensions of 4.0 m x 4.0 m (width x height);
· The ventilation raisebore holes have a diameter of 3.0 m;
· Maximum ramp gradient of 12%;
· Truck loading station and drains will be installed in the main accesses; and
· In order to improve the productivity of the haulage equipment, mineralized material passes (ø 3 m) will be built and electro-hydraulic hoppers will be installed to load mineralized material directly into the trucks.

Sierra Metals estimates that 163,813 m of combined horizontal and vertical development meters are required to achieve the mine plans proposed in this PEA (Table 16-21 and Figure 16-37).

Table 16-21: Bolivar Mine - Development Meters in the LOM Plan

Development Type Meters
Horizontal 159,225
Vertical 4,588
Total 163,813

Source: Sierra Metals, 2020

Source: Sierra Metals, 2020

Figure 16-37: Mine Design and Mineralized Areas

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 125
16.7 Mine Production Schedule (Base Case)

Sierra Metals prepared LOM production and development plans based on production rates ranging from a base case of 5,000 tpd to 15,000 tpd (Table 16-22) and these production schedules are financially evaluated in Section 21.3.

Table 16-22: LOM Production Rates

Tonnes/Day (tpd) Tonnes/Year (t/y) Comments
5,000 (base case) 1.8 M Constant production rate through LOM
7,000 2.5 M Increases from 5,000 tpd to 7,000 tpd in 2024
10,000 3.6 M Reaches 10,000 tpd in 2024
10,000 3.6 M Reaches 10,000 tpd in 2026
12,000 4.3 M Reaches 12,000 tpd in 2024
12,000 4.3 M Reaches 12,000 tpd in 2026
15,000 5.4 M Reaches 15,000 tpd in 2024

Source: Sierra Metals, 2020

The base case LOM production and development schedule generated for the Bolivar mineable inventory based on 5,000 tpd (1.8 M t/y) is shown in Table 16-23, Figure 16-38, Figure 16-39 and Table 16-24.

The start date of this schedule is January 2020 as this is the month immediately following the cut-off date of the mined-out data used in this report. Typical mining rates of 5,000 tpd mineralized material and 500 tpd waste were applied as these are the rates the mine has been reportedly operating at in early 2020. The mine has made significant improvements to the on-site management team and increased its engineering resources in 2019, and the mine has greatly improved the mechanical availability of its underground mining fleet which has allowed for increases in daily production.

LOM production and development tables and figures for the production rates greater than the base case (shown in Table 16-22) are provided in the following pages (Table 16-23 to Table 16-36, and Figure 16-40 to Figure 16-51).

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 126

Table 16-23: LOM Production Schedule for 5,000 Tonnes/Day

Production Mine Años 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 Total
Tonnes Ore t 1,800,000 1,800,000 1,800,000 1,800,000 1,800,000 1,800,000 1,800,000 1,800,000 1,800,000 1,800,000 1,800,000 1,800,000 1,800,000 1,800,000 1,800,000 1,800,000 1,800,000 1,800,000 1,800,000 1,800,000 1,800,000 1,800,000 1,800,000 398,073 41,798,073
Tonnes Waste t 376,101 458,721 431,383 376,101 376,101 376,101 376,101 376,101 376,101 376,101 376,101 376,101 376,101 376,101 376,101 376,101 376,101 376,101 376,101 376,101 376,101 320,818 293,481 83,175 8,733,487
Tonnes Total t 2,176,101 2,258,721 2,231,383 2,176,101 2,176,101 2,176,101 2,176,101 2,176,101 2,176,101 2,176,101 2,176,101 2,176,101 2,176,101 2,176,101 2,176,101 2,176,101 2,176,101 2,176,101 2,176,101 2,176,101 2,176,101 2,120,818 2,093,481 481,248 50,531,560
Cu % 0.88 0.88 0.88 0.82 0.72 0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.67 0.62 0.62 0.62 0.72
Ag g/t 20.76 20.58 20.00 19.75 15.39 12.33 12.33 12.33 12.33 12.33 12.33 12.33 12.33 12.33 12.33 12.33 12.33 12.33 12.33 12.33 11.55 9.89 9.89 9.89 13.56
Au g/t 0.11 0.10 0.11 0.08 0.15 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.22 0.25 0.25 0.25 0.19
Cu eq % 1.13 1.13 1.13 1.04 0.95 0.93 0.93 0.93 0.93 0.93 0.93 0.93 0.93 0.93 0.93 0.93 0.93 0.93 0.93 0.93 0.91 0.85 0.85 0.85 0.95
TPD tpd 5,000 5,000 5,000 5,000 5,000 5,000 5,000 5,000 5,000 5,000 5,000 5,000 5,000 5,000 5,000 5,000 5,000 5,000 5,000 5,000 5,000 5,000 5,000 1,106

Source: Sierra Metals, 2020

Source: Sierra Metals, 2020

Source: Sierra Metals, 2020

Figure 16-38: LOM Production - Tonnes, Cu Grade and Cu Equivalent Grade by Year Figure 16-39: LOM Production - Tonnes per Year and Tonnes Per Day

Table 16-24: LOM Development Schedule for 5,000 Tonnes/Day

Total Meters
task Development Años 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 Total
Horizontal m 6,857 8,357 7,857 6,857 6,857 6,857 6,857 6,857 6,857 6,857 6,857 6,857 6,857 6,857 6,857 6,857 6,857 6,857 6,857 6,857 6,857 5,857 5,357 1,516 159,225
Vertical m 198 298 298 198 198 198 198 198 198 198 198 198 198 198 198 198 198 198 198 198 198 98 98 44 4,588
Total m 7,054 8,654 8,154 7,054 7,054 7,054 7,054 7,054 7,054 7,054 7,054 7,054 7,054 7,054 7,054 7,054 7,054 7,054 7,054 7,054 7,054 5,954 5,454 1,560 163,813

Source: Sierra Metals, 2020

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 127

Table 16-25: LOM Production Schedule for 7,000 Tonnes/Day (7,000 tpd in 2024)

Production Mine Años 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 Total
Tonnes Ore t 1,800,000 1,800,000 1,800,000 1,800,000 2,520,000 2,520,000 2,520,000 2,520,000 2,520,000 2,520,000 2,520,000 2,520,000 2,520,000 2,520,000 2,520,000 2,520,000 2,520,000 1,838,073 41,798,073
Tonnes Waste t 376,101 458,721 486,301 655,915 526,541 526,541 526,541 526,541 526,541 526,541 526,541 526,541 526,541 526,541 526,541 525,933 301,462 137,107 8,733,487
Tonnes Total t 2,176,101 2,258,721 2,286,301 2,455,915 3,046,541 3,046,541 3,046,541 3,046,541 3,046,541 3,046,541 3,046,541 3,046,541 3,046,541 3,046,541 3,046,541 3,045,933 2,821,462 1,975,180 50,531,560
Cu % 0.88 0.88 0.88 0.82 0.71 0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.68 0.63 0.62 0.72
Ag g/t 20.76 20.58 20.00 19.75 14.52 12.33 12.33 12.33 12.33 12.33 12.33 12.33 12.33 12.33 12.33 11.84 10.12 9.94 13.56
Au g/t 0.11 0.10 0.11 0.08 0.17 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.20 0.25 0.28 0.19
Cu eq % 1.13 1.13 1.13 1.04 0.94 0.93 0.93 0.93 0.93 0.93 0.93 0.93 0.93 0.93 0.93 0.91 0.86 0.87 0.95
TPD tpd 5,000 5,000 5,000 5,000 7,000 7,000 7,000 7,000 7,000 7,000 7,000 7,000 7,000 7,000 7,000 7,000 7,000 5,106

Source: Sierra Metals, 2020

Source: Sierra Metals, 2020

Source: Sierra Metals, 2020

Figure 16-40: LOM Production - Tonnes, Cu Grade and Cu Equivalent Grade by Year Figure 16-41: LOM Production - Tonnes per Year and Tonnes Per Day

Table 16-26: LOM Development Schedule for 7,000 Tonnes/Day (7,000 tpd in 2024)

Total Meters
Tak Development Años 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 Total
Horizontal m 6,857 8,357 8,857 11,957 9,600 9,600 9,600 9,600 9,600 9,600 9,600 9,600 9,600 9,600 9,600 9,600 5,500 2,502 159,225
Vertical m 198 298 338 358 277 277 277 277 277 277 277 277 277 277 277 177 127 52 4,588
Total m 7,054 8,654 9,194 12,314 9,876 9,876 9,876 9,876 9,876 9,876 9,876 9,876 9,876 9,876 9,876 9,776 5,626 2,554 163,813

Source: Sierra Metals, 2020

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 128

Table 16-27: LOM Production Schedule for 10,000 Tonnes/Day (10,000 tpd in 2024)

Production Mine Años 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 Total
Tonnes Ore t 1,800,000 1,800,000 1,800,000 1,800,000 3,600,000 3,600,000 3,600,000 3,600,000 3,600,000 3,600,000 3,600,000 3,600,000 3,600,000 2,198,073 41,798,073
Tonnes Waste t 376,101 458,721 595,712 804,084 752,201 752,201 752,201 752,201 752,201 752,201 752,201 751,290 324,521 157,652 8,733,487
Tonnes Total t 2,176,101 2,258,721 2,395,712 2,604,084 4,352,201 4,352,201 4,352,201 4,352,201 4,352,201 4,352,201 4,352,201 4,351,290 3,924,521 2,355,725 50,531,561
Cu % 0.88 0.88 0.88 0.82 0.71 0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.64 0.62 0.72
Ag g/t 20.76 20.58 20.00 19.75 13.86 12.33 12.33 12.33 12.33 12.33 12.33 12.33 10.72 9.89 13.56
Au g/t 0.11 0.10 0.11 0.08 0.18 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.24 0.25 0.19
Cu eq % 1.13 1.13 1.13 1.04 0.94 0.93 0.93 0.93 0.93 0.93 0.93 0.93 0.88 0.85 0.95
TPD tpd 5,000 5,000 5,000 5,000 10,000 10,000 10,000 10,000 10,000 10,000 10,000 10,000 10,000 6,106

Source: Sierra Metals, 2020

Source: Sierra Metals, 2020

Source: Sierra Metals, 2020

Figure 16-42: LOM Production - Tonnes, Cu Grade and Cu Equivalent Grade by Year Figure 16-43: LOM Production - Tonnes per Year and Tonnes Per Day

Table 16-28: LOM Development Schedule for 10,000 Tonnes/Day (10,000 tpd in 2024)

Total Meters

Tak Development Años 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 Total
Horizontal m 6,857 8,357 8,857 11,957 9,600 9,600 9,600 9,600 9,600 9,600 9,600 9,600 9,600 9,600 9,600 9,600 5,500 2,502 159,225
Vertical m 198 298 338 358 277 277 277 277 277 277 277 277 277 277 277 177 127 52 4,588
Total m 7,054 8,654 9,194 12,314 9,876 9,876 9,876 9,876 9,876 9,876 9,876 9,876 9,876 9,876 9,876 9,776 5,626 2,554 163,813

Source: Sierra Metals,2020

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 129

Table 16-29: LOM Production Schedule for 10,000 Tonnes/Day (10,000 tpd in 2026)

Production Mine Años 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 Total
Tonnes Ore t 1,800,000 1,800,000 1,800,000 1,800,000 2,520,000 2,520,000 3,600,000 3,600,000 3,600,000 3,600,000 3,600,000 3,600,000 3,600,000 3,600,000 758,073 41,798,073
Tonnes Waste t 376,101 458,721 486,301 655,915 663,957 773,732 752,201 752,201 752,201 752,201 751,897 751,229 450,031 280,477 76,322 8,733,487
Tonnes Total t 2,176,101 2,258,721 2,286,301 2,455,915 3,183,957 3,293,732 4,352,201 4,352,201 4,352,201 4,352,201 4,351,897 4,351,229 4,050,031 3,880,477 834,395 50,531,561
Cu % 0.88 0.88 0.88 0.82 0.71 0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.69 0.62 0.62 0.72
Ag g/t 20.76 20.58 20.00 19.75 14.52 12.33 12.33 12.33 12.33 12.33 12.33 12.33 11.99 10.02 10.15 13.56
Au g/t 0.11 0.10 0.11 0.08 0.17 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.20 0.25 0.31 0.19
Cu eq % 1.13 1.13 1.13 1.04 0.94 0.93 0.93 0.93 0.93 0.93 0.93 0.93 0.91 0.86 0.89 0.95
TPD tpd 5,000 5,000 5,000 5,000 7,000 7,000 10,000 10,000 10,000 10,000 10,000 10,000 10,000 10,000 2,106

Source: Sierra Metals, 2020

Source: Sierra Metals, 2020

Source: Sierra Metals, 2020

Figure 16-44: LOM Production - Tonnes, Cu Grade and

Cu Equivalent Grade by Year

Figure 16-45: LOM Production - Tonnes per Year and Tonnes Per Day

Table 16-30: LOM Development Schedule for 10,000 Tonnes/Day (10,000 tpd in 2026)

Total Meters
Task Development Años 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 Total
Horizontal m 6,857 8,357 8,857 11,957 12,100 14,100 13,714 13,714 13,714 13,714 13,714 13,714 8,214 5,114 1,388 159,225
Vertical m 198 298 338 358 397 467 395 395 395 395 345 235 155 145 73 4,588
Total m 7,054 8,654 9,194 12,314 12,496 14,566 14,109 14,109 14,109 14,109 14,059 13,949 8,369 5,259 1,461 163,813

Source: Sierra Metals, 2020

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 130

Table 16-31: LOM Production Schedule for 12,000 Tonnes/Day (12,000 tpd in 2024)

Production Mine Años 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 Total
Tonnes Ore t 1,800,000 1,800,000 1,800,000 1,800,000 4,320,000 4,320,000 4,320,000 4,320,000 4,320,000 4,320,000 4,320,000 4,220,000 138,073 41,798,073
Tonnes Waste t 376,101 458,721 595,712 883,363 902,641 902,641 902,641 902,641 902,641 902,641 683,030 291,864 28,850 8,733,487
Tonnes Total t 2,176,101 2,258,721 2,395,712 2,683,363 5,222,641 5,222,641 5,222,641 5,222,641 5,222,641 5,222,641 5,003,030 4,511,864 166,923 50,531,561
Cu % 0.88 0.88 0.88 0.82 0.71 0.70 0.70 0.70 0.70 0.71 0.68 0.62 0.62 0.72
Ag g/t 20.76 20.58 20.00 19.75 13.60 12.33 12.33 12.33 12.33 12.56 11.79 10.07 9.89 13.56
Au g/t 0.11 0.10 0.11 0.08 0.19 0.21 0.21 0.21 0.21 0.22 0.22 0.24 0.25 0.19
Cu eq % 1.13 1.13 1.13 1.04 0.94 0.93 0.93 0.93 0.93 0.95 0.92 0.85 0.85 0.95
TPD tpd 5,000 5,000 5,000 5,000 12,000 12,000 12,000 12,000 12,000 12,000 12,000 11,722 384

Source: Sierra Metals, 2020

Source: Sierra Metals, 2020

Source: Sierra Metals, 2020

Figure 16-46: LOM Production - Tonnes, Cu Grade and Cu Equivalent Grade by Year Figure 16-47: LOM Production - Tonnes per Year and Tonnes Per Day

Table 16-32: LOM Development Schedule for 12,000 Tonnes/Day (12,000 tpd in 2024)

Total Meters
Task Development Años 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 Total
Horizontal m 6,857 8,357 10,857 16,107 16,457 16,457 16,457 16,457 16,457 16,457 12,457 5,326 526 159,225
Vertical m 198 298 348 448 474 474 474 474 474 474 324 113 15 4,588
Total m 7,054 8,654 11,204 16,554 16,931 16,931 16,931 16,931 16,931 16,931 12,781 5,439 541 163,813

Source: Sierra Metals, 2020

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 131

Table 16-33: LOM Production Schedule for 12,000 Tonnes/Day (12,000 tpd in 2026)

Production Mine Años 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 Total
Tonnes Ore t 1,800,000 1,800,000 1,800,000 1,800,000 2,520,000 2,520,000 4,320,000 4,320,000 4,320,000 4,320,000 4,320,000 4,320,000 3,638,073 41,798,073
Tonnes Waste t 376,101 458,721 486,301 655,915 691,477 855,927 902,641 902,641 902,641 902,034 693,570 502,208 403,311 8,733,487
Tonnes Total t 2,176,101 2,258,721 2,286,301 2,455,915 3,211,477 3,375,927 5,222,641 5,222,641 5,222,641 5,222,034 5,013,570 4,822,208 4,041,384 50,531,560
Cu % 0.88 0.88 0.88 0.82 0.71 0.70 0.70 0.70 0.70 0.70 0.70 0.68 0.62 0.72
Ag g/t 20.76 20.58 20.00 19.75 14.52 12.33 12.33 12.33 12.33 12.33 12.33 11.66 10.05 13.56
Au g/t 0.11 0.10 0.11 0.08 0.17 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.26 0.19
Cu eq % 1.13 1.13 1.13 1.04 0.94 0.93 0.93 0.93 0.93 0.93 0.93 0.90 0.87 0.95
TPD tpd 5,000 5,000 5,000 5,000 7,000 7,000 12,000 12,000 12,000 12,000 12,000 12,000 10,106

Source: Sierra Metals, 2020

Source: Sierra Metals, 2020

Source: Sierra Metals, 2020

Figure 16-48: LOM Production - Tonnes, Cu Grade and Cu Equivalent Grade by Year Figure 16-49: LOM Production - Tonnes per Year and Tonnes Per Day

Table 16-34: LOM Development Schedule for 12,000 Tonnes/Day (12,000 tpd in 2026)

Total Meters 2500 6500
Task Development Años 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 Total
Horizontal m 6,857 8,357 8,857 11,957 12,600 15,600 16,457 16,457 16,457 16,457 12,657 9,157 7,359 159,225
Vertical m 198 298 338 358 427 497 474 474 474 374 259 259 159 4,588
Total m 7,054 8,654 9,194 12,314 13,026 16,096 16,931 16,931 16,931 16,831 12,916 9,416 7,518 163,813

Source: Sierra Metals, 2020

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 132

Table 16-35: LOM Production Schedule for 15,000 Tonnes/Day (15,000 tpd in 2024)

Production Mine Años 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 Total
Tonnes Ore t 1,800,000 1,800,000 1,800,000 1,800,000 5,400,000 5,400,000 5,400,000 5,400,000 5,400,000 5,400,000 2,198,073 41,798,073
Tonnes Waste t 376,101 458,721 705,062 1,034,327 1,128,302 1,128,302 1,128,302 1,128,302 799,037 579,729 267,306 8,733,487
Tonnes Total t 2,176,101 2,258,721 2,505,062 2,834,327 6,528,302 6,528,302 6,528,302 6,528,302 6,199,037 5,979,729 2,465,379 50,531,560
Cu % 0.88 0.88 0.88 0.82 0.70 0.70 0.70 0.70 0.70 0.66 0.62 0.72
Ag g/t 20.76 20.58 20.00 19.75 13.35 12.33 12.33 12.33 12.33 11.25 9.89 13.56
Au g/t 0.11 0.10 0.11 0.08 0.19 0.21 0.21 0.21 0.21 0.23 0.25 0.19
Cu eq % 1.13 1.13 1.13 1.04 0.94 0.93 0.93 0.93 0.93 0.90 0.85 0.95
TPD tpd 5,000 5,000 5,000 5,000 15,000 15,000 15,000 15,000 15,000 15,000 6,106

Source: Sierra Metals, 2020

Source: Sierra Metals, 2020

Source: Sierra Metals, 2020

Figure 16-50: LOM Production - Tonnes, Cu Grade and Cu Equivalent Grade by Year Figure 16-51: LOM Production - Tonnes per Year and Tonnes Per Day

Table 16-36: LOM Development Schedule for 15,000 Tonnes/Day (15,000 tpd in 2024)

Total Meters
Task Development Años 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 Total
Horizontal m 6,857 8,357 12,857 18,857 20,571 20,571 20,571 20,571 14,571 10,571 4,873 159,225
Vertical m 198 298 348 548 593 593 593 593 393 293 141 4,588
Total m 7,054 8,654 13,204 19,404 21,163 21,163 21,163 21,163 14,963 10,863 5,015 163,813

Source: Sierra Metals, 2020

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 133
16.8 Waste Storage

Currently, development waste material is hauled by LHD and placed into historical workings resulting in approximately 30% to 40% fill factor. Consideration should be given to investing in equipment to pack the waste rock into the stope to improve the fill factor and to increase the amount of underground storage capacity. Historically, approximately 90% of waste material has been stored underground in old mine workings with the remainder sent to surface for use in construction.

For the early stage of development in Bolivar NW and Bolivar West, waste material will be hauled to surface and then hauled for placement underground in El Gallo Inferior and other historical mined out areas. Initial review indicates that the development waste material from these areas can be stored underground in historical mine openings. Further analysis of the initial development waste handling and storage strategy is required. If underground storage in historical mine openings is not a viable solution, due to lack of space or operationally difficult to transfer waste material from the new mining areas to the historical mining areas, then an analysis of the surface storage locations will be required.

16.9 Major Mining Equipment

The major underground mining equipment currently used at Bolivar Mine is listed in Table 16-37.

Table 16-37: Current List of Major Underground Mining Equipment at Bolivar

EQUIPMENT MINE OPERATION (August 2020) Quantity
JBL01 Jumbo Raptor 44 1
JBL02 Jumbo Raptor 44 1
JBF07 Jumbo Development Troidon 66-Xp 1
JBF09 Jumbo Development Troidon 66-Xp 1
JBF10 Jumbo Development Troidon 66-Xp 1
JBA01 Jumbo rock Bolting Bolter 88 1
Total Jumbo Drill 6
ST005 Scooptram ST14 1
ST006 Scooptram ST14 1
ST008 Scooptram ST14 1
ST009 CAT R1700G 1
Total Scooptram 4
CM015 Dumper MT-431 B 1
Trucks 14 m3 9
Total Trucks 10
AM001 Scalers SV-11 1
Total Scaling equipment 1
CF001 Wheel Loader 980 H 1
Total Wheel Loaders 1
AN001 ANFO Loader AL600R 1
Total ANFO Loader equipment 1

Source: Sierra Metals, 2020

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 134

Bolivar Mine also has surface equipment to haul mineralized material to the Piedras Verdes processing plant. This equipment consists of 18-t average capacity trucks (e.g., FMX 440 Volvo, 30-t nominal capacity).

Equipment performance was calculated and validated using actual operational performance data provided by Bolivar Mine. The equipment performance was used to estimate the quantity of equipment required for the production and development plans considered in this PEA. The maximum number of equipment required to meet the production plans is listed by year and shown in Table 16-38 to Table 16-44. The number of underground personnel required to operate the equipment is also listed for reference.

Table 16-38: Main Planned Underground Mining Equipment (5,000 tpd)

Equipment 2020 2021 2022 2023/2040 2041 2042 2043
Jumbo 3 3 3 3 3 3 2
Raptor 3 3 3 3 3 3 2
Scoop 4 4 4 4 4 4 2
Trucks 9 9 9 9 9 9 3
Personal 134 139 138 134 131 129 30

Source: Sierra Metals, 2020

Table 16-39: Main Planned Underground Mining Equipment (7,000 tpd - 2024)

Equipment 2020 2021 2022 2023 2024/2034 2035 2036 2037
Jumbo 3 3 3 4 4 4 3 2
Raptor 3 3 3 3 4 4 4 3
Scoop 4 4 5 5 7 7 6 5
Trucks 9 9 9 9 12 12 12 9
Personal 134 139 141 152 188 188 174 122

Source: Sierra Metals, 2020

Table 16-40: Main Planned Underground Mining Equipment (10,000 tpd - 2024)

Equipment 2020 2021 2022 2023 2024/2032 2032 2033
Jumbo 3 3 4 5 5 3 2
Raptor 3 3 3 3 5 5 4
Scoop 8 yd3 4 4 5 5 8 7 5
Trucks 9 9 9 9 17 17 11
Personal 134 139 148 161 268 242 145

Source: Sierra Metals, 2020

Table 16-41: Main Planned Underground Mining Equipment (10,000 tpd - 2026)

Equipment 2020 2021 2022 2023 2024 2025 2026/2032 2033 2034
Jumbo 3 3 3 4 4 5 5 3 2
Raptor 3 3 3 3 4 4 5 5 2
Scoop 8 yd3 4 4 5 5 7 7 8 7 3
Trucks 9 9 9 9 12 12 17 17 5
Personal 134 139 141 152 196 203 268 239 52

Source: Sierra Metals, 2020

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 135

Table 16-42: Main Planned Underground Mining Equipment (12,000 tpd - 2024)

Equipment 2020 2021 2022 2023 2024/2029 2030 2031 2032
Jumbo 3 3 4 5 5 4 3 2
Raptor 3 3 3 3 6 6 6 2
Scoop 4 4 5 5 10 10 8 2
Trucks 9 9 9 9 20 20 20 2
Personal 134 139 148 166 322 308 278 11

Source: Sierra Metals, 2020

Table 16-43: Main Planned Underground Mining Equipment (12,000 tpd - 2026)

Equipment 2020 2021 2022 2023 2024 2025 2026/2030 2030 2031 2032
Jumbo 3 3 3 4 4 5 5 4 4 3
Raptor 3 3 3 3 4 4 6 6 6 5
Scoop 8 yd3 4 4 5 5 7 7 10 10 10 8
Trucks 9 9 9 9 12 12 20 20 20 17
Personal 134 139 141 152 198 208 322 309 297 249

Source: Sierra Metals, 2020

Table 16-44: Main Planned Underground Mining Equipment (15,000 tpd - 2024)

Equipment 2020 2021 2022 2023 2024/2027 2028 2029 2030
Jumbo 3 3 4 6 6 5 4 3
Raptor 3 3 3 3 7 7 7 4
Scoop 4 4 5 6 12 11 11 5
Trucks 9 9 9 9 25 25 25 11
Personal 134 139 155 175 402 382 368 152

Source: Sierra Metals, 2020

The equipment will be shared for development and production activities. The equipment estimate considers a spare scoop, dumper, jumbo, and truck as contingency. This extra equipment could be used in any mineralized zone as necessary.

An auxiliary mine equipment list was provided by the mine and is listed in Table 16-45 for reference.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 136

Table 16-45: Auxiliary Mining Equipment

Auxiliary Equipment
Pick-up
No Ec 40 Dodge 2014
No Ec 51 Dodge 2014
No Ec 55 Dodge 2014
No Ec 61 Dodge 2014
Nissan Pick Up (Powder Magazine)
No Ec 9 Mitsubishi 2017
No Ec 11 Mitsubishi 2017
No Ec 56 Mitsubishi 2017
No Ec 58 Mitsubishi 2017
Surface Equipment
Truck for personnel 95 No.1 (26P)
Truck for personnel 02 (50P) '76
Sterling Truck 2005 (Water tank)
Freightliner Truck 2007 (Water tank)
Motor Grader 72V16992 Caterpillar 140G
Underground repair
Scissor lifts 4927 Getman A-64
Boart Longyear StopeMaster
Marcotte ANFO Truck M40 Minejack

Source: Sierra Metals, 2020

16.10 Ventilation

In the past, the Bolivar Mine has relied on natural ventilation, and as a result airflow through the mine varied in quantity and direction as the atmospheric conditions on the surface changed. Bolivar personnel have modeled the workings and airflow for the mine in Ventsim™ as illustrated in Figure 16-52.

Source: Sierra Metals, 2020

Figure 16-52: Sierra Metals Ventilation Model for Existing Workings

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 137

As mining progresses into other zones such as Bolivar West, Bolivar NW, and further east in El Gallo Inferior, a forced ventilation system is required, and some ventilation fans have already been installed to provide superior ventilation.

Table 16-46 shows the mine equipment used in determining the mine total airflow under the current operating scenario. Commonly used airflow requirement assumptions of 100 cfm/bhp (0.06 m3/s per kW) was used for equipment and 55 cfm/person (0.026 m3/sec per person) for personnel. The production rate was based on 5,000 tpd.

Table 16-46: Ventilation Requirements for Equipment and Personnel (5,000 tpd)

Item Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Camiones 9 4275 75% 100 3,204 1.5
Raptor/Jumbo 6 600 50% 100 300 0.1
Scoop 4 1180 76% 100 896 0.4
Personal 134 55 7,382 3.5
Total 11,783 5.6

Source: Sierra Metals, 2020

Using the base case LOM production schedule (5,000 tpd), a simplified ventilation model was generated for the three main mining areas. The maximum airflow through the mine was calculated by summing the airflow requirements of the equipment and personnel working in each zone at peak production. An additional 10% was then added for contingency (losses). It was assumed that all vehicles would be turned off when not in use for extended periods. The ventilation requirements by year are shown in Table 16-47.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 138

Table 16-47: Ventilation Requirements by Year (5,000 tpd)

2020 Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Volquete 9 3780 75% 100 283,332 133.7
Raptor/Jumbo 6 600 50% 100 29,982 14.2
Scoop 4 1180 76% 100 89,627 42.3
Personal 134 55.1 7,382 3.5
Total + 10% perdidas 451,355 213.0

2021 Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Volquete 9 3780 75% 100 283,332 133.7
Raptor/Jumbo 6 600 50% 100 29,982 14.2
Scoop 4 1180 76% 100 89,627 42.3
Personal 139 55 7,658 3.6
Total + 10% perdidas 451,658 213.2

2022 Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Volquete 9 3780 75% 100 283,332 133.7
Raptor/Jumbo 6 600 50% 100 29,982 14.2
Scoop 4 1180 76% 100 89,627 42.3
Personal 138 55 7,603 3.6
Total + 10% perdidas 451,597 213.1

2023-2041 Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Volquete 9 3780 75% 100 283,332 133.7
Raptor/Jumbo 6 600 50% 100 29,982 14.2
Scoop 4 1180 76% 100 89,627 42.3
Personal 134 55 7,382 3.5
Total + 10% perdidas 451,355 213.0

2042 Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Volquete 9 3780 75% 100 283,332 133.7
Raptor/Jumbo 6 600 50% 100 29,982 14.2
Scoop 4 1180 76% 100 89,627 42.3
Personal 129 55 7,107 3.4
Total + 10% perdidas 451,052 212.9

2043 Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Volquete 3 1260 75% 100 94,444 44.6
Raptor/Jumbo 4 400 50% 100 19,988 9.4
Scoop 2 590 76% 100 44,813 21.1
Personal 30 55 1,653 0.8
Total + 10% perdidas 176,988 83.5

Source: Sierra Metals, 2020

According to the mining plans developed by Sierra Metals, the ventilation requirements were determined per year for the daily production rates of 7,000 tpd, 10,000 tpd, 12,000 tpd and 15,000 tpd, reaching the maximum production rates in the years 2024 to 2026. The air requirements for these production rates are shown in Table 16-48 to Table 16-53. Figure 16-53 and Figure 16-54 show the ventilation development design for 12,000 tpd for the years 2020 to 2023, and 2024-2032 respectively.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 139

Table 16-48: Ventilation Requirements by Year (7,000 tpd - 2024)

2020 Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Camiones 9 3780 75% 100 283,332 133.7
Raptor/Jumbo 6 600 50% 100 29,982 14.2
Scoop 4 1180 76% 100 89,627 42.3
Personal 134 55 7,382 3.5
Total+ perdidas 10% 451,355 213.0

2021 Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Camiones 9 3780 75% 100 283,332 133.7
Raptor/Jumbo 6 600 50% 100 29,982 14.2
Scoop 4 1180 76% 100 89,627 42.3
Personal 139 55 7,658 3.6
Total+ perdidas 10% 451,658 213.2

2022 Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Camiones 9 3780 75% 100 283,332 133.7
Raptor/Jumbo 6 600 50% 100 29,982 14.2
Scoop 5 1475 76% 100 112,033 52.9
Personal 141 55 7,768 3.7
Total+ perdidas 10% 476,427 224.8

2023 Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Camiones 9 3780 75% 100 283,332 133.7
Raptor/Jumbo 7 700 50% 100 34,979 16.5
Scoop 5 1475 76% 100 112,033 52.9
Personal 152 55 8,374 4.0
Total+ perdidas 10% 482,590 227.8

2024-2035 Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Camiones 12 5040 75% 100 377,775 178.3
Raptor/Jumbo 8 800 50% 100 39,976 18.9
Scoop 7 2065 76% 100 156,847 74.0
Personal 188 55 10,357 4.9
Total+ perdidas 10% 643,451 303.7

2036 Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Camiones 12 5040 75% 100 377,775 178.3
Raptor/Jumbo 7 700 50% 100 34,979 16.5
Scoop 6 1770 76% 100 134,440 63.4
Personal 174 55 9,586 4.5
Total+ perdidas 10% 612,459 289.0

2037 Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Camiones 9 3780 75% 100 283,332 133.7
Raptor/Jumbo 5 500 50% 100 24,985 11.8
Scoop 5 1475 76% 100 112,033 52.9
Personal 122 55 6,721 3.2
Total+ perdidas 10% 469,778 221.7

Source: Sierra Metals, 2020

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 140

Table 16-49: Ventilation Requirements by Year (10,000 tpd - 2024)

2020 Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Camiones 9 3780 75% 100 283,332 133.7
Raptor/Jumbo 6 600 50% 100 29,982 14.2
Scoop 4 1180 76% 100 89,627 42.3
Personal 134 55.1 7,382 3.5
Total+ perdidas 10% 451,355 213.0

2021 Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Camiones 9 3780 75% 100 283,332 133.7
Raptor/Jumbo 6 600 50% 100 29,982 14.2
Scoop 4 1180 76% 100 89,627 42.3
Personal 139 55 7,658 3.6
Total+ perdidas 10% 451,658 213.2

2022 Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Camiones 9 3780 75% 100 283,332 133.7
Raptor/Jumbo 7 700 50% 100 34,979 16.5
Scoop 5 1475 76% 100 112,033 52.9
Personal 148 55 8,153 3.8
Total+ perdidas 10% 482,347 227.6

2023 Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Camiones 9 3780 75% 100 283,332 133.7
Raptor/Jumbo 8 800 50% 100 39,976 18.9
Scoop 5 1475 76% 100 112,033 52.9
Personal 161 55 8,870 4.2
Total+ perdidas 10% 488,632 230.6

2024-2031 Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Camiones 17 7140 75% 100 535,182 252.6
Raptor/Jumbo 10 1000 50% 100 49,970 23.6
Scoop 8 2360 76% 100 179,253 84.6
Personal 268 55 14,764 7.0
268 857,087 404.5

2032 Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Camiones 17 7140 75% 100 535,182 252.6
Raptor/Jumbo 8 800 50% 100 39,976 18.9
Scoop 7 2065 76% 100 156,847 74.0
Personal 242 55 13,332 6.3
Total+ perdidas 10% 819,871 386.9

2033 Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Camiones 11 4620 75% 100 346,294 163.4
Raptor/Jumbo 6 600 50% 100 29,982 14.2
Scoop 5 1475 76% 100 112,033 52.9
Personal 145 55 7,988 3.8
Total+ perdidas 10% 545,928 257.6

Source: Sierra Metals, 2020

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 141

Table 16-50: Ventilation Requirements by Year (10,000 tpd - 2026)

2020 Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Camiones 9 3780 75% 100 283,332 133.7
Raptor/Jumbo 6 600 50% 100 29,982 14.2
Scoop 4 1180 76% 100 89,627 42.3
Personal 134 55 7,382 3.5
Total+ perdidas 10% 451,355 213.0

2021 Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Camiones 9 3780 75% 100 283,332 133.7
Raptor/Jumbo 6 600 50% 100 29,982 14.2
Scoop 4 1180 76% 100 89,627 42.3
Personal 139 55 7,658 3.6
Total+ perdidas 10% 451,658 213.2

2022 Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Camiones 9 3780 75% 100 283,332 133.7
Raptor/Jumbo 6 600 50% 100 29,982 14.2
Scoop 5 1475 76% 100 112,033 52.9
Personal 141 55 7,768 3.7
Total+ perdidas 10% 476,427 224.8

2023 Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Camiones 9 3780 75% 100 283,332 133.7
Raptor/Jumbo 7 700 50% 100 34,979 16.5
Scoop 5 1475 76% 100 112,033 52.9
Personal 152 55 8,374 4.0
Total+ perdidas 10% 482,590 227.8

2024-2025 Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Camiones 12 5040 75% 100 377,775 178.3
Raptor/Jumbo 8 800 50% 100 39,976 18.9
Scoop 7 2065 76% 100 156,847 74.0
Personal 196 55 10,798 5.1
Total+ perdidas 10% 643,936 303.9

2026-2032 Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Camiones 17 7140 75% 100 535,182 252.6
Raptor/Jumbo 10 1000 50% 100 49,970 23.6
Scoop 8 2360 76% 100 179,253 84.6
Personal 268 55 14,764 7.0
Total+ perdidas 10% 857,087 404.5

2033 Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Camiones 17 7140 75% 100 535,182 252.6
Raptor/Jumbo 8 800 50% 100 39,976 18.9
Scoop 7 2065 76% 100 156,847 74.0
Personal 239 55 13,167 6.2
Total+ perdidas 10% 819,689 386.8

2034 Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Camiones 5 2100 75% 100 157,406 74.3
Raptor/Jumbo 4 400 50% 100 19,988 9.4
Scoop 3 885 76% 100 67,220 31.7
Personal 52 55 2,865 1.4
Total+ perdidas 10% 272,227 128.5

Source: Sierra Metals, 2020

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 142

Table 16-51: Ventilation Requirements by Year (12,000 tpd - 2024)

2020 Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Camiones 9 3780 75% 100 283,332 133.7
Raptor/Jumbo 6 600 50% 100 29,982 14.2
Scoop 4 1180 76% 100 89,627 42.3
Personal 134 55 7,382 3.5
Total+ perdidas 10% 451,355 213.0

2021 Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Camiones 9 3780 75% 100 283,332 0.0
Raptor/Jumbo 6 600 50% 100 29,982 0.0
Scoop 4 1180 76% 100 89,627 0.0
Personal 139 55 7,658 0.0
Total+ perdidas 10% 451,658 0.0

2022 Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Camiones 9 3780 75% 100 283,332 133.7
Raptor/Jumbo 7 700 50% 100 34,979 16.5
Scoop 5 1475 76% 100 112,033 52.9
Personal 148 55 8,153 3.8
Total+ perdidas 10% 482,347 227.6

2023 Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Camiones 9 3780 75% 100 283,332 133.7
Raptor/Jumbo 8 800 50% 100 39,976 18.9
Scoop 5 1475 76% 100 112,033 52.9
Personal 166 55 9,145 4.3
Total+ perdidas 10% 488,935 230.8

2024-2029 Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Camiones 20 8400 75% 100 629,626 297.2
Raptor/Jumbo 11 1100 50% 100 54,967 25.9
Scoop 10 2950 76% 100 224,067 105.7
Personal 322 55 17,739 8.4
Total+ perdidas 10% 1,019,039 480.9

2030 Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Camiones 20 8400 75% 100 629,626 297.2
Raptor/Jumbo 10 1000 50% 100 49,970 23.6
Scoop 10 2950 76% 100 224,067 105.7
Personal 308 55 16,968 8.0
Total+ perdidas 10% 1,012,694 477.9

2031 Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Camiones 20 8400 75% 100 629,626 297.2
Raptor/Jumbo 9 900 50% 100 44,973 21.2
Scoop 8 2360 76% 100 179,253 84.6
Personal 278 55 15,315 7.2
Total+ perdidas 10% 956,085 451.2

2032 Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Camiones 2 840 75% 100 62,963 29.7
Raptor/Jumbo 4 400 50% 100 19,988 9.4
Scoop 2 590 76% 100 44,813 21.1
Personal 11 55 606 0.3
Total+ perdidas 10% 141,207 66.6

Source: Sierra Metals, 2020

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 143

Table 16-52: Ventilation Requirements by Year (12,000 tpd - 2026)

2020 Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Camiones 9 4275 75% 100 320,435 151.2
Raptor/Jumbo 6 600 50% 100 29,982 14.2
Scoop 4 1180 76% 100 89,627 42.3
Personal 134 55 7,382 3.5
Total+ perdidas 10% 492,168 232.3

2021 Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Camiones 9 4275 75% 100 320,435 151.2
Raptor/Jumbo 6 600 50% 100 29,982 14.2
Scoop 4 1180 76% 100 89,627 42.3
Personal 139 55 7,658 3.6
Total+ perdidas 10% 492,471 232.4

2022 Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Camiones 9 4275 75% 100 320,435 151.2
Raptor/Jumbo 6 600 50% 100 29,982 14.2
Scoop 5 1475 76% 100 112,033 52.9
Personal 141 55 7,768 3.7
Total+ perdidas 10% 517,240 244.1

2023 Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Camiones 9 4275 75% 100 320,435 151.2
Raptor/Jumbo 7 700 50% 100 34,979 16.5
Scoop 5 1475 76% 100 112,033 52.9
Personal 141 55 7,768 3.7
Total+ perdidas 10% 522,736 246.7

2024 Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Camiones 12 5700 75% 100 427,246 201.6
Raptor/Jumbo 8 800 50% 100 39,976 18.9
Scoop 7 2065 76% 100 156,847 74.0
Personal 198 55 10,908 5.1
Total+ perdidas 10% 698,475 329.6

2025 Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Camiones 12 5700 75% 100 427,246 201.6
Raptor/Jumbo 9 900 50% 100 44,973 21.2
Scoop 7 2065 76% 100 156,847 74.0
Personal 208 55 11,459 5.4
Total+ perdidas 10% 704,578 332.5

2026-2031 Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Camiones 20 9500 75% 100 712,077 336.1
Raptor/Jumbo 11 1100 50% 100 54,967 25.9
Scoop 10 2950 76% 100 224,067 105.7
Personal 322 55 17,739 8.4
Total+ perdidas 10% 1,109,735 523.7

2032 Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Camiones 17 8075 75% 100 605,265 285.7
Raptor/Jumbo 8 800 50% 100 39,976 18.9
Scoop 8 2360 76% 100 179,253 84.6
Personal 249 55 13,718 6.5
Total+ perdidas 10% 922,034 435.2

Source: Sierra Metals, 2020

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 144

Table 16-53: Ventilation Requirements by Year (15,000 tpd - 2024)

2020 Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Camiones 9 3780 75% 100 283,332 133.7
Raptor/Jumbo 6 600 50% 100 29,982 14.2
Scoop 4 1180 76% 100 89,627 42.3
Personal 134 55 7,382 3.5
Total+ perdidas 10% 451,355 213.0

2021 Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Camiones 9 3780 75% 100 283,332 0.0
Raptor/Jumbo 6 600 50% 100 29,982 0.0
Scoop 4 1180 76% 100 89,627 0.0
Personal 139 55 7,658 0.0
Total+ perdidas 10% 451,658 0.0

2022 Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Camiones 9 3780 75% 100 283,332 133.7
Raptor/Jumbo 7 700 50% 100 34,979 16.5
Scoop 5 1475 76% 100 112,033 52.9
Personal 155 55 8,539 4.0
Total+ perdidas 10% 482,772 227.8

2023 Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Camiones 9 3780 75% 100 283,332 133.7
Raptor/Jumbo 9 900 50% 100 44,973 21.2
Scoop 6 1770 76% 100 134,440 63.4
Personal 175 55 9,641 4.6
Total+ perdidas 10% 519,624 245.2

2024-2027 Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Camiones 25 10500 75% 100 787,032 371.4
Raptor/Jumbo 13 1300 50% 100 64,961 30.7
Scoop 12 3540 76% 100 268,880 126.9
Personal 402 55 22,147 10.5
Total+ perdidas 10% 1,257,322 593.4

2028 Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Camiones 25 10500 75% 100 787,032 371.4
Raptor/Jumbo 12 1200 50% 100 59,964 28.3
Scoop 11 3245 76% 100 246,474 116.3
Personal 382 55 21,045 9.9
Total+ perdidas 10% 1,225,966 578.6

2029 Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Camiones 25 10500 75% 100 787,032 371.4
Raptor/Jumbo 11 1100 50% 100 54,967 25.9
Scoop 11 3245 76% 100 246,474 116.3
Personal 368 55 20,273 9.6
Total+ perdidas 10% 1,219,621 575.6

2030 Unid HP Utilización CFM/pers CFM/HP Total [CFM] Total [m3/s]
Camiones 11 4620 75% 100 346,294 163.4
Raptor/Jumbo 7 700 50% 100 34,979 16.5
Scoop 5 1475 76% 100 112,033 52.9
Personal 152 55 8,374 4.0
Total+ perdidas 10% 551,849 260.4

Source: Sierra Metals, 2020

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 145

Source: Sierra Metals, 2020

Figure 16-53: Bolivar W/Bolivar NW/El Gallo Inferior Key Ventilation Development Layout 2020-2023 Mine Production 12,000 tpd

Source: Sierra Metals, 2020

Figure 16-54: Bolivar W/Bolivar NW/El Gallo Inferior Key Ventilation Development Layout 2024-2032 Mine Production 12,000 tpd

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 146
17 Recovery Methods
17.1 Process Description

Bolivar's Piedras Verdes processing plant has been in operation since late 2011. Prior to late 2011, no processing facilities were available on site, and the ore was trucked to the Cusi Mine's Malpaso Mill located 270 km by road.

Sierra Metals operates the Piedras Verdes conventional concentration plant consisting of crushing, grinding, flotation and concentrate thickening and filtration processes. Flotation tails are placed into a conventional tailings storage facility. Bolivar is also planning to install a magnetic separation circuit to recover magnetite from both flotation tailings and existing old tailings.

A simplified block diagram of the processing plant is shown in Figure 17-1.

Source: Sierra Metals, 2021

Figure 17-1: Piedras Verdes Mill - Block Diagram

17.1.1 Crushing Stage

The crushing stage is supplied with mineralized material hauled from the mine site using contractor operated haul trucks. A typical haul truck has approximately 20 tonnes capacity and delivers mineralized material from the mine area to the primary crusher's mineralized material stockpiling area. Trucks can dump directly to the primary crusher or alternatively, to one of several stockpiles. Typically, a front-end loader reclaims mineralized material from the stockpiles and then feeds the jaw crusher.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 147

The crushing plant is fed through a hopper equipped with a 20-inch x 20-inch static grizzly that discharges to a jaw crusher operating in open circuit. The nominal four-inch material discharging from the jaw crusher is classified by two double-deck vibrating screens. The top screen is two inches by one inch and the bottom screen is 3/4 inch by 3/8 inch. Material smaller than 3/8 inch becomes the final crushed product that is transferred to two silos of 1,000 tonnes capacity each and one new silo of 2,000 tonnes capacity. The vibrating screen's oversize feeds a secondary crushing stage consisting of two cone crushers. The top screen is conveyed to a Sandvik HC660 cone crusher and the bottom screen oversize is conveyed to a Metso HP-400 cone crusher. The cone crusher's discharge joins the primary crusher's discharge and feeds the double-deck vibrating screens.

17.1.2 Grinding Circuit

Feed to the grinding circuit is sourced from two 1,000 tonne silos and one 2,000 tonne silo that hold the final crushed product from the crushing plant. The grinding circuit consists of conventional ball mills operating in closed-circuit operation with hydrocyclones. Two 9.5 ft x 14 ft ball mills and one 12 ft x 15.5 ft ball mill operate in parallel, each one in closed circuit with a hydrocyclone cluster. The hydrocyclones were changed from D26 to D20 to improve plant stability. The product size in the cyclone overflow ranges between 34% and 48% passing 75 micrometers, with an average size of 43.5% passing 75 micrometers. The hydrocyclone overflow feeds the flotation circuit. The hydrocyclone underflow stream is returned to the ball mills for further size reduction.

17.1.3 Flotation Circuit

The flotation circuit operates three identical parallel flotation lines. Each flotation line includes a 12 ft x 12 ft flash flotation tank and three DR 300 ft3 rougher flotation cells. From the rougher cells, the overflow feeds the cleaning cells. The cleaning flotation cells consist of two DR 300 ft3 primary cleaner flotation cells, three Sub A 100-ft3 secondary flotation cells and two Sub A 100 ft3 tertiary cleaning flotation cells. The rougher flotation tails feed the rougher-scavenger stage which consists of four DR 300 ft3 flotation cells. The final copper concentrate typically comes from the flash flotation and second cleaner flotation product. Tails from the rougher-scavenger cells become the processing plant's final tails.

17.1.4 Thickening and Filtration

The flotation concentrate is thickened in one 40 ft x 10 ft thickener and one 50 ft x 10 ft thickener before being dewatered using one new pressure filter of 200 tonne of concentrate/day capacity. Solids are thickened to greater than 40%-45% solids by weight in the thickener underflow and filtered using a Clever filter press with 30 plates 1200 mm x 1200 mm dimension. Filtrate from the filter is recycled back to the thickener and the thickener overflow is recycled back to the process. The filter copper concentrate contains approximately 9% to 10% moisture. Final flotation tails are pumped to the tailings storage facility where they are classified using hydrocyclones. Process water is reclaimed from the tailings water pond and reused in the process plant.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 148
17.1.5 Magnetite Concentration Circuit (Projected)

A planned magnetite recovery circuit would be fed with the copper flotation circuit's tailings stream and reclaimed old tailings. The old tailings will be reclaimed from the old tailing storage facility using a front-end loader and the old tailings would be delivered to a new repulping and cleaning stage that uses trash screens and agitation tanks.

The cleaned old tailings, along with the fresh flotation tailings stream, would feed a multistage magnetic separation circuit using magnetic drums. The first magnetic separation stage would consist of three drums operating in parallel, and concentrates produced by all three magnetic drums would then feed a first cleaning stage that would consist of a single magnetic drum. The concentrate from the first cleaning stage would then feed a second and final cleaning stage consisting of a single magnetic drum.

The final magnetite concentrate would be thickened and then filtered using a vacuum drum filter, and then stored on site for eventual truck transport off-site.

17.1.6 Tails Storage Facility

Final tails would be generated from the Magnetite Separation Circuit, as shown in Figure 17-1. The tailings would be thickened for water recovery and the thickener's underflow stream would be disposed of in the mine's new tailings storage facility.

17.2 Piedras Verdes Concentrator Performance
17.2.1 Operational Performance

The operational performance for 18 months from July 2018 to December 2019 is in Table 17-1.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 149

Table 17-1: Piedras Verdes Performance - 18-month Period July 2018 to December 2019

Period Mineralized Material Head Grade Cu Head Grade Ag Head Grade Au Metal
recovery Cu
Metal
recovery Ag
Metal
recovery Au
Concentrate solids Concentrate
Cu grade
tonnes % gr/t gr/t % % % Tonnes
Dry
%
Jul-18 86,097 1.01% 16.97 0.17 79.55% 75.32% 67.11% 3,082 22.5%
Aug-18 69,662 0.94% 16.69 0.15 76.22% 74.63% 69.97% 2,233 22.3%
Sep-18 71,931 1.02% 18.13 0.18 78.67% 72.78% 69.19% 2,560 22.6%
Oct-18 91,383 0.90% 17.06 0.19 79.10% 77.67% 64.20% 2,404 27.2%
Nov-18 93,316 0.89% 20.27 0.21 79.50% 78.21% 65.72% 2,689 24.7%
Dec-18 87,945 0.86% 19.65 0.22 79.20% 75.50% 62.96% 2,560 23.5%
Jan-19 83,970 0.79% 14.70 0.16 80.95% 79.66% 68.59% 2,406 22.3%
Feb-19 93,050 0.83% 19.90 0.24 82.16% 78.37% 62.45% 2,502 25.3%
Mar-19 86,218 0.81% 23.63 0.17 83.54% 79.53% 75.59% 2,369 24.8%
Apr-19 100,433 0.72% 18.32 0.18 81.79% 78.92% 62.52% 2,463 23.9%
May-19 111,767 0.91% 18.03 0.22 83.65% 79.23% 63.98% 3,706 23.0%
Jun-19 114,008 0.95% 17.95 0.30 84.53% 81.81% 65.12% 3,550 25.7%
Jul-19 107,798 0.87% 20.07 0.26 80.68% 80.94% 64.40% 3,502 21.6%
Aug-19 101,751 0.79% 18.00 0.30 80.51% 77.62% 62.96% 2,803 23.2%
Sep-19 122,269 0.90% 23.05 0.36 82.44% 78.61% 60.63% 3,807 24.0%
Oct-19 117,582 0.89% 21.18 0.34 80.49% 75.35% 59.05% 3,011 28.0%
Nov-19 95,078 0.88% 22.60 0.28 88.32% 80.52% 64.96% 3,305 22.3%
Dec-19 135,775 0.85% 19.66 0.32 86.08% 80.34% 63.58% 3,778 26.2%
1,770,032 0.88% 19.35 0.25 81.80% 78.28% 64.76% 52,729 24.1%

Source: Sierra Metals, 2020

Note: Totals may not match due to rounding.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 150

For the 18-month period in reference, mineralized material throughput was 1,770,032 tonnes equivalent to a calendar average of 98,335 t/m or 3,224 tpd. The corresponding head grades were 0.88% Cu, 19.35 g/t Ag, and 0.25 g/t Au.

Overall, the Piedras Verdes concentrator's mineralized material feed shows positive trends in Q4 2019 compared to Q4 2018 (Table 17-2, Figure 17-2 and Figure 17-3):

· Mineralized material throughput increased 28% from average 2,964 tpd in Q4 2018 to 3,787 tpd in Q4 2019.
· Copper head grade decreased by 2%, but the total copper metal content fed to the plant increased by 25% in average after factoring in the mineralized material throughput increase over the same period.
· Silver head grade increased by 10% and the silver metal fed to the mill increased by 41%.
· Gold head grade increased by 54% and the gold metal fed to the mill increased by 97% average.

Table 17-2: Piedras Verdes' Performance Comparison - Q4 2018 and Q4 2019

Stream Units

Q4 2018

(average)

Q4 2019

(average)

Difference
Mineralized material throughput tpd 2,964 3,787 28%
Mineralized material grade Cu % 0.89 0.87 -2%
Mineralized material grade Ag g/t 19.0 21.0 10%
Mineralized material grade Au g/t 0.21 0.32 54%
Mineralized material metal Cu tonnes 2,630.9 3,291.7 25%
Mineralized material metal Ag grams 56,299 79,440 41%
Mineralized material metal Au grams 612 1,203 97%
Metal recovery Cu % 79.27 84.80 7%
Metal recovery Ag % 77.15 78.70 2%
Metal recovery Au % 64.32 62.43 -3%
Concentrate production t/m 2,552 3,390 33%
Concentrate mass-pull % 2.8% 2.9% 3%
Concentrate Cu grade % 25.07 25.43 1.5%
Concentrate Ag grade g/t 522 570 9%
Concentrate Au grade g/t 4.7 6.8 44%
Concentrate Bi grade % 0.21 0.29 41%
Concentrate metal Cu tonnes 640 862 35%
Concentrate metal Ag grams 1,332,279 1,931,580 45%
Concentrate metal Au grams 12,060 23,145 92%

Source: Sierra Metals, 2020

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 151

Source: Sierra Metals, 2020

Figure 17-2: Piedras Verdes - Mineralized Material Throughout (Tonnes) and Copper Head Grade %

Source: Sierra Metals, 2020

Figure 17-3: Piedras Verdes - Mill Feed Head Grade (Cu %, Ag g/t, Au x 10 g/t)

Piedras Verdes' metallurgical performance during the July 2018 to December 2019 period can be observed in Figure 17-4 and is summarized in Table 17-2 for the period Q4 2018 to Q4 2019.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 152

An improvement in metallurgical performance can be observed for the key parameters, which has had a leveraging effect over metal contained in the final copper concentrate production as follows:

· From May 2019 onward, mineralized material throughput increased consistently along with a marginal increase in mass-pull which resulted in an approximate 33% increase in copper concentrate production. Copper concentrate quality remained relatively constant at approximately 25% Cu grade, see Table 17-2.
· A 7% increase in copper recovery along with a 28% mineralized material throughput increase and a marginal copper head grade decrease (-2%) resulted in an overall increment of 35% copper metal content in the final concentrate.
· A 2% increase in silver recovery along with a 28% mineralized material throughput increase and a 10% increase in silver head grade resulted in an overall increment of 45% silver metal content in the final concentrate.
· A 3% decrease in gold recovery along with a 28% mineralized material throughput increase and a 54% increase in gold head grade resulted in an overall increment of 92% gold metal content in the final concentrate.
· Bismuth is the only deleterious element reported. Sierra Metals has not reported paying penalties for Bismuth whose concentration remained below 0.3% in the final copper concentrate for the July 2018 to December 2019 period.

Source: Sierra Metals, 2020

Figure 17-4: Piedras Verdes - Copper Concentrate and Metal Recoveries

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 153
17.2.2 Process Plant, Operating Costs and Consumables

Process plant operating costs for the Q4 2018 to Q4 2019 period are shown in Figure 17-5. The concentrator is achieving significant improvements in terms of cost as follows:

· 2019 started at US$ 10.25/tonne of mineralized material, after a peak of US$ 11.39/tonne of mineralized material in April and decreased to US$ 7.60/tonne of mineralized material in December 2019.
· 2019 started at US$ 0.54/lb Cu equivalent which then peaked at US$ 0.71/lb Cu equivalent in April and decreased to US$ 0.38/lb Cu equivalent in December 2019.

Source: Sierra Metals, 2020

Figure 17-5: Piedras Verdes - Copper Concentrate Operating Cost

A breakdown analysis of consumables and services in Q4 2019 is shown in Figure 17-6. Five cost items account for 75% of the operating cost:

· Other/Undefined account for the largest cost item at 23%,
· Labor and electrical power account for 17% each
· Reagents and mobile equipment rentals account each for 9%

Piedras Verde's cost structure and/or expenditure allocation needs some improvement. It is a good business practice to ensure that other/unclassified items account for a minor portion of the total expenditure. SRK has not reviewed the cost structure and the actual allocation of expenditures.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 154

Source: Sierra Metals, 2020

Figure 17-6: Piedras Verdes - Operating Cost Breakdown Q3 2019

Piedras Verdes' reagents include a combination of the followings: X-343, S-7583, T-100, CC-1065, ZnSO4, X-343, S-7583, T-100, CC-1065, ZnSO4. Reagents account for 9% of the total expenditure during Q4 2019. Steel balls accounted for 4% of the total expenditure in the concentrator.

17.3 Plant Design and Equipment Characteristics

Bolivar uses a conventional copper concentrator plant. The operation is completely manual with no automation or online monitoring being used in the processing circuit. The grinding product, or flotation feed particle size distribution is approximately P80=250 microns.

Tables Table 17-3 and Table 17-4 show the Piedras Verdes Mill's major process equipment, key characteristics, and power ratings.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 155

Table 17-3: Piedras Verdes Mill's Major Process Equipment

Area Equipment Quantity Manufacturer, Model Motor (kW)
Crushing Apron feeder 1 Metso AF5-60MN-16.4 22
Jaw crusher 1 Stedman 93
Cone crusher 1 Sandvik H6800 336
Cone crusher 1 Metso HP-400 298
Vibrating screen 1 Terex Simplicity 6 ft x 16 ft 15
Vibrating screen 1 Diester 6 ft x 1 ft' 20
Grinding Ball mill 1 Dominion 9 ft-6-inch x 14 ft 447
Ball mill 1 Dominion 9 ft-6-inch x 14 ft 447
Ball mill 1 Dominion 12 ft x 15 ft-6-inch 1000
Flotation Flash Flotation cell 3 12 ft x 12 ft 100
Rougher cell 3 x 3 DR 300, 300 ft3 22
Rougher-scavenger cell 3 x 4 DR 300, 300 ft3 22
Cleaning first 3 x 2 DR 300, 300 ft3 22
Cleaning second 3 x 3 Sub-A 100 ft3 11
Cleaning third 3 x 2 Sub-A 100 ft3 11
Thickening Thickener 1 50 ft 15
Thickener 1 40 ft 15
Filtration Filter press 1 Clever 1.2 m x 1.2 m 30 plates 25

Source: Sierra Metals, 2020

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 156

Table 17-4: Piedras Verdes Mill's Magnetic Separation Equipment

Area Equipment Quantity Manufacturer, Model Motor (kW)
Tailings Storage Grizzly Sieve 1 Petimex 4' X 12' 30
Fine hooper 1 IPMC -
TANQUE AGITADOR 20'ø X 20' H Agitator tank 1 - 100
Magnetic Separation Wet, low intensity magnetic separators (magnetic drums) 5 Eriez 38" X 3100 mm 15
Static mixer 2 Ryasa 6"ø -
Thickening & Clarifying Contact thickener 1 IPMC -
High resolution clarifier 1

IPMC 3.375 m X 6.089 m

MOD. AR-39-3043

-
Concentrate Filtering Agitator tank 1 10'ø X 10' h 75
Disks filter 1 NFM Mexico Mod 9, 9ø´disks 25
Belt Conveyor 1 Martin TB-01 10
Vacuum receiver 2 NFM Mexico -
Humidity trap 1 NFM Mexico -
Reactants Flocculant preparer 1 SNF Floeger PPH-15100-02-50 -

17.4 Conclusion and Recommendations

Sierra operates a conventional concentration plant consisting of crushing, grinding, flotation, thickening and filtration of the final concentrate. Thickened flotation tails are placed into a conventional tailings storage facility.

Sierra is implementing a magnetic separation process line to produce commercial quality iron concentrate that is scheduled to begin production in November 2021.

Fresh feed to the Piedras Verdes concentrator has consistently improved its key indicators and performance over the 18-month period from July 2018 to reach 3,787 tpd average during Q4 2019. In addition to the throughput increase, head grades for silver and gold also improved within the same time period reaching 21 g/t silver (+10% increase) and 0.32 g/t gold (+54% increase).

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 157

Copper concentrate produced by Piedras Verdes is of typical commercial quality at approximately 25% Cu throughout the entire period evaluated. Consistently with the throughput and head grades increases, copper concentrate production increased by 33% from approximately 2,500 t/m to 3,400 t/m by Q4 2019.

Concentrate quality also improved: the silver grade increased by approximately 9% from 522 g/t to 570 g/t, and the gold grade increased by 44% from 4.7 g/t to 6.8 g/t. Bismuth is the only deleterious metal reported at values below 0.3% with no penalty payments reported by Sierra Metals.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 158
18 Project Infrastructure

The Bolivar Mine has fully developed infrastructure including access roads, a 329-person man-camp that includes a cafeteria, laundry facilities, maintenance facilities for the underground and surface mobile equipment, electrical shop, guard house, fuel storage, laboratories, warehousing, storage yards, administrative offices, plant offices, truck scales, explosives storage, processing plant and associated facilities, tailings storage facility (TSF), water storage reservoir and water tanks. The site has electric power from the Mexican power grid, backup diesel generators, and heating from site propane tanks. The Bolivar Mine is fully functional and built out for the currently producing mine and mill.

Figure 18-1 shows the general facilities location for the Project.

Source: SRK, 2020

Figure 18-1: Bolivar General Facilities Location

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 159
18.1 Access and Local Communities

Access to the Bolivar Mine is by paved road approximately 305 km southwest from Chihuahua and then approximately 80 km by all-season gravel roads. The Bolivar Mine is located near several small communities namely Cieneguita Lluvia de Oro (population ~500), Piedras Verdes (population ~500), and San José del Pinal (population <10).

The mine is approximately 5 km southeast of the small Ejido community of Piedras Verdes (population ~500) with the offices and camp known as Loma Café located about 2 km to the southwest of Piedras Verdes. The community of Piedras Verdes supports the mine by providing potable water, trash collection and disposal in the nearby Cieneguita landfill, and transportation for construction materials including sand and gravel. The water is supplied by two local springs.

The Bolivar Mine camp supports 329 workers and contractors.

Figure 18-2 shows photographs of the mine camp. Figure 18-3 shows the camp layout.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 160

Source: Sierra Metals, 2020

Figure 18-2: Bolivar Camp - Accommodation Units

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 161

Source: Sierra Metals, 2020

Figure 18-3: Bolivar Camp - Plan Layout

The majority of the project staff live outside the local area in regional cities of Delicias, Parral, Chihuahua, Durango, San Luis Potosi, Creel, Torreon, Sonora and Mexico City. The company provides transportation in buses and vans from transfer locations in the City of Chihuahua, approximately seven hours northeast of the project, and from the community of Choix, Sinaloa, approximately five hours to southwest. Crew changes occur on Tuesday and Wednesday each week.

Personnel living in the region work six days with one day off, usually on Sunday. Personnel living outside the region work 14 days followed by seven days off. Personnel work one of two shifts per day, 7:00 am to 7:00 pm or 7:00 pm to 7:00 am.

The camp is located 2.7 km from the Bolivar Mine, and 8.4 km from the Piedras Verdes processing plant site. The company provides transportation from the camp to the mine or mill in four buses.

18.2 Service Roads

The site has well maintained gravel roads that connect the mine portals, water storage reservoir, camp, and process facilities. The roads between the mine and processing plant are used daily by the fleet of contract trucks that move the ore from the mine ore pads to the processing plant.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 162
18.3 Mine Operations and Support Facilities

The mine is accessed through various portals as described in Section 16. The mine operation is supported by the newer mine camp with rooms, change house facilities, and cafeteria. The mine office is located at the portal to the Bolivar Mine.

There are two mine related surface maintenance facilities. The first is a mine maintenance facility at the portal of the Bolivar Mine, and the second is located near the portal accessing the El Gallo Inferior orebody. A third maintenance facility for the surface equipment is located near the mill. The mine infrastructure includes a compressed air system, located at the main portal to the Bolivar Mine, with compressors and receiving tanks that support the underground operations. Refuge chambers are located in various sections of the underground mine. There are small functional shops underground to support minor equipment repairs and servicing. A medical building is located at the portal to the Bolivar Mine. Explosives storage is in a controlled area located remotely from site.

A photograph of the mine maintenance shop is provided in Figure 18-4.

Source: SRK, 2020

Figure 18-4: Bolivar Maintenance Shop

18.4 New Ore Delivery Tunnel

The mine is in the process of developing a new tunnel that will enable the cost-effective delivery of ore to the Piedras Verdes processing plant. Use of the tunnel will negate the requirement for using surface ore haul trucks. The work is underway and is expected to be completed in 2022. The capital costs for this project are included in the capex figures shown in Section 21.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 163

The tunnel will daylight adjacent to the Piedras Verdes processing plant and will link up underground with the El Gallo Inferior, Bolivar West and Bolivar NW ore zones as shown in Figure 18-5.

Source: Sierra Metals, 2020

Figure 18-5: Isometric View of New Mineralized Material Delivery Tunnel

Use of the new ore delivery tunnel will reduce ore delivery times, transportation costs and will also eliminate the impact of climate and environmental factors such as bad weather, dust, reduced visibility and poorly bermed roads, all of which can lead to accidents with the current surface trucking system. The mine plans to use 30 tonne trucks initially and will consider the use of more cost-effective transportation options in the future (e.g., conveyor belts).

The tunnel lengths and dimensions are shown in Table 18-1.

Table 18-1: Tunnel Dimensions and Lengths

Component

Dimensions

(metres)

Length

(metres)

Main tunnel 5.0 m x 7.0 m 4,200
Bolivar West tunnel 5.0 m x 5.0 m 2,340
El Gallo Inferior tunnel 5.0 m x 5.0 m 2,530

Source: Sierra Metals, 2020

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 164
18.5 Process Support Facilities

The Piedras Verdes processing area has a security building, administrative offices, truck scales, electrical shop, maintenance shop, fuel storage, smaller camp and cafeteria, and the processing facilities are described in Section 17.

Figure 18-6 shows an aerial view of the Piedras Verdes processing plant. Figure 18-7 shows a picture of the inside of the processing plant, and Figure 18-8 shows the tailings storage facility as seen from the processing plant.

Source: Google Maps, 2020

Figure 18-6: Aerial View of the Piedras Verdes Processing Plant

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 165

Source: SRK, 2020

Figure 18-7: Inside the Piedras Verdes Processing Plant

Source: SRK, 2020

Figure 18-8: Piedras Verdes Tailings Storage Facility - Looking South

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 166
18.6 Energy
18.6.1 Propane

The site uses propane for general heating and heating of water in the camp. A local supplier, Equipos Y Gas de la Sierra from Guazapares provides the fuel in 10,000 kg tanker trucks every 15 days. The propane is stored in several tanks on the Project site.

Table 18-2 summarizes the tanks with their location and capacities.

Table 18-2: Propane Tank Location and Capacities

Tank Location Capacity Units
Piedras Verde Plant 4,000 L
Piedras Verde Plant 5,000 L
Camp - Module I 5,000 L
Camp - Module L 135 kg
Camp - Module L 500 kg
Camp - Module N 135 kg
Camp - Module S 500 kg
Camp - Module D 1,000 kg
Laundry 135 kg
Cafeteria 5,000 kg

Source: Sierra Metals, 2020

18.6.2 Power Supply and Distribution

Power to the site is supplied by a 33 kV high voltage power line supplied by the Comisión Federal de la Electricidad (CFE), the state-owned utility. The Bolivar Mine has a substation that feeds the mine and the Piedras Verdes processing plant through a secondary distribution line. The connected load on site is approximately 4 MW. The system operates at a typical load of 2 MW. Backup generation is provided for the mine and processing plant with a diesel-powered generator set. The backup generator, with a capacity of 2,000 kVA is located at the processing plant location.

Figure 18-9 shows the monthly power consumption for the period January 2018 to December 2019.

The plant uses approximately 78% of power consumed with the mine using the remainder. Electricity has varied in unit cost averaged approximately US$0.08/kWh in 2018 and US$0.09/kWh in 2019. The monthly cost for electricity averages US$213,000.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 167

Source: Sierra Metals, 2020

Figure 18-9: Monthly Power Consumption

18.6.3 Fuel Storage

The site has on site diesel storage tanks that supply fuel for the underground and surface mine equipment, as well as the backup electrical generators. The fuel is restocked approximately every three days by with a 10,000 L tanker truck supplied by a local vendor. The tank storage and capacity are summarized in Table 18-3. The average price per liter for diesel and gasoline was MXN$18.54/L and MXN$17.99/L respectively in 2019.

Table 18-3: Fuel Tank Storage and Capacity Summary

Location Tank Quantity Type (units)
Mine Storage Workshop Tank 10,350 Diesel (L)
Mine Tank 9,700 Diesel (L)
Mine Tank 5,510 Gasoline (L)
Plant Storage Processing Tank 1 4,500 Diesel (L)
Processing Tank 2 4,500 Diesel (L)
Processing Tank 3 2,000 Diesel (L)

Source: Sierra Metals, 2020

18.7 Water Supply
18.7.1 Potable Water

Potable water for use at the camp is supplied by the community of Piedras Verde from local springs through the local water utility piping at a rate of 40,000 to 50,000 L/d. The plant uses approximately 2,700 L/d of potable water.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 168
18.7.2 Process Water

The supply water for the Piedras Verdes processing plant is supplied from a nearby Piedras Verdes dam, owned by Dia Bras. The water reservoir has a capacity of 1.5 Mm3 and can meet the plant makeup water requirement of approximately 123,000 m3/month (based on historical usage). The water is pumped from a pump house at the reservoir to an interim 1 Mm3 water tank located near the reservoir. The water tank then supplies water via a pipeline to storage tanks located near the processing plant that have a capacity of 500,000 m3. A photograph of the reservoir is shown in Figure 18-10.

Source: SRK, 2019

Figure 18-10: Piedras Verdes Water Reservoir

The site water usage for 2018 and 2019 are summarized in Table 18-4 and Table 18-5. Approximately 53% of the total process water is recycled.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 169

Table 18-4: Site Water Use (January to December 2018)

Month

Fresh

Water

Recovered

Water

Consumed

Water

Tonnes

Milled

Water Use per

Tonne Processed

(m3) (m3) (m3) (t) (m3/t)
January 67,882 126,066 193,947 83,120 2.33
February 61,483 114,183 175,667 80,581 2.23
March 72,999 135,570 208,570 95,674 2.13
April 71,051 131,952 203,002 93,120 2.33
May 68,921 127,533 196,917 90,329 2.33
June 67,595 125,533 193,128 88,591 2.23
July 65,692 121,999 187,691 86,097 2.33
August 53,152 98,711 151,863 69,662 2.23
September 61,142 91,713 152,854 71,931 2.13
October 47,896 129,496 177,391 91,383 1.94
November 45,286 135,857 181,143 93,316 1.94
December 37,497 141,059 178,555 87,945 2.03
Total 720,594 1,480,134 2,200,729 1,031,750 2.18

Source: Sierra Metals, 2020

Table 18-5: Site Water Use (January to December 2019)

Month

Fresh

Water

Recovered

Water

Consumed

Water

Tonnes

Milled

Water Use per

Tonne Processed

(m3) (m3) (m3) (t) (m3/t)
January 32,950 150,105 183,055 83,970 1.94
February 36,513 166,335 202,848 93,050 2.03
March 33,832 154,123 187,955 86,210 1.78
April 39,410 179,533 218,943 100,433 2.03
May 43,857 199,794 243,652 111,767 2.03
June 44,737 203,802 248,539 114,008 2.17
July 58,750 176,249 234,999 107,798 2.13
August 66,545 155,272 221,817 101,751 2.23
September 93,291 173,255 266,546 122,269 2.33
October 91,600 170,115 261,715 117,582 2.23
November 77,647 134,726 212,373 95,078 2.33
December 93,086 177,349 270,435 125,158 2.13
Total 712,218 2,040,658 2,752,876 1,259,081 2.12

Source: Sierra Metals, 2020

18.8 Site Communications

The site is equipped with a satellite communications system, including telephone and internet, that enables communication between the mine, processing plant and office facilities. A radio system is also in use. The mine also has hardline telephone service.

18.9 Site Security

The site has a separate security force of approximately 12 people with typically four people on each crew. Additionally, there is a Mexican Army base located in close proximity to the Project site. The mine site guard house is located at the entrance to the Bolivar Mine. Another guard house is located near the scales at the processing plant.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 170
18.10 Logistics

The copper concentrates are loaded onto 18-t trucks and shipped by road to the port at Guaymas, Mexico. The concentrate is sold FOB port. The Project produced 31,937 t of concentrate in 2018 (approximately 2,660 t/m). During the first nine months of 2019, concentrate totaled 27,137 t. The 2019 average per month is approximately 3,600 t/m.

The copper concentrate is sampled and placed in a shipping truck, weighed and then covered by a tarpaulin and then shipped 530 km, approximately 10 hours one way, through Bahuichivo to the port of Guaymas, Mexico. All other materials required for the Project are shipped to the site via the road system by truck. Figure 18-11 shows the concentrate trucking route.

Source: Google Maps, 2020

Figure 18-11: Concentrate Trucking Route

18.11 Waste Handling and Management
18.11.1 Waste Management

The site has septic systems to handle wastewater and sewage. The septic system is pumped clean on a quarterly basis. Trash is hauled to a landfill in Cieneguita.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 171
18.11.2 Waste Rock Storage

The site has minimal waste rock storage needs as the majority of the underground waste rock is stored underground. Any waste rock brought to surface is placed in permitted storage areas.

18.12 Tailings Management
18.12.1 Existing Tailings Storage Facility

The existing tailings storage facility (TSF) has been in operation since the Piedras Verdes Mill was commissioned in late 2011. The existing TSF1 and TSF2 can be seen in Figure 18-12 along with expansion areas, TSF3 through TSF5, adjacent to the existing facility.

Source: Sierra Metals, 2020

Figure 18-12: Active Tailings Area Location

The tailings management plan at the Bolivar Mine includes placement of tailings in a number of locations. The site utilized the capacity in TSF2 and TSF3 in 2018 and 2019. The remaining capacity in TSF1 is as contingency capacity. The TSF4 tailings placement was divided to increase volume in 2019.

In general, the existing tailings facility were operated by moving the tailings from the processing plant via pipelines to holding cells on the tailings area near the leading edge of the embankment. Water was drained to the back of the facility (closest to the plant). The multiple cells allow the tailings to drain while new tailings are placed in the next cell. Once drained, the higher density material is moved to the front of the embankment to build the next lift embankment with mobile equipment (excavator and dozer). The construction method is known as "upstream construction."

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 172

The sequence repeats from the front of the embankment across the tailings storage facility (TSF) until the next lift is prepared to raise the TSF to the next level. A sump exists at the bottom of the tailing facility that captures any seep or runoff water and is returned for use at the processing plant.

Figure 18-13 shows the dewatering cells and the general shape of the TSF operational area.

Source: Sierra Metals, 2020

Figure 18-13: TSF Operational Area

The existing permitted facility was inspected by Tierra Group Consultoria in 2019 and recommendations were made to the repair of the existing boards and to maintain the inclination of 30° in berm. Additional work was suggested by Tierra Group Consultoría to maintain a drainage channel to keep water off the edges of the TSF, and to clean up and re-establish the edges of the TSF on solid rock. Dia Bras provided survey data showing the slope corrections and these can be seen in the photograph in Figure 18-14.

SRK does not take any TSF design responsibility as SRK is not the "Engineer on Record" for the design or inspection.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 173

Source: Sierra Metals, 2020

Figure 18-14: Active Tailings Area

18.12.2 Tailings Facility Expansion

Dia Bras contracted with Flopac Ingenieria for the geotechnical evaluation, design, costing and construction of a TSF expansion program that allows the processing of ore beyond the reserves stated in this report. The current status and planned sequence of expansion is described in this section.

Figure 18-15 shows an isometric view of the current TSF and the Flopac Ingenieria study area.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 174

Source: Sierra Metals, 2020

Figure 18-15: Current TSF - Isometric View of Flopac Ingenieria Study Area

As part of the overall management plan, the site is also installing infrastructure to recover additional process water and reduce the water content of the final tailings. Current tailings are approximately 35% solids.

Expansion beyond TSF5 will consist of the construction of a New TSF, located to the west of the existing TSF. This new facility, when complete, will provide capacity beyond 2025 based on the mine's current LoM production schedule.

In summary, tailings consisting of approximately 35% solids have been placed in conventional tailings storage facilities (TSF1-TSF4) in previous years and including 2019. Expansion around the main TSF, in TSF1-TSF5, will be utilized until mid-2020 when dry stack tailings will begin to be placed in the New TSF.

All permits are in place for TSF1 through TSF5, and for the New TSF. Dia Bras allocated US$1 million in 2018 and US$3 million in 2019 for the TSF expansion civil works.

Figure 18-16 shows an isometric view of the new TSF.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 175

Source: Sierra Metals, 2020

Figure 18-16: Isometric View of the New TSF

SRK recommends that an analysis of utilizing tailings as backfill in the underground mine should be carried out, and a trade-off study completed. The underground storage of plant tailings would serve to significantly reduce the TSF volume required for surface storage.

Figure 18-17 shows a plan view of the current TSF and the New TSF locations.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 176

Source: Sierra Metals, 2020

Figure 18-17: Plan View of the Current TSF and New TSF Locations

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 177
18.13 Reprocessing of Old Tailings to Recover Magnetite

Sierra Metals is evaluating a plan to excavate and reprocess legacy (old) tailings for the recovery of magnetite mineral at the Piedras Verdes processing plant. Preliminary test work has shown that that a magnetite recovery plant could potentially produce iron concentrates of up to 68% grade and with a recovery of up to 81%. Sierra Metals is therefore considering the reprocessing of approximately 6 million tonnes of legacy tailings contained in the existing tailings storage facility.

Recovered legacy tailings from the existing tailings storage facility (TSF) would be processed in the proposed Magnetite Recovery portion of the Piedras Verdes processing plant. Tailings coming from the Magnetite Recovery portion of the Piedras Verdes processing plant would be deposited in a new TSF located to the west of the current TSF, as shown in Figure 18-18 and described in Section 18.12.2. The yellow shaded portion of the current TSF shown in Figure 18-18 cannot be recovered and reprocessed due to stability concerns.

Source: Sierra Metals, 2021

Figure 18-18: New TSF for tailings following magnetite recovery

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 178

Following the recovery of magnetite, the tailings would be placed into a new TSF and would be deposited in layers no thicker than 0.30 m and compacted with a roller to a 95% standard proctor test (Figure 18-19).

Source: Sierra Metals, 2021

Figure 18-19: Tailings compaction process in the new TSF

18.14 Back-fill Plant

Sierra Metals is evaluating the construction of a surface back-fill plant and the cost for this has been included in the project economics. The proposed plant would produce paste back-fill that would be used to fill mined out stopes underground and would therefore potentially enable a higher recovery of underground ore and would reduce operating costs by reducing the size of the TSF.

The proposed plan would be to extract tailings from the new TSF and mix it with water to achieve a slurry comprised of 70% water, 30% solids. The slurry would then be pumped to the paste back-fill plant using a 3.2 km long, 6" diameter pipeline and the back-fill plant would be located 150 m from the primary mine entrance (Figure 18-20). At the back-fill plant, the slurried tailings would be dewatered to approximately 40% water content and then cement would be added. Thereafter, the tailings-cement slurry mixture would be pumped into the underground mine where the slurry mixture would be processed through a battery of hydrocyclones and the cyclone underflow, containing approximately 8% water, would be pumped into the empty stopes.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 179

Source: Sierra Metals, 2021

Figure 18-20: Tailings return pipeline to potential back-fill plant

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 180
19 Market Studies and Contracts

Bolivar is an underground mining operation producing commercial quality copper concentrate Bolivar is an underground mining operation producing commercial quality copper concentrate containing payable amounts of copper, silver and gold. The operation is also evaluating the potential for marketing Fe in the form of a magnetite concentrate.

Dia Bras currently holds a contract for the sale of its copper concentrate. Contract terms were reviewed by SRK and they appear reasonable and in line with similar operations that SRK is familiar with.

The metals produced from the Bolivar concentrate are traded on various metals exchanges. LT Metal prices were provided by Sierra Metals and have been derived from the August 2020 CIBC Global Mining Group Analyst Consensus Commodity Price Forecast. For this PEA update, the Fe price was based on the June 2021 Jeffries Commodity Price Forecast. In SRK's opinion the prices used are reasonable for the statement of mineral resources. The metal price assumptions are presented in Table 19-1.

Table 19-1: Forecast Metal Prices for Au, Ag and Cu

Commodity LT Forecasted Prices Unit
Au 1,502 US$/oz
Ag 18.24 US$/oz
Cu 3.05 US$/lb

Source: Sierra Metals, 2020

The forecasted prices for Fe are based on the June 2021 Jeffries Commodity Price Forecast as shown in Table 19-2.

Table 19-2: Forecast Metal Prices for Fe

Year Jeffries June 2021 Forecast Price DMS Price Fe 62% to DMS Ratio Forecast Price Used in Financial Model
($US/tonne, 62% Fe)
2021 153 229.5 100/1 153
2022 125 137.5 50/50 131.25
2023 100 150 80/20 110
2024 95 142.5 80/20 104.5
2025 85 127.5 80/20 93.5
LT 80 120 80/20 88

Source: Sierra Metals, 2021

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 181
20 Environmental Studies, Permitting, and Social or Community Impact
20.1 Environmental Studies and Liabilities

Summaries of some of the environmental studies were provided to SRK, including environmental impact assessment documentation used to support the permitting efforts of the current operation and future tailings storage area.

Based on communications with representatives from Sierra, it does not appear that there are currently any known environmental issues that could materially impact the extraction and beneficiation of mineral resources or reserves.

From previous assessments (Gustavson, 2013), known environmental liabilities include unreclaimed exploration disturbances (i.e., roads, drill pads, etc.) and small residual waste rock piles from historical mining operations, and the current tailings storage facilities would also constitute a reclamation liability for the operation.

As observed by SRK personnel during previous site visits, dust emissions generated as a result of mineralized material haulage traffic from the mine to mill can be an issue, and to address this, the mine has developed a mitigation plan that involves the use of water trucks.

20.2 Environmental Management
20.2.1 Tailings Disposal

Existing Tailings Storage Facility

Currently, Sierra is constructing a raise on TSF embankment using waste rock generated from the Bolivar West underground mining operation. While a stability study was supposedly prepared for this raise, SRK was not provided a copy for this review, though Sierra personnel noted that it did meet with regulatory approval. Since the embankment raise is occurring within an already permitted area, a new Manifesto de Impacto Ambiental or MIA, was not required. The mine has also constructed stormwater diversion channels to reduce the ingress of non-contact stormwater into the impoundment.

Future Tailings Storage Facility

A second tailings storage facility (TSF) location, adjacent to the existing TSF, has been identified and is permitted to receive tailings for at least three years. Any future expansions of this new facility will likely include the relocation of the adjacent federal highway in order to achieve the required capacity. Additionally, Sierra is considering installing a dry stack facility instead of depositing conventional tailings slurry; this approach would increase the capacity of the second TSF.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 182
20.3 Geochemistry

Geochemical characterization of the Bolivar Mine tailings has been conducted annually by a qualified third-party laboratory in Mexico as part of the monitoring and reporting requirements of NOM-141-SEMARNAT-2003. The testing includes leach testing for metals and acid-base accounting (ABA). ABA testing is a static test procedure designed to measure the long-term potential for waste rock and/or tailings to generate acid.

Net-neutralization potential (NNP) consists of two measurements: (1) neutralization potential (NP) and (2) the acid-generating potential (AP). NNP is defined as the difference between these two measurements (NNP = NP - AP). The NP/AP ratio is also used to describe the acid-producing potential of mine waste. ABA classifications for mine-waste samples are based on both NNP and NP/AP and are divided into three categories including acid-generating, uncertain, and non-acid generating.

According to the Nevada Division of Environmental Protection report on Waste Rock, Overburden, and Ore dated February 2014, if the ratio is less than 1.2:1, the material is considered potentially acid generating (PAG). If the ratio is greater than 1.2, no additional testing is required.

The test results for 2014 and 2015 provided to SRK indicate low metals leaching potential and either uncertain or non-acid generating potential. The 2016 ABA results (NP = 52.5 kg CaCO3/ton; AP = 141 kg CaCO3/ton); however, suggest that some of the more recent material may be potentially acid generating: NP/AP = 0.372. Additional investigation of the current materials being deposited into the tailings impoundment may be warranted; however, given the dryness of the Chihuahuan Desert, this may not necessarily be a material issue for the project.

20.3.1 Emission and Waste Management

In 2015, an authorization for the Unique Environmental License (Licencia Ambiental Unica [LAU]) was granted by SEMARNAT to EXMIN in order to carry out mineral processing and other metallurgical activities (beneficiation) at the Bolivar mill site.

The document establishes the environmental obligations to be met by the company. It establishes that EXMIN operations must adhere to the authorizations provided by the LAU in the matter of atmospheric emissions and generation/management of hazardous wastes.

Several key conditions of the LAU include:

· EXMIN must submit its Annual Operating Card (Cédula de Operacion Anual) between March 1st and June 30th of each year;
· Discharges of wastewater to natural water reservoirs or sewers, without CONAGUA approval, is prohibited;
· The operation shall develop and maintain a contingency plan (not reviewed by SRK);
· For point sources of atmospheric emissions (end of pipe), all emission sampling ports shall be installed and maintained in good conditions;
CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 183
· Emissions must meet the Maximum Permissible Limits (Limites Maximos Permisibles [MPL]) established by the NOM-085-SEMARNAT-2011 and NOM-043-SEMARNAT-1193;
· Emissions of Volatile Organic Compounds (VOCs) should be kept to a minimum, since there is not any normative regulating emissions at this time; and
· Records of the operation and maintenance of equipment that generates emissions shall be maintained.
20.4 Mexican Environmental Regulatory Framework
20.4.1 Mining Law and Regulations

Mining in Mexico is regulated through the Mining Law, approved on June 26, 1992, and amended by decree on December 24, 1996, Article 27 of the Mexican Constitution.

Article 6 of the Mining Law states that mining exploration; exploitation and beneficiation are public utilities and have preference over any other use or utilization of the land, subject to compliance with laws and regulations.

Article 19 specifies the right to obtain easements, the right to use the water flowing from the mine for both industrial and domestic use, and the right to obtain a preferential right for a concession of the mine waters.

Articles 27, 37 and 39 rule that exploration; exploitation and beneficiation activities must comply with environmental laws and regulations, and should incorporate technical standards in matters such as mine safety, ecological balance and environmental protection.

The Mining Law Regulation of February 15, 1999 repealed the previous regulation of March 29, 1993. Article 62 of the regulation requires mining projects to comply with the General Environmental Law, its regulations, and all applicable norms.

20.4.2 General Environmental Laws and Regulations

In February 12, 2012, a new Mining Law Regulation was issued and the last amendment of the Mining Law Regulation is dated October 31, 2014. Mexico's environmental protection system is based on the General Environmental Law known as Ley General del Equilibrio Ecológico y la Protección al Ambiente - LGEEPA (General Law of Ecological Equilibrium and the Protection of the Environment), approved on January 28, 1988, and updated on December 13, 1996 and again on June 6, 2012.

The Mexican federal authority over the environment is the Secretaría de Medio Ambiente y Recursos Naturales - SEMARNAT (Secretariat of the Environment and Natural Resources). SEMARNAT, formerly known as SEDESOL, was formed in 1994, as the Secretaría de Medio Ambiente Recursos Naturales y Pesca (Secretariat of the Environment and Natural Resources and Fisheries). On November 30, 2000, the Federal Public Administration Law was amended giving rise to SEMARNAT.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 184

The change in name corresponded to the movement of the fisheries subsector to the Secretaría de Agricultura, Ganadería, Desarrollo Rural, Pesca y Alimentación - SAGARPA (Secretariat of Agriculture, Livestock, Rural Development, Fisheries and Food), through which an increased emphasis was given to environmental protection and sustainable development.

SEMARNAT is organized into a number of sub-secretariats and the following main divisions:

· INECC - Instituto Nacional de Ecología y Cambio Climático (National Institute of Ecology and Climate Change), an entity responsible for planning, research and development, conservation of national protection areas and approval of environmental standards and regulations.
· PROFEPA - Procuraduría Federal de Protección al Ambiente (Federal Attorney General for the Protection of the Environment) responsible for law enforcement, public participation and environmental education.
· CONAGUA - Comisión Nacional del Agua (National Water Commission), responsible for assessing fees related to water use and discharges.
· IMTA - Instituto Mexicano de Tecnología del Agua (Mexican Institute of Water Technology).
· CONANP - Comisión Nacional de Areas Naturales Protegidas (National Commission of Natural Protected Areas).
· CONAFOR - Comisión Nacional Forestal (National Forestry Commission).
· CONABIO - Comisión Nacional para el conocimiento y uso de la Biodiversidad (National Commission for the Knowledge and use of Biodiversity)
· PROFEPA - Procuradoría Federal de Protección al Ambiente (Federal Attorney for Environmental Protection).
· ASEA - Agencia de Seguridad, Energía y Ambiente (Security, Energy and Environment Agency)

The federal delegation or state agencies of SEMARNAT are known as Consejo Estatal de Ecología - COEDE (State Council of Ecology).

PROFEPA is the federal entity in charge of carrying out environmental inspections and negotiating compliance agreements. Voluntary environmental audits, coordinated through PROFEPA, are encouraged under the LGEEPA.

Under LGEEPA, a number of regulations and standards related to environmental impact assessment, air and water pollution, solid and hazardous waste management and noise have been issued. LGEEPA specifies compliance by the states and municipalities and outlines the corresponding duties.

Applicable regulations under LGEEPA include:

· Regulation to LGEEPA on the Matter of Environmental Impact Evaluations, May 30, 2000;
CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 185
· Regulation to LGEEPA on the Matter of Prevention and Control of Atmospheric Contamination, November 25, 1988;
· Regulation to LGEEPA on the Matter of Environmental Audits, November 29, 2000;
· Regulation to LGEEPA on Natural Protected Areas, November 20, 2000;
· Regulation to LGEEPA on Protection of the Environment Due to Noise Contamination, December 6, 1982; and
· Regulation to LGEEPA on the Matter of Hazardous Waste, November 25, 1988.
· Regulation to LGEEPA on the Registration of Emissions and Transfer of Pollutants, June 3, 2004.

Mine tailings are listed in the Regulation to LGEEPA on the Matter of Hazardous Waste. Norms include:

· Norma Official Mexicana (NOM)-CRP-001-ECOL, 1993, which establishes the characteristics of hazardous wastes, lists the wastes, and provides threshold limits for determining its toxicity to the environment;
· NOM-CRP-002-ECOL, 1993 establishes the test procedure for determining if a waste is hazardous;
· On September 13, 2004, SEMARNAT published the final binding version of its new standard on mine tailings and mine tailings dams, NOM-141-SEMARNAT-2003. The new rule has been renamed since the draft version was published in order to better reflect the scope of the new regulation. This NOM sets out the procedure for characterizing tailings, as well as the specifications and criteria for characterizing, preparing, building, operating, and closing a mine tailings dam. This very long (over 50 pages) and detailed standard sets out the new criteria for characterizing tailings as hazardous or non-hazardous, including new test methods. A series of technical annexes address everything from waste classification to construction of the dams. The rule is applicable to all generators of non-radioactive tailings and to all dams constructed after this NOM goes into effect; and
· Existing tailings dams will have to comply with the new standards on post-closure. The NOM formally went into effect 60 days after its publication date.

PROFEPA "Clean Industry"

The Procuraduría Federal de Protección al Ambiente (the enforcement portion of Mexico's Environmental Agency, referred to as PROFEPA), administers a voluntary environmental audit program and certifies businesses with a "Clean Industry" designation if they successfully complete the audit process. The voluntary audit program was established by legislative mandate in 1996 with a directive for businesses to be certified once they meet a list of requirements including the implementation of international best practices, applicable engineering and preventative corrective measures.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 186

In the Environmental Audit, firms contract third-party, PROFEPA-accredited auditors, considered experts in fields such as risk management and water quality, to conduct the audit process. During this audit, called "Industrial Verification," auditors determine if facilities are in compliance with applicable environmental laws and regulations. If a site passes, it receives designation as a "Clean Industry" and is able to utilize the Clean Industry logo as a message to consumers and the community that it fulfills its legal responsibilities. If a site does not pass, the government can close part, or all of a facility if it deems it necessary. However, PROFEPA wishes to avoid such extreme actions and instead prefers to work with the business to create an "Action Plan" to correct problem areas.

The Action Plan is established between the government and the business based on suggestions of the auditor from the Industrial Verification. It creates a time frame and specific actions a site needs to take in order to be in compliance and solve existing or potential problems. An agreement is then signed by both parties to complete the process. When a facility successfully completes the Action Plan, it is then eligible to receive the Clean Industry designation.

PROFEPA believes this program fosters a better relationship between regulators and industry, provides a green label for businesses to promote themselves and reduces insurance premiums for certified facilities. The most important aspect, however, is the assurance of legal compliance through the use of the Action Plan, a guarantee that ISO 14001 and other Environmental Management Systems cannot make.

According to Sierra, the company has initiated the PROFEPA "Clean Industry" application process for the Bolivar plant site in 2018.

20.4.3 Other Laws and Regulations

Water Resources

Water resources are regulated under the National Water Law, December 1, 1992 and its regulation, January 12, 1994 (amended by decree, December 4, 1997). In Mexico, ecological criteria for water quality is set forth in the Regulation by which the Ecological Criteria for Water Quality are Established, CE-CCA-001/89, dated December 2, 1989. These criteria are used to classify bodies of water for suitable uses including drinking water supply, recreational activities, agricultural irrigation, livestock use, aquaculture use and for the development and preservation of aquatic life. The quality standards listed in the regulation indicate the maximum acceptable concentrations of chemical parameters and are used to establish wastewater effluent limits. Ecological water quality standards defined for water used for drinking water, protection of aquatic life, agricultural irrigation and irrigation water and livestock watering are listed.

Discharge limits have been established for particular industrial sources, although limits specific to mining projects have not been developed. NOM-001-ECOL-1996, January 6, 1997, establishes maximum permissible limits of contaminants in wastewater discharges to surface water and national "goods" (waters under the jurisdiction of the CONAGUA).

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 187

Daily and monthly effluent limits are listed for discharges to rivers used for agricultural irrigation, urban public use and for protection of aquatic life; for discharges to natural and artificial reservoirs used for agricultural irrigation and urban public use; for discharges to coastal waters used for recreation, fishing, navigation and other uses and to estuaries; and discharges to soils and to wetlands. Effluent limitations for discharges to rivers used for agricultural irrigation, for protection of aquatic life and for discharges to reservoirs used for agricultural irrigation have also been established.

Sierra constructed a water dam to provide water for use in the process plant and for domestic use (camp, cooking, etc.). SRK did not receive or review the permits related to this activity.

Ecological Resources

In 2000, the National Commission of Natural Protected Areas (CONANP) (formerly CONABIO, the National Commission for Knowledge and Use of Biodiversity) was created as a decentralized entity of SEMARNAT. As of November 2001, 127 land and marine Natural Protected Areas had been proclaimed, including biosphere reserves, national parks, national monuments, flora and fauna reserves, and natural resource reserves.

Ecological resources are protected under the Ley General de Vida Silvestre (General Wildlife Law). (NOM)-059-ECOL-2000 specifies protection of native flora and fauna of Mexico. It also includes conservation policy, measures and actions, and a generalized methodology to determine the risk category of a species.

Other laws and regulations include:

· Forest Law, December 22, 1992, amended November 31, 2001, and the Forest Law Regulation, September 25, 1998;
· Fisheries Law, June 25, 1992, and the Fisheries Law Regulations, September 29, 1999; and
· Federal Ocean Law, January 8, 1986.

Regulations Specific to Mining Projects

All aspects related to Mine Safety and Occupational Health are regulated in Mexico by NOM-023-STPS 2003 issued by the Secretariat of Labor. Appendix D of this regulation refers specifically to ventilation for underground mines, such as Bolivar Mine, and establishes all the requirement underground mines should comply with, which are subject of regular inspections.

New tailings dams are subject to the requirements of NOM-141-SEMARNAT-2003, Standard that Establishes the Requirements for the Design, Construction and Operation of Mine Tailings Dams. Under this regulation, studies of hydrogeology, hydrology, geology and climate must be completed for sites considered for new tailings impoundments. If tailings are classified as hazardous under NOM-CRP-001-ECOL/93, the amount of seepage from the impoundment must be controlled if the facility has the potential to affect groundwater. Environmental monitoring of groundwater and tailings pond water quality and revegetation requirements is specified in the regulations.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 188

NOM-120-ECOL-1997, November 19, 1998 specifies environmental protection measures for mining explorations activities in temperate and dry climate zones that would affect xerophytic brushwood (matorral xerofilo), tropical (caducifolio) forests, or conifer or oak (encinos) forests. The regulation applies to "direct" exploration projects defined as drilling, trenching, and underground excavations. A permit from SEMARNAT is required prior to initiating activities and SEMARNAT must be notified when the activities have been completed. Development and implementation of a Supervision Program for environmental protection and consultation with CONAGUA is required if aquifers may be affected. Environmental protection measures are specified in the regulations, including materials management, road construction, reclamation of disturbance and closure of drillholes. Limits on the areas of disturbance by access roads, camps, equipment areas, drill pads, portals, trenches, etc. are specified.

20.4.4 Expropriations

Expropriation of ejido (an area of communal land mainly used for agriculture) and communal properties is subject to the provisions of agrarian laws. The Bolivar Project is subject to these provisions with respect to Ejido Piedras Verdes, in the Municipality of Urique, in the State of Chihuahua, Mexico.

20.4.5 NAFTA

Canada, the United States and Mexico participate in the North American Free Trade Agreement (NAFTA). NAFTA addresses the issue of environmental protection, but each country is responsible for establishing its own environmental rules and regulations. However, the three countries must comply with the treaties between themselves; and the countries must not reduce their environmental standards as a means of attracting trade.

20.4.6 International Policy and Guidelines

International policies and/or guidelines that may be relevant to the Bolivar Mine include:

· International Finance Corporation (Performance Standards) - social and environmental management planning; and
· World Bank Guidelines (Operational Policies and Environmental Guidelines).

These items were not specifically identified and included in SRK's environmental scope of work; however, given that Sierra Metals is a Canadian entity, general corporate policy tends to be in compliance with IFC, World Bank and Equator Principles.

SRK recommends that a more comprehensive audit of the Bolivar Mine be conducted with respect to these guidelines and performance standards.

20.4.7 The Permitting Process

Environmental permits are required from various federal and state agencies. The general process for obtaining authorization to construct a new industrial facility is shown in Figure 20-1.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 189

Source: SRK, 2020

Figure 20-1: Construction and Start-up Authorization for Industrial Facilities

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 190
20.4.8 Required Permits and Status

The required permits for continued operation at the Bolivar Mine, including exploration of the site, have been obtained based on information provided by Sierra. These include the necessary Changes in Use of Soil (Land Use Change), Forest Permits, and MIA authorizations. SRK has not investigated the current status of all the required permits. Currently, SRK is not aware of any outstanding permits or any non-compliance at the project or nearby exploration sites. Sierra is currently preparing a study to comply with CONAGUA (National Water Commission) requirements to demonstrate that no impact is produced on adjacent arroyos (creeks). Information regarding the exploration and mining permits in Table 20-1 and Table 20-2 was provided by Sierra.

Table 20-1: Permit and Authorization Requirements for the Bolivar Mine

Permit Agency Approval Date (or anticipated Approval Date)
Mining Concession President via the Minister of Commerce and Industrial and the General Directorate of Mines Promotion - Mexican Secretaría de Economía See Table 20-2
Manifestación de Impacto Ambiental (MIA) - Environmental Impact Statement Secretaría de Medio Ambiente y Recursos Naturales (SEMARNAT) - Secretariat of the Environment and Natural Resources

The operating mines of the Bolivar project are exempt from having to apply for the MIA according to the document SG.IR.08-2009/191 from SEMARNAT dated May 2009 that recognizes the exception since Sierra proved that the mining concessions predated the 1988 law. Any other concession will need a MIA or prove pre-existence. The new mines of the Bolivar Project have MIA authorization document SG.IR.08-2015/271 from SEMARNAT dated October 2015.

The plant site has an MIA, document SG.IR.08-2010/106. The MIA for the power line and substation is the document number SG.IR.08-2013/004.

Análisis de Riesgo - Risk Analysis Report Dirección Estatal de Proteccion Civil Chihuahua (with assistance from external consultant) A risk analysis focusing on the security on the use of explosives, was conducted and approved in D.O. 901/2015. Additional studies have recently been completed, but not yet submitted to SEMARNAT.
Operating License (and Air Quality Permit) SEMARNAT

The Bolivar Mine area has no atmospheric emissions.

The Bolivar plant area has a Licencia Unica Ambiental (unique environmental license) dated October 14, 2015 and approved under SG. CA.08-2015/075.

Cambio de Uso de Suelo - Land Use Change Permit SEMARNAT The operating concessions in the Bolivar Project are exempt from having to apply for the Cambio de Uso de Suelo, according to the document SG.IR.08-2009/191 from SEMARNAT dated May 2009, since Sierra proved that the mining concessions existed prior to the 1988 law.
Concession Title for Underground Water Extraction Comisión Nacional del Agua (CONAGUA) - National Water Commission) Mine dewatering is regulated under the Mining Law and no permit is required to extract mine water. This permit was not found.
Authorization for Utilization of National Surface Water CONAGUA For decades, new water appropriations in the area have been under moratorium; which was recently lifted by CONAGUA. Sierra has applied for new water appropriations.
Wastewater Discharge Permit CONAGUA

For the Bolivar Mine offices, there is a title permit BOO.906.01-1341 dated June 21, 2015.

For the Bolivar plant, there are documents No B00.E.22.4.-420 and No B00.906.01-1340 dated June 21, 2015. The following permits were found Dec 2019:

- 02CHI141178/34EMDL15

- 02CHI141179/34EMDL16

- 03CHI141277/10EMDL16

Hazardous Waste Registration SEMARNAT The last update to this registration is dated September 18, 2015. The site reviews annually to determine if additional updates are necessary.
Explosives Use Permit Secretaría de la Defensa Nacional (SEDENA) Updated permit from January 1 to December 31, 2020. Permit was issued 1 January 2020.
Archeological release letter Instituto Nacional de Antropologia y Historia (INAH) Updated in November 2013. No sites of interest for the INAH
Contract for Land Use Local Ejido The original contract was updated January 28, 2015.

Source: Sierra, 2020

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 191

Table 20-2: Bolivar Project Concessions

Holding Company Name Type Area File No. Title No. Enrolled Expiry
Sierra
Mexicana (DBM)
La Cascada Exploration 1,944.33 016/32259 222720 8/27/2004 8/26/2054
Javier Bencomo
Muñoz 50%, DBM 50%
Bolivar III Exploitation 48.00 321.1/1-64 180659 7/14/1987 7/13/2037
Javier Bencomo
Muñoz 50%, DBM 50%
Bolivar IV Exploitation 50.00 321.1/1-118 195920 9/23/1992 9/22/2042
Sierra
Mexicana
Piedras Verdes Exploration 92.4698 016/31958 220925 10/28/2003 10/27/2053
Sierra
Mexicana
Mezquital Exploration 2,475.41 016/32157 223019 10/5/2004 10/4/2054
Sierra
Mexicana
Mezquital Fracc. 1 Exploration 4.73 016/32157 223020 10/5/2004 04/10/2054
Sierra
Mexicana
Mezquital Fracc. 2 Exploration 2.4338 016/32157 223021 10/5/2004 10/4/2054
Sierra
Mexicana
Mezquital Fracc. 3 Exploration 974.5713 016/32157 223022 10/5/2004 10/4/2054
Sierra
Mexicana
El Gallo Exploration 251.7977 016/32514 224112 4/8/2005 4/7/2055
Sierra
Mexicana
La Mesa Exploration 718.95 016/32556 223506 1/12/2005 1/11/2055
EXMIN,
S.A. DE C.V.
Moctezuma Exploitation 67.4364 1/1/01432 226218 01/12/2005 01/12/2055
EXMIN,
S.A. DE C.V.
San Guillermo Exploration 96.0000 099/02161 196862 13/08/1993 12/08/2043

Source: Sierra Metals, 2020

20.4.9 MIA and CUS Authorizations

In 2009, SEMARNAT agreed that an MIA for the Bolivar Mine was not necessary since the area has been under exploration and exploitation since 1979; however, Sierra was still subject to the applicable environmental regulations according to article 29 of the LGEEPA. Additionally, if modifications to the existing operation were proposed, SEMARNAT would need to be consulted to determine the appropriate procedures for authorization.

In a resolution between SEMARNAT Chihuahua (Brenda Ríos Prieto) and Sierra MEXICANA (Arturo Valles Chávez) dated October 2015, the agency conditionally authorized the Bolivar Mine consisting of opening five (5) shafts for underground mines, 11 boreholes, waste dumps, material stock yard, tailings dam, and infrastructure construction (roads, substation, dining room, electricity distribution line, two (2) explosives magazines and temporary waste storage based on the information presented in the Environmental Impact Manifestation (Manifestacion de Impacto Ambiental (MIA)) submitted in August 2015.

The area covered by the Land Use Change (Cambio de Uso de Suelo (CUS)) is 9.7570 Hectares (24.11 acres) and the total construction area is 11.448 Hectares (28.28 acres).

The resolution has a validity of 15 years and can be renewed through an advance request to SEMARNAT, accompanied by a verification issued by PROFEPA.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 192
20.5 Social Management Planning and Community Relations

As part of the project review by SEMARNAT, the MIA document was made available to the public for review and comment prior to the issuance of the conditional authorization. SRK is not aware of any other public consultation or stakeholder engagement activities on the part of Sierra.

Dust on surface roadways between the mine and the plant location has been a challenge and the mine has been using two water trucks to keep the dust under control; however, due to the evaporative levels in Chihuahua, this system of dust control is not particularly efficient. According to Sierra, a new dust control strategy is being developed using clay/silt soil, which is currently undergoing on-site trials.

20.6 Closure and Reclamation Plan

Current regulations in México require that a preliminary closure program be included in the MIA and a definite program be developed and submitted to the authorities during the operation of the mine (generally accepted as three years into the operation). These closure plans tend to be conceptual and typically lack much of the detail necessary to develop an accurate closure cost estimate. However, Sierra has attempted to prescribe the necessary closure activities for the operation. In February 2017, Treviño Asociados Consultores presented to Sierra, a work breakdown of the anticipated tasks for closure and reclamation of the Bolivar Mine (Table 20-3).

Table 20-3: Bolivar Mine - Estimated Cost of Reclamation and Closure of the Mine

Closure Activity Cost MXN$

Waste Rock Piles

(regrading, soil preparation, revegetation) (2 ha)

105,430

Exploration Drill Pads

(remove contaminated soils, soil preparation, revegetation, erosion control) (4Ha)

48,300

Roads

(Border reconstruction, ditches, revegetation) (8 ha)

96,600

Building Demolition

(camps, plant, mill - dismantle, remove, soil remediation, soil preparation, revegetation)

7,653,250

Tailings Impoundment

(regrading, soil cover and preparation, revegetation) (6ha)

316,020

Power Line Corridor

(soil preparation, revegetation) (12 ha)

62,218

Power Line Removal

(850 poles; 12.64 km cable)

977,500

Total (MXN)

$9,259,318

Total (US$) (1)

$475,324

Source: Sierra Metals, 2020

(1) Based on exchange rate of US$1 = MXN$19.48 (February 27, 2020)
CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 193

SRK's scope of work did not include an assessment of the veracity of this closure cost estimate; however, based on projects of similar nature and size within México, the estimate appears low in comparison. SRK recommends that Sierra conduct an outside review of this estimate, with an emphasis on benchmarking against other projects in northern México.

While México requires the preparation of a reclamation and closure plan, as well as a commitment on the part of the operator to implement the plan, no financial surety (bonding) has thus far been required of mining companies. Environmental damages, if not remediated by the owner/operator, can give rise to civil, administrative and criminal liability, depending on the action or omission carried out. PROFEPA is responsible for the enforcement and recovery for those damages, or any other person or group of people with an interest in the matter. Also, recent reforms introduced class actions to demand environmental responsibility from damage to natural resources.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 194
21 Capital and Operating Costs

Capital and operating cost estimates for the underground mining were prepared by Sierra Metals' technical team to support the proposed mine plans based on six different production rates.

21.1 Capital Cost (Capex)

Sierra Metals' technical team prepared an estimate of capital required to sustain the mining and processing operations. This capital estimate is broken down into the following main areas:

· Mine development
· Ventilation
· Equipment
· Infill drilling and exploration
· Plant
· Paste backfill plant
· TSF
· Mine closure

Mine development is related to any underground mine development that is capitalized. The cost estimate is based on site specific data from Bolivar.

Equipment sustaining cost includes the capital to maintain and replace mine equipment, while plant and TSF sustaining capital accounts for the expansion of the TSF. Additional capital costs have been included to account for Plant improvements.

Exploration capital will be used in the exploration of future mining opportunities within the company's mining and exploration concessions.

The capital cost includes the construction of a paste backfill plant. The plant will use dewatered mill tailings, combined with cement, which is mixed to a specific viscosity in a continuous mixer and then pumped underground to the stopes.

21.2 Operating cost (Opex)

Sierra Metals' technical team prepared estimates using site specific data and historical operating costs. The costs were broken down into four main areas:

· Mine
· Plant
· G&A
· Backfill paste

The cost of the paste backfill was estimated based on benchmarking of projects and underground mines that operate with this type of fill.

Table 21-1 through Table 21-12 show the capital and operating cost estimates for the six production rate scenarios proposed in this PEA report.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 195

Table 21-1: Opex Estimate at 5,000 Tonnes/Day (US$)

Opex Total Total [kUS$] 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043
Mine 512,790 22,083 22,083 22,083 22,083 22,083 22,083 22,083 22,083 22,083 22,083 22,083 22,083 22,083 22,083 22,083 22,083 22,083 22,083 22,083 22,083 22,083 22,083 22,083 4,884
Plant 259,792 11,188 11,188 11,188 11,188 11,188 11,188 11,188 11,188 11,188 11,188 11,188 11,188 11,188 11,188 11,188 11,188 11,188 11,188 11,188 11,188 11,188 11,188 11,188 2,474
G&A 78,009 3,359 3,359 3,359 3,359 3,359 3,359 3,359 3,359 3,359 3,359 3,359 3,359 3,359 3,359 3,359 3,359 3,359 3,359 3,359 3,359 3,359 3,359 3,359 743
Backfill 145,984 7,219 7,219 7,219 7,219 7,219 7,219 7,219 7,219 7,219 7,219 7,219 7,219 7,219 7,219 7,219 7,219 7,219 7,219 7,219 7,219 1,597
Total 996,574 36,630 36,630 36,630 43,849 43,849 43,849 43,849 43,849 43,849 43,849 43,849 43,849 43,849 43,849 43,849 43,849 43,849 43,849 43,849 43,849 43,849 43,849 43,849 9,697

Source: Sierra Metals, 2020

Table 21-2: Capex Estimate at 5,000 Tonnes/Day (US$)

Capex Total Total [kUS$] 2,020 2,021 2,022 2,023 2,024 2,025 2,026 2,027 2,028 2,029 2,030 2,031 2,032 2,033 2,034 2,035 2,036 2,037 2,038 2,039 2,040 2,041 2,042 2,043
Development Sustaining 88,399 3,807 5,307 4,807 3,807 3,807 3,807 3,807 3,807 3,807 3,807 3,807 3,807 3,807 3,807 3,807 3,807 3,807 3,807 3,807 3,807 3,807 2,807 2,307 842
Ventilation Sustaining 4,588 198 298 298 198 198 198 198 198 198 198 198 198 198 198 198 198 198 198 198 198 198 98 98 44
Development tunnel Growth 5,852 566 1,807 1,233 1,407 840
Equipment Sustaining 46,100 1,500 3,600 2,600 2,100 1,000 2,500 2,000 2,600 2,100 2,600 2,500 2,000 1,000 2,100 2,600 4,100 2,000 1,000 500 2,600 3,100
Exploration Sustaining 18,800 1,200 800 800 800 800 800 800 800 800 800 800 800 800 800 800 800 800 800 800 800 800 800 800
Exploration Growrh 35,897 1,397 1,500 1,500 1,500 1,500 1,500 1,500 1,500 1,500 1,500 1,500 1,500 1,500 1,500 1,500 1,500 1,500 1,500 1,500 1,500 1,500 1,500 1,500 1,500
Backfill Plant 17,226 17,226
Plants Sustainig 13,940 1,140 1,800 500 500 500 500 500 500 500 500 500 500 500 500 500 500 500 500 500 500 500 500 500 500
Ampliación Planta Growth
Instalation of tails storage facility (TSF) 5,369 1,369 4,000
TSF Growth PEA Growth 1,380 60 660 660
Studies 2,274 1,274 1,000
Closure 5,000 5,000
Total 244,825 11,010 18,672 30,623 10,811 9,744 7,804 9,304 8,804 9,404 8,904 9,404 9,304 8,804 7,804 8,904 9,404 10,904 8,804 7,804 7,304 9,404 8,804 5,204 7,886

Source: Sierra Metals, 2020

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 196

Table 21-3: Opex Estimate at 7,000 Tonnes/Day (US$) (7,000 tpd in 2024)

Opex Total Total [kUS$] 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037
Mine 472,036 22,083 22,083 22,083 22,083 27,948 27,948 27,948 27,948 27,948 27,948 27,948 27,948 27,948 27,948 27,948 27,948 27,948 20,385
Plant 242,443 11,188 11,188 11,188 11,188 14,399 14,399 14,399 14,399 14,399 14,399 14,399 14,399 14,399 14,399 14,399 14,399 14,399 10,503
G&A 73,397 3,359 3,359 3,359 3,359 4,367 4,367 4,367 4,367 4,367 4,367 4,367 4,367 4,367 4,367 4,367 4,367 4,367 3,185
Backfill 128,510 7,219 8,834 8,834 8,834 8,834 8,834 8,834 8,834 8,834 8,834 8,834 8,834 8,834 8,834 6,444
Total 916,385 36,630 36,630 36,630 43,849 55,548 55,548 55,548 55,548 55,548 55,548 55,548 55,548 55,548 55,548 55,548 55,548 55,548 40,517

Source: Sierra Metals, 2020

Table 21-4: Capex Estimate at 7,000 Tonnes/Day (US$) (7,000 tpd in 2024)

Capex Total Total [kUS$] 2,020 2,021 2,022 2,023 2,024 2,025 2,026 2,027 2,028 2,029 2,030 2,031 2,032 2,033 2,034 2,035 2,036 2,037
Development Sustaining 89,876 3,807 5,307 5,807 8,907 5,330 5,330 5,330 5,330 5,330 5,330 5,330 5,330 5,330 5,330 5,330 5,330 2,084 10
Ventilation Sustaining 4,588 198 298 338 358 277 277 277 277 277 277 277 277 277 277 277 177 127 52
Development tunnel Growth 5,852 566 1,807 1,233 1,407 840 - - - - - - - - - - - - -
Equipment Sustaining 42,600 - 1,500 4,100 3,600 5,000 - 2,500 2,500 3,600 2,600 4,000 2,000 3,000 2,000 2,600 1,600 2,000 -
Exploration Sustaining 18,800 1,200 800 1,120 1,120 1,120 1,120 1,120 1,120 1,120 1,120 1,120 1,120 1,120 1,120 1,120 1,120 1,120 -
Exploration Growrh 35,897 1,397 1,500 2,200 2,200 2,200 2,200 2,200 2,200 2,200 2,200 2,200 2,200 2,200 2,200 2,200 2,200 2,200 -
Backfill Plant 20,547 - - 20,547 - - - - - - - - - - - - - - -
Plants Sustainig 13,940 1,140 1,800 500 500 714 714 714 714 714 714 714 714 714 714 714 714 714 714
Ampliación Planta Growth 22,500 - - 11,250 11,250 - - - - - - - - - - - - - -
Instalation of tails storage facility (TSF) 5,369 1,369 4,000 - - - - - - - - - - - - - - - -
TSF Growth PEA Growth 1,380 60 660 660 - - - - - - - - - - - - - - -
Studies 2,274 1,274 1,000 - - - - - - - - - - - - - - - -
Closure 5,000 - - - - - - - - - - - - - - - - - 5,000
Total 268,624 11,010 18,672 47,755 29,341 15,480 9,640 12,140 12,140 13,240 12,240 13,640 11,640 12,640 11,640 12,240 11,140 8,244 5,776

Source: Sierra Metals, 2020

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 197

Table 21-5: Opex Estimate at 10,000 Tonnes/Day (US$) (10,000 tpd in 2024)

Opex Total Total [kUS$] 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033
Mine 433,099 22,083 22,083 22,083 22,083 35,874 35,874 35,874 35,874 35,874 35,874 35,874 35,874 35,874 21,904
Plant 225,578 11,188 11,188 11,188 11,188 18,815 18,815 18,815 18,815 18,815 18,815 18,815 18,815 18,815 11,488
G&A 55,409 3,359 3,359 3,359 3,359 4,367 4,367 4,367 4,367 4,367 4,367 4,367 4,367 4,367 2,667
Backfill 112,383 - - - 7,219 10,942 10,942 10,942 10,942 10,942 10,942 10,942 10,942 10,942 6,681
Total 826,469 36,630 36,630 36,630 43,849 69,999 69,999 69,999 69,999 69,999 69,999 69,999 69,999 69,999 42,740

Source: Sierra Metals, 2020

Table 21-6: Capex Estimate at 10,000 Tonnes/Day (US$) (10,000 tpd in 2024)

Capex Total Total [kUS$] 2,020 2,021 2,022 2,023 2,024 2,025 2,026 2,027 2,028 2,029 2,030 2,031 2,032 2,033
Development Sustaining 89,940 3,807 5,307 7,807 11,607 7,614 7,614 7,614 7,614 7,614 7,614 7,614 7,614 424 80
Ventilation Sustaining 4,588 198 298 348 448 395 395 395 395 395 395 395 245 195 91
Development tunnel Growth 5,852 566 1,807 1,233 1,407 840
Equipment Sustaining 41,200 2,500 5,100 4,600 4,500 4,200 500 3,000 7,000 3,700 2,600 500 3,000
Exploration Sustaining 18,800 1,200 800 1,527 1,527 1,527 1,527 1,527 1,527 1,527 1,527 1,527 1,527 1,527
Exploration Growrh 35,897 1,397 1,500 2,000 3,000 3,000 3,250 3,250 3,250 3,250 3,000 3,000 3,000 3,000
Backfill plant 24,884 24,884
Plants Sustainig 13,940 1,140 1,800 500 500 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000
Ampliación Planta Growth 67,500 33,750 33,750
Instalation of tails storage facility (TSF) 5,369 1,369 4,000
TSF Growth PEA Growth 1,380 60 660 660
Studies 2,274 1,274 1,000
Closure 5,000 5,000
Total 316,624 11,010 19,672 77,808 56,839 18,876 17,986 14,286 16,786 20,786 17,236 16,136 13,886 9,146 6,171

Source: Sierra Metals, 2020

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 198

Table 21-7: Opex Estimate at 10,000 Tonnes/Day (US$) (10,000 tpd in 2026)

Opex Total Total [kUS$] 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034
Mine 438,771 22,083 22,083 22,083 22,083 27,948 27,948 35,874 35,874 35,874 35,874 35,874 35,874 35,874 35,874 7,554
Plant 228,035 11,188 11,188 11,188 11,188 14,399 14,399 18,815 18,815 18,815 18,815 18,815 18,815 18,815 18,815 3,962
G&A 58,030 3,359 3,359 3,359 3,359 4,367 4,367 4,367 4,367 4,367 4,367 4,367 4,367 4,367 4,367 920
Backfill 114,732 7,219 8,834 8,834 10,942 10,942 10,942 10,942 10,942 10,942 10,942 10,942 2,304
Total 839,567 36,630 36,630 36,630 43,849 55,548 55,548 69,999 69,999 69,999 69,999 69,999 69,999 69,999 69,999 14,740

Source: Sierra Metals, 2020

Table 21-8: Capex Estimate at 10,000 Tonnes/Day (US$) (10,000 tpd in 2026)

Capex Total Total [kUS$] 2,020 2,021 2,022 2,023 2,024 2,025 2,026 2,027 2,028 2,029 2,030 2,031 2,032 2,033 2,034
Development Sustaining 91,770 3,807 5,307 5,807 8,907 7,830 9,830 7,614 7,614 7,614 7,614 7,614 7,614 2,114 2,064 424
Ventilation Sustaining 4,588 198 298 338 358 397 467 395 395 395 395 345 235 155 145 73
Development tunnel Growth 5,852 566 1,807 1,233 1,407 840
Equipment Sustaining 42,600 2,500 5,100 4,600 4,500 2,600 2,900 3,000 3,000 4,500 2,600 2,900 2,200 2,200
Exploration Sustaining 18,800 1,200 800 1,120 1,120 1,527 1,527 1,438 1,438 1,438 1,438 1,438 1,438 1,438 1,438
Exploration Growrh 35,897 1,397 1,500 2,200 2,200 2,860 2,860 2,860 2,860 2,860 2,860 2,860 2,860 2,860 2,860
Backfill Plant 24,884 24,884
Plants Sustainig 13,940 1,140 1,800 500 500 714 714 952 952 952 952 952 952 952 952 952
Ampliación Planta Growth 67,500 25,000 25,000 17,500
Instalation of tails storage facility (TSF) 5,369 1,369 4,000
TSF Growth PEA Growth 1,380 60 660 660
Studies 2,274 1,274 1,000
Closure 5,000 5,000
Total 319,854 11,010 19,672 41,841 44,091 43,668 35,498 16,159 16,259 16,259 17,759 15,809 15,999 9,719 9,660 6,450

Source: Sierra Metals, 2020

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 199

Table 21-9: Opex Estimate at 12,000 Tonnes/Day (US$) (12,000 tpd in 2024)

Opex Total Total [kUS$] 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032
Mine 414,747 22,083 22,083 22,083 22,083 40,757 40,757 40,757 40,757 40,757 40,757 40,757 39,814 1,303
Plant 217,521 11,188 11,188 11,188 11,188 21,572 21,572 21,572 21,572 21,572 21,572 21,572 21,073 689
G&A 48,414 3,359 3,359 3,359 3,359 4,367 4,367 4,367 4,367 4,367 4,367 4,367 4,266 140
Backfill 104,987 7,219 12,207 12,207 12,207 12,207 12,207 12,207 12,207 11,925 390
Total 785,669 36,630 36,630 36,630 43,849 78,904 78,904 78,904 78,904 78,904 78,904 78,904 77,078 2,522

Source: Sierra Metals, 2020

Table 21-10: Capex Estimate at 12,000 Tonnes/Day (US$) (12,000 tpd in 2024)

Capex Total Total [kUS$] 2,020 2,021 2,022 2,023 2,024 2,025 2,026 2,027 2,028 2,029 2,030 2,031 2,032
Development Sustaining 91,259 3,807 5,307 7,807 13,057 9,136 9,136 9,136 9,136 9,136 9,136 5,136 1,035 292
Ventilation Sustaining 4,588 198 298 348 448 474 474 474 474 474 474 324 113 15
Development tunnel Growth 5,852 566 1,807 1,233 1,407 840
Equipment Sustaining 43,600 2,500 5,100 4,600 6,900 5,000 500 3,000 7,000 4,500 1,000 500 3,000
Exploration Sustaining 18,800 1,200 800 1,680 1,680 1,680 1,680 1,680 1,680 1,680 1,680 1,680 1,680
Exploration Growrh 35,897 1,397 1,500 2,000 3,000 3,500 3,500 3,500 3,500 3,500 3,500 3,500 3,500
Backfill Plant 29,646 29,646
Plants Sustainig 13,940 1,140 1,800 500 500 1,102 1,102 1,102 1,102 1,102 1,143 1,143 1,102 1,102
Ampliación Planta Growth 97,500 48,750 48,750
Instalation of tails storage facility (TSF) 5,369 1,369 4,000
TSF Growth PEA Growth 1,380 60 660 660
Studies 2,274 1,274 1,000
Closure 5,000 5,000
Total 355,105 11,010 19,672 97,723 73,441 23,632 20,893 16,393 18,893 22,893 20,434 12,784 7,930 9,409

Source: Sierra Metals, 2020

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 200

Table 21-11: Opex Estimate at 12,000 Tonnes/Day (US$) (12,000 tpd in 2026)

Opex Total Total [kUS$] 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032
Mine 423,093 22,083 22,083 22,083 22,083 27,948 27,948 40,757 40,757 40,757 40,757 40,757 40,757 34,323
Plant 221,151 11,188 11,188 11,188 11,188 14,399 14,399 21,572 21,572 21,572 21,572 21,572 21,572 18,167
G&A 52,053 3,359 3,359 3,359 3,359 4,367 4,367 4,367 4,367 4,367 4,367 4,367 4,367 3,678
Backfill 108,413 7,219 8,834 8,834 12,207 12,207 12,207 12,207 12,207 12,207 10,280
Total 804,711 36,630 36,630 36,630 43,849 55,548 55,548 78,904 78,904 78,904 78,904 78,904 78,904 66,449

Source: Sierra Metals, 2020

Table 21-12: Capex Estimate at 12,000 Tonnes/Day (US$) (12,000 tpd in 2026)

Capex Total Total [kUS$] 2,020 2,021 2,022 2,023 2,024 2,025 2,026 2,027 2,028 2,029 2,030 2,031 2,032
Development Sustaining 93,792 3,807 5,307 5,807 8,907 8,330 11,330 9,136 9,136 9,136 9,136 5,336 4,764 3,660
Ventilation Sustaining 4,588 198 298 338 358 427 497 474 474 474 374 259 259 159
Development tunnel Growth 5,852 566 1,807 1,233 1,407 840
Equipment Sustaining 43,600 2,500 5,100 4,600 6,900 5,000 500 3,000 7,000 4,500 1,000 500 3,000
Exploration Sustaining 18,800 1,200 800 1,120 1,120 1,680 1,680 1,868 1,868 1,867 1,866 1,866 1,864
Exploration Growrh 35,897 1,397 1,500 2,200 2,200 3,200 3,200 3,200 3,200 3,200 3,200 3,200 3,200 3,000
Backfill Plant 29,646 29,646
Plants Sustainig 13,941 1,140 1,800 500 500 714 714 1,225 1,225 1,225 1,225 1,225 1,222 1,225
Ampliación Planta Growth 97,500 37,500 37,500 22,500
Instalation of tails storage facility (TSF) 5,369 1,369 4,000
TSF Growth PEA Growth 1,380 60 660 660
Studies 2,274 1,274 1,000
Closure 5,000 5,000
Total 357,639 11,010 19,672 46,603 56,591 59,590 44,920 16,404 18,904 22,903 20,302 12,887 11,810 16,044

Source: Sierra Metals, 2020

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 201
21.3 Incremental Opex and Capex of the Magnetite Recovery Project

Operating and capital costs were estimated for the magnetite recovery project and are presented here for the 10,000 tpd case (2024). Table 21-13 and Table 21-14 show the total operating cost estimate and the magnetite recovery project opex estimate detail, and Table 21-15 and Table 21-16 show the total capital cost estimate and the magnetite recovery project capex estimate detail.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 202

Table 21-13: Opex Estimation 10,000 Tonnes/Day (US$) (2024) including the Magnetite Recovery Project

Opex Total Total [kUS$] 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033
Mine 433,099 22,083 22,083 22,083 22,083 35,874 35,874 35,874 35,874 35,874 35,874 35,874 35,874 35,874 21,904
Plant 225, 578 11,188 11,188 11,188 11,188 18,815 18,815 18,815 18,815 18,815 18,815 18,815 18,815 18,815 11,488
G&A 55,409 3,359 3,359 3,359 3,359 4,367 4,367 4,367 4,367 4,367 4, 367 4,367 4,367 4,367 2,667
Magnetite Recovery Project 290,958 - - 21,965 24,660 21,613 21,395 24,150 23,620 23,232 23,115 27,441 21,441 21,038 18,629
Backfill 112, 383 - - - 7,219 10,942 10,942 10,942 10,942 10,942 10,942 10,942 10,942 10,942 6,681
Total 1,117,427 36,630 36,630 58,595 68,509 97,672 97,394 94,749 93,618 93,231 93,114 97,440 97,440 91,037 61,369

Table 21-14: Opex Estimation Detail for the Magnetite Recovery Project

Opex Total Total [kUS$] 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033
Mine - -
Plant 34,357 - - 2,594 2,912 3,268 3,235 2,922 2, 789 2, 743 2, 729 3,240 3,240 2,484 2,200
Bahuichivo yard 6,193 - - 468 525 589 583 527 503 494 492 584 584 448 397
G&A - Topolobampo port 44,119 - - 3,331 3,739 4,196 4 ,154 3,753 3, 582 3, 523 3, 505 4,161 4,161 3,190 2,825
G&A -General Services 1,895 - - 143 161 180 178 161 154 151 151 179 179 137 121
G&A - Bahuichivo - Topolobampo freight 204, 394 - - 15,430 17,323 19,440 19,245 17,386 16, 592 16, 320 16, 238 19,277 19,277 14,779 13,087
Backfill -
Total 290,958 - - 21,965 24,660 27,673 27,395 24,750 23,620 23, 232 23,115 27,441 27,441 21,038 18,629

Table 21-15: Capex Estimation 10,000 Tonnes/Day (US$) (2024) including the Magnetite Recovery Project

CAPEX Total [kUS$] 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033
Development Sustaining 89,940 3,807 5,307 7,807 11,607 7,614 7,614 7,614 7,614 7, 614 7, 614 7,614 7,614 4 24 80
Venti lation Sustaining 4,588 198 298 348 448 395 395 395 395 395 395 395 245 195 91
Development tunnel Growth 5,852 566 1,807 1,233 1,407 840 - - - - - - - - -
Equipment Susta ining 41 ,200 - 2,500 5,100 4,600 4,500 4,200 500 3,000 7,000 3, 700 2,600 500 3,000 -
Exploration Sustaining 18,800 1, 200 800 1,527 1,527 1,527 1,527 1,527 1, 527 1, 527 1, 527 1,527 1,527 1,527 -
Exploration Growrh 35,897 1,397 1,500 2,000 3,000 3,000 3,250 3,250 3, 250 3, 250 3,000 3,000 3,000 3,000 -
Backfill Plant 24,884 - - 24,884 - - - - - - - - - - -
Plants Sustainig 13,940 1,140 1,800 500 500 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000
Ampliaci6n Planta Growth 67,500 - - 33,750 33,750 - - - - - - - - - -
lnstalation of tails storage faci lity (TSF) 5, 369 1, 369 4,000 - - - - - - - - - - - -
TSF Growth PEA Growth 1, 380 60 660 660 - - - - - - - - - - -
Magnetite Recovery Project 28,172 - 24,613 3,5591 - - - - - - - - - - -
Studies 2, 274 1, 274 1,000 - - - - - - - - - - - -
Closure 5,000 - - - - - - - - - - - - - 5,000
Total 344,796 11,010 44,285 81,367 56,839 18,876 17,986 14,286 16, 786 20, 786 17, 236 16,136 13,886 9,146 6,171

Table 21-16: Capex Estimation Detail for the Magnetite Recovery Project

CAPEX Total
[kUS$]
2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033
Pilot Plant 0 0
Design and Engineering 1, 233 1,085 148
Construction 5,180 4,264 916
Tailing Dam 2,010 1,206 804
Scooptrams and Trucks 1,168 1,168
Plant Equipment 3,878 3,878
Road Engineering 103 103
Road and yard works 3, 208 2,669 539
Concentrate yard (warehouse) 611 611
Trucks 1,160 1,160
Road rehab 964 916 48
Owner Cost 3,847 3,356 491
Contingencies 4,809 4,196 614
Total 28,172 - 24,613 3,559 - - - - - - - - - - -
CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 203

22 Economic Analysis

The economic results shown in subsection 22.1 do not include the magnetite recovery project. Subsection 22.2 is an update to this PEA report and describes the economic analysis of the magnetite recovery project.

22.1 Economic Analysis without the magnetite recovery project

The economic analysis for this PEA was prepared by Sierra Metals and reviewed by SRK. The analysis is based on Mineral Resources only and includes Inferred Mineral Resources. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability and should be supported at least by a pre-feasibility study. This PEA is preliminary in nature and there is no certainty that the results of the PEA will be realized.

As explained in Section 19, the commodity prices used in the economic analysis include the following:

Table 22-1: Commodity Price Forecast by Year

Metal Unit 2020 2021 2022 2023 Long Term (LT)
Au $/oz 1,755 1,907 1,782 1,737 1,541
Ag $/oz 19.83 24.12 22.22 22.47 20.0
Cu $/lb 2.65 2.86 2.89 2.93 3.05
Pb $/lb 0.82 0.87 0.89 0.90 0.91
Zn $/lb 0.94 0.99 1.04 1.04 1.07

Source: CIBC, Sierra Metals, 2021

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 204

In addition to the prices listed above in Table 22-1, the following NSR factors (Table 22-2) and economic factors (Table 22-3) were also used in the economic analysis:

Table 22-2: NSR Factors

Process Recoveries*
Cu % 88
Ag % 78.7
Au % 62.43
Concentrate Grades
Cu % 25
Ag g/t 570
Au g/t 6.8
Moisture content % 8
Freight, Insurance and Marketing
Transport losses % 0.5
Transportation US$/wmt 42
Port US$/wmt 9
Load US$/wmt 40
Marketing US$/dmt 10
Insurances US$/wmt 10
Total US$/dmt 102.92
Smelter Terms
Cu payable % 96
Ag payable % 90
Au payable % 92
Cu minimum deduction % 1
Ag minimum deduction oz/t 0
Au minimum deduction oz/t 0
Treatment Charges/Refining Charges (TC/RC)
Cu Concentrate TC US$/dmt 69.00
Cu Refining charge US$/lb Cu 0.069
Cu Refining cost US$/t Cu 152.12
Cu Price Participation US$/dmt 0
Average Penalties US$/dmt 10
Ag Refining charge US$/oz 0.35
Au Refining charge US$/oz 6
Total treatment cost US$/t Cu 727.68
Total cost of sales US$/t Cu 879.80
Net Smelter Return Factors
Cu US$/t/% 48.8171
Ag US$/t/g/t 0.4444
Au US$/t/g/t 28.1940

Source: Sierra Metals, 2020

* NI 43-101 Technical Report (SRK Consulting (Canada) Inc. May 8, 2020)

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 205
SRK Consulting
2US043.005 Sierra Metals Inc.
Bolivar_Technical_Report_PEA_Update
Page 211

The economic contribution of the Fe was not included in the calculation of the NSR values, and the analysis of the magnetite recovery project is provided in Section 22.1. Other economic factors and assumptions used in the economic analysis include:

Table 22-3: Economic Factors

Measure Unit Value
Discount Rate % 8.0
LOM Average grade - Au g/t 0.19
LOM Average grade - Ag g/t 13.56
LOM Average grade - Cu % 0.72
Ordinary Mining Entitled Royalty US$/year 220,000
Extraordinary Mining Entitled Royalty (applied to precious metals) % 0.5
Variable Special Mining Royalty US$/year Depends on operating margin
Tax Rate % 30.0

Source: Sierra Metals, 2020

Numbers are presented on a 100% ownership basis and do not include financing costs

The economic analysis is based on mine schedule, CAPEX and OPEX estimation, and price assumptions detailed above.

Table 22-4 shows the results of the economic evaluations for the production rates evaluated in this PEA using the metal prices in Table 22-1 sourced from CIBC Consensus September 30, 2020. The production rate option of 15,000 tpd (2024) has the highest post tax NPV with respect to the other options and both the 10,000 tpd (2024) and 12,000 tpd (2024) options have better returns than their 2026 counterparts.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 206

Table 22-4: Summary Economic Evaluation

Summary Economic Evaluation
Description Units

5 KTPD

7 KTPD 10 KTPD 10 KTPD 12 KTPD 12 KTPD 15 KTPD
2024 2024 2026 2024 2026 2024
Life of mine Years 24 18 14 15 13 13 11
Market Prices (Long Term)
Gold $/oz 1,541 1,541 1,541 1,541 1,541 1,541 1,541
Silver $/oz 20 20 20 20 20 20 20
Copper $/lb 3.05 3.05 3.05 3.05 3.05 3.05 3.05
Net Sales
Gold k$ 233,617 233,617 233,617 233,617 233,617 233,617 233,617
Silver k$ 265,316 265,316 265,316 265,316 265,316 265,316 265,316
Copper k$ 1,680,297 1,680,297 1,680,297 1,680,297 1,680,297 1,680,297 1,680,297
Gross Revenue k$ 2,179,230 2,179,230 2,179,230 2,179,230 2,179,230 2,179,230 2,179,230
Charges for treatment, refining, impurities k$ 172,461 172,461 172,461 172,461 172,461 172,461 172,461
Gross Revenue After Selling and Treatment Costs k$ 2,006,769 2,006,769 2,006,769 2,006,769 2,006,769 2,006,769 2,006,769
Royalties and Mining Permits k$ 83,539 88,233 94,097 93,335 96,937 95,509 99,936
Gross Revenue After All Costs k$ 1,923,230 1,918,536 1,912,672 1,913,435 1,909,832 1,911,260 1,906,833
Operating Costs
Mine k$ 512,790 472,036 433,099 438,771 414,747 423,093 393,612
Plant k$ 259,792 242,443 225,578 228,035 217,521 221,151 208,147
G&A k$ 78,009 73,397 55,409 58,030 48,414 52,053 41,419
Back Fill k$ 145,984 128,510 112,383 114,732 104,987 108,413 96,638
Total Operating k$ 996,574 916,385 826,469 839,567 785,669 804,711 739,815
EBITDA k$ 926,656 1,002,151 1,086,203 1,073,867 1,124,163 1,106,550 1,167,018
LoM Capital + Sustaining Capital k$ 244,825 268,624 316,624 319,854 355,105 357,639 408,345
Working Capital k$ 18,849 18,276 18,146 18,696 18,950 17,566 18,146
Income Taxes k$ -209,021 -220,058 -230,874 -230,410 -242,044 -224,673 -230,807
Cash flow before Taxes k$ 662,982 715,251 751,433 735,317 750,108 731,344 740,527
Cash flow after Taxes k$ 453,961 495,193 520,559 504,908 508,064 506,671 509,720
Post Tax NPV @ 5% k$ 282,882 320,898 350,787 334,178 349,978 336,798 354,455
Post Tax NPV @ 8% k$ 225,191 256,236 282,546 267,228 284,080 268,832 288,105
Post Tax NPV @ 10% k$ 197,271 223,529 246,605 232,484 248,693 233,214 252,002

Source: Sierra Metals, 2020

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 207

A sensitivity analysis of the Post Tax NPV vs Tonnes Per Day throughput is shown in Figure 22-1.

Source: Sierra Metals, 2020

Note: 5,000 tpd (base case), 7,000 tpd, 10,000 tpd (2024), 12,000 tpd (2024), 15,000 tpd are shown

Figure 22-1: Sensitivity Analysis - Post Tax NPV vs TPD

Table 22-5: Incremental Post Tax NPV and IRR

Production Rates Post Tax NPV US$ Post Tax IRR %
7ktpd - 5ktpd 31,044,119 29.21%
10ktpd (2024) - 5ktpd 57,354,818 27.87%
10ktpd (2024) - 7ktpd 26,310,699 26.83%
12ktpd (2024) - 5ktpd 58,888,188 26.63%
12ktpd (2024) - 7ktpd 27,844,069 25.20%
12ktpd (2024) - 10ktpd (2024) 1,533,370 5.75%
15ktpd - 5ktpd 62,914,037 24.84%
15ktpd - 7ktpd 31,869,917 23.03%
15ktpd - 10ktpd (2024) 5,559,219 18.31%
15ktpd - 12ktpd (2024) 4,025,848 16.84%

Source: Sierra Metals, 2020

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 208

As seen in Table 22-5, the incremental benefit generated by increasing the production rate from 5,000 tpd to 10,000 tpd is very significant with an incremental post tax NPV of US$ 57.4 M and an incremental post tax IRR of 28%. However, the incremental benefit generated by increasing the production rate to 12,000 tpd or 15,000 tpd is far less significant and given that trebling the production rate can potentially present significant operational challenges, Sierra Metals has therefore selected the 10,000 tpd (2024) production rate as the preferred option.

The 10,000 tpd (2024) proposed mine plan requires a capital requirement (initial and sustaining) of US$ 317 M over the life of mine; efficiencies associated with higher throughputs are expected to drive a reduction in operating costs on a per tonne basis. This PEA indicates a post tax NPV (8%) at 10,000 tpd (in 2024) of US$ 283 M. Total operating cost for the life of mine is US$ 827 M, equating to a total operating cost of US$ 19.77 per tonne milled and US$ 1.16 per pound copper equivalent.

A sensitivity analysis was performed for each of the seven production plans in order to analyze the impact of the change on the main drivers; operating cost, gross income, cost of capital, Cu grade, Ag grade and Au grade. This is shown in Table 22-6 to Table 22-12 and is shown graphically in Figure 22-2 to Figure 22-15.

Figure 22-6 shows the sensitivity analysis for the 10,000 tpd (2024) production rate, the preferred production rate option for Sierra Metals. The figure shows the relative sensitivity of the Bolivar Mine's economics to changes in the metal grades (Cu, Au, Ag), operating and capital costs, and gross income.

The project is most sensitive to changes in gross income and the grade of copper, moderately sensitive to changes in operating and capital costs, and relatively insensitive to changes in the grades of gold and silver. As the project is slightly more sensitive to changes in operating costs than capital costs, capital increases which can reduce operating costs should increase project value.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 209

Table 22-6: Sensitivity Analysis NPV - 5,000 Tonnes/Day (US$)

Sensitivity -30% -20% -10% 0% 10% 20% 30%
OPEX 310,036,251 281,754,655 253,473,058 225,191,462 196,909,866 168,628,270 140,346,674
CAPEX 264,030,069 251,083,867 238,137,664 225,191,462 212,245,260 199,299,058 186,352,856
Gross Income 35,437,009 99,200,219 162,195,841 225,191,462 288,187,084 351,182,705 414,178,327
Cu% 93,878,308 137,649,359 181,420,411 225,191,462 268,962,514 312,733,565 356,504,616
Ag g/t 201,341,786 209,291,678 217,241,570 225,191,462 233,141,354 241,091,246 249,041,138
Au g/t 206,777,846 212,915,718 219,053,590 225,191,462 231,329,334 237,467,207 243,605,079

Source: Sierra Metals, 2020

Source: Sierra Metals, 2020

Figure 22-2: Sensitivity Analysis - 5,000 tpd

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 210

Source: Sierra Metals, 2020

Figure 22-3: Sensitivity NPV vs Discount Rate - 5,000 tpd

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 211

Table 22-7: Sensitivity Analysis NPV - 7,000 Tonnes/Day (US$)

Sensitivity -30% -20% -10% 0% 10% 20% 30%
OPEX 352,629,468 320,498,173 288,366,877 256,235,581 224,104,286 191,972,990 159,841,694
CAPEX 306,904,338 290,014,753 273,125,167 256,235,581 239,345,996 222,456,410 205,566,824
Gross Income 41,730,165 113,785,257 185,189,506 256,235,581 327,281,656 398,327,732 469,373,807
Cu% 107,795,780 157,514,083 206,874,832 256,235,581 305,596,330 354,957,080 404,317,829
Ag g/t 229,850,466 238,645,505 247,440,543 256,235,581 265,030,620 273,825,658 282,620,697
Au g/t 234,903,358 242,014,099 249,124,840 256,235,581 263,346,323 270,457,064 277,567,805

Source: Sierra Metals, 2020

Source: Sierra Metals, 2020

Figure 22-4: Sensitivity Analysis - 7,000 tpd

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 212

Source: Sierra Metals, 2020

Figure 22-5: Sensitivity NPV vs Discount Rate - 7,000 tpd

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 213

Table 22-8: Sensitivity Analysis NPV - 10,000 Tonnes/Day (US$) (10,000 tpd in 2024)

Sensitivity -30% -20% -10% 0% 10% 20% 30%
OPEX 372,477,890 342,500,687 312,523,484 282,546,280 252,569,077 222,591,873 192,614,670
CAPEX 349,778,889 327,368,020 304,957,150 282,546,280 260,135,410 237,724,541 215,313,671
Gross Income 45,268,023 124,959,674 203,904,686 282,546,280 361,187,874 439,829,468 518,471,062
Cu% 118,335,680 173,296,127 227,921,203 282,546,280 337,171,357 391,796,433 446,421,510
Ag g/t 253,778,841 263,367,987 272,957,134 282,546,280 292,135,426 301,724,573 311,313,719
Au g/t 258,419,716 266,461,904 274,504,092 282,546,280 290,588,468 298,630,656 306,672,844

Source: Sierra Metals, 2020

Source: Sierra Metals, 2020

Figure 22-6: Sensitivity Analysis - 10,000 tpd in 2024

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 214

Source: Sierra Metals, 2020

Figure 22-7: Sensitivity NPV vs Discount Rate - 10,000 tpd in 2024

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 215

Table 22-9: Sensitivity Analysis NPV - 10,000 Tonnes/Day (US$) (10,000 tpd in 2026)

Sensitivity -30% -20% -10% 0% 10% 20% 30%
OPEX 356,525,410 326,759,546 296,993,682 267,227,819 237,461,955 207,696,091 177,930,228
CAPEX 332,231,378 310,563,525 288,895,672 267,227,819 245,559,966 223,892,112 202,224,259
Gross Income 37,685,377 114,199,525 190,713,672 267,227,819 343,741,966 420,256,113 496,770,260
Cu% 107,826,156 160,960,043 214,093,931 267,227,819 320,361,706 373,495,594 426,629,482
Ag g/t 239,147,289 248,507,465 257,867,642 267,227,819 276,587,995 285,948,172 295,308,349
Au g/t 243,812,186 251,617,397 259,422,608 267,227,819 275,033,030 282,838,241 290,643,452

Source: Sierra Metals, 2020

Source: Sierra Metals, 2020

Figure 22-8: Sensitivity Analysis - 10,000 tpd in 2026

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 216

Source: Sierra Metals, 2020

Figure 22-9: Sensitivity NPV vs Discount Rate - 10,000 tpd in 2026

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 217

Table 22-10: Sensitivity Analysis NPV - 12,000 Tonnes/Day (US$) (12,000 tpd in 2024)

Sensitivity -30% -20% -10% 0% 10% 20% 30%
OPEX 380,691,470 348,487,530 316,283,590 284,079,651 251,875,711 219,671,771 187,467,831
CAPEX 362,035,513 336,050,225 310,064,938 284,079,651 258,094,363 232,109,076 206,123,788
Gross Income 37,343,185 119,866,092 201,972,871 284,079,651 366,186,430 448,293,209 530,399,988
Cu% 113,013,652 170,035,652 227,057,651 284,079,651 341,101,650 398,123,649 455,145,649
Ag g/t 254,231,316 264,180,761 274,130,206 284,079,651 294,029,095 303,978,540 313,927,985
Au g/t 258,664,660 267,136,323 275,607,987 284,079,651 292,551,314 301,022,978 309,494,641

Source: Sierra Metals, 2020

Source: Sierra Metals, 2020

Figure 22-10: Sensitivity Analysis - 12,000 tpd in 2024

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 218

Source: Sierra Metals, 2020

Figure 22-11: Sensitivity NPV vs Discount Rate - 12,000 tpd in 2024

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 219

Table 22-11: Sensitivity Analysis NPV - 12,000 Tonnes/Day (US$) (12,000 tpd in 2026)

Sensitivity -30% -20% -10% 0% 10% 20% 30%
OPEX 356,905,865 327,547,843 298,189,821 268,831,800 239,473,778 210,115,756 180,757,735
CAPEX 343,449,866 318,577,177 293,704,489 268,831,800 243,959,111 219,086,422 194,213,733
Gross Income 31,139,537 111,569,912 190,383,028 268,831,800 347,280,571 425,729,342 504,178,114
Cu% 104,970,830 159,857,361 214,344,580 268,831,800 323,319,019 377,806,238 432,293,458
Ag g/t 240,138,224 249,702,749 259,267,274 268,831,800 278,396,325 287,960,850 297,525,375
Au g/t 244,742,619 252,772,346 260,802,073 268,831,800 276,861,527 284,891,254 292,920,981

Source: Sierra Metals, 2020

Source: Sierra Metals, 2020

Figure 22-12: Sensitivity Analysis - 12,000 tpd in 2026

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 220

Source: Sierra Metals, 2020

Figure 22-13: Sensitivity NPV vs Discount Rate - 12,000 tpd in 2026

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 221

Table 22-12: Sensitivity Analysis NPV - 15,000 Tonnes/Day (US$) (15,000 tpd in 2024)

Sensitivity -30% -20% -10% 0% 10% 20% 30%
OPEX 377,549,280 347,734,686 317,920,093 288,105,499 258,290,905 228,476,311 198,661,717
CAPEX 381,454,960 350,338,473 319,221,986 288,105,499 256,989,012 225,872,525 194,756,038
Gross Income 26,980,168 114,114,539 201,138,952 288,105,499 375,072,045 460,877,379 546,521,155
Cu% 106,912,743 167,359,879 227,732,689 288,105,499 348,478,308 408,544,919 468,022,465
Ag g/t 256,774,015 267,217,843 277,661,671 288,105,499 298,549,327 308,993,155 319,436,982
Au g/t 260,792,582 269,896,888 279,001,193 288,105,499 297,209,804 306,314,110 315,418,415

Source: Sierra Metals, 2020

Source: Sierra Metals, 2020

Figure 22-14: Sensitivity Analysis - 15,000 tpd in 2024

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 222

Source: Sierra Metals, 2020

Figure 22-15: Sensitivity NPV vs Discount Rate - 15,000 tpd in 2024

22.2 Magnetite Recovery Project

The magnetite recovery project was evaluated as an incremental addition to the Bolivar mine project. In this section, an economic evaluation of the magnetite recovery project is provided, and is based on the 10,000 tonnes/day (10,000 tpd in 2024) case. The commodity price forecast is shown in Table 22-13. The modified Fe price forecast values used in the financial model are provided in Section 19 in Table 19-2.

Table 22-13: Commodity Price Forecast by Year

Metal Unit 2020 2021 2022 2023 Long Term (LT)
Au $/oz 1,755 1,907 1,782 1,737 1,541
Ag $/oz 19.83 24.12 22.22 22.47 20.0
Cu $/lb 2.65 2.86 2.89 2.93 3.05
Pb $/lb 0.82 0.87 0.89 0.90 0.91
Zn $/lb 0.94 0.99 1.04 1.04 1.07
Fe $/tonne N/A 153.00 125.00 100.00 80.00

Source: CIBC, Sierra Metals, 2020 (except Fe, Jeffries, June 2021)

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 223

The economic analysis of the Bolivar mine, including the incremental addition of the magnetite recovery project, indicates an after tax NPV of US$361 million (using a discount rate of 8%) at 10,000 tonnes/day (10,000 tpd in 2024). Total operating cost for the life of mine is US$1,117 million, equating to a total operating cost of US$26.73 per tonne of mineralized material milled and US$1.56 per pound copper equivalent not including the revenue from magnetite, and US$1.32 per pound copper equivalent including the magnetite revenue. Highlights of the economic analysis are provided in Table 22-14.

Table 22-14: Economic analysis of project including magnetite recovery project

Measure Unit Value
Net Present Value (After Tax 8% Discount Rate) US$ M 361
LOM Mill Feed (ROM mineralized material) Tonnes (Mt) 41.8
LOM Mill Feed (tailings) Tonnes (Mt) 6.0
Mining Production Rate t/year 3,600,000
LOM Project Operating Period Years 14
Total Life of Mine (LoM) Capital Costs US$ M 345
Total Life of Mine (LoM) Operating Costs US$ M 1,117
Net After - Tax Cashflow US$ M 650
EBITDA US$ M 1,299
Total Operating Unit Costs US$/t 26.73
LOM Copper Production (Payable) Mt 0.25
LOM Gold Production (Payable) Moz 0.15
LOM Silver Production (Payable) Moz 12.9
LOM Iron Concentrate Production, 62% Fe (Payable) Mt 5.7

Source: Sierra Metals, 2021

The magnetite recovery project is also expected to provide additional benefits that have not been accounted for in the PEA report's economic evaluation:

1. Reduction of overall tailings management costs (less tailings to be handled and stored, reduced tailings storage development capital).
2. Reduction in future closure costs.
22.3 Risk Assessment

The Bolivar Mine experiences risks that are similar to those faced by any other base and precious metals mining operation. The mine features several positive characteristics which significantly reduce the risks involved with the mine's continued operation. These include, but are not limited to, many years of proven mine extraction and processing history, knowledge and experience, a favourable regulatory climate with existing agreements and permits for operations, access, power, water and land use, and the ability to further reduce unit costs by increasing the production rate.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 224

Table 22-15 provides a list of the potential risks associated with the continued operation of the Bolivar Mine, each of which has been assigned a risk rating. The risks related to each category for Bolivar (operations, economics, technical, and other) are rated as "Low" or "Medium". No risks are assigned a "High" rating.

Table 22-15: Bolivar Mine - Risk Assessment

Risk Risk Rating
Low Medium High
Operations
LOM Schedule
Production Expansion
Infrastructure
Economics
Opex
Capex
Metal prices
Off-site treatment costs
Marketing agreements
Technical
Resources/Exploration
Geotechnical/Hydrogeological
Mining
Backfill
Pillar recovery
Processing
Tailings Storage
Other
Permits
Social License
Environment

Operations

The risks associated with the continued operation of the Bolivar Mine are considered low. The operation is in production and has been for many years. The LOM schedule is based on actual productivity data, not on engineering estimates, and is therefore considered to be realistic. The magnetite recovery project is a relatively simplistic process and is therefore estimated to be a low-risk enterprise that provides a supplementary revenue stream.

There are opportunities to lower unit operating costs by increasing the production rate, explore opportunities to recover mineralized material from pillars, and to place tailings underground for reduced surface tailings storage costs. There is no major infrastructure to construct such as a mill or tailings facilities, except the new TSF, as these already exist, as do other important infrastructure elements such as power, water, offices, and road access.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 225

Capital is being spent on the development of an underground haulage tunnel which will benefit the mine by lowering mineralized material transport costs and by improving transport reliability. Additional capital investments will be required to support an increase in the production rate (mining equipment, plant and TSF expansion, UG ventilation, backfill plant) and these costs have been included in the economic analysis.

Economics

Operating costs are based on actual production data and are therefore more accurate than estimated operating costs normally found in PEA reports. These costs form the basis of the base case (5,000 tpd) and have been conservatively factored to estimate the operating costs for higher production rates. As shown in Section 22 of this PEA report, the NPV is moderately sensitive to changes in capital cost and therefore capital cost control will be important as the mine undertakes new capital expenditures to support production expansion.

Bolivar enjoys relatively robust economics as shown in Section 22 and has pre-existing, long-term concentrate supply agreements that help to mitigate off-site risks and provide cost certainty. Nonetheless, the mine cannot control metals prices and therefore metal price fluctuations are a medium risk.

Technical

This PEA report includes Inferred Resources in the LOM schedule. Inferred Resources are too speculative to be used in an economic analysis, except as allowed for by NI 43-101 standards in PEA studies. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. There is no certainty that Inferred Resources can be converted to Indicated or Measured Resources or Mineral Reserves, and as such, there is no certainty that the results of this PEA will be realized. As such, the Mineral Resource risk for the Bolivar Mine is medium. More exploration work will be required to establish increases in Measured and Indicated Resources.

The geotechnical knowledge of the Bolivar Mine is good, and the stope and ground support designs derived from this knowledge have served the mine well. The mineralized zones yet to be developed are not considered materially different than the zones being currently mined. The mine is also very dry and there are no known hydrogeological issues or concerns. As such, the geotechnical and hydrogeological risks are deemed to be low. The mining methods employed at the mine are time-tested and proven. The only noted risk with the mining is that the recovery of mineralized material in longhole stopes with dip angles of less than 50 degrees can result in less effective recovery of mineralized material.

The use of tailings as backfill, and the mining of pillars will be new operational processes for Bolivar that require further study and evaluation. As such, these have been deemed to be medium risks. It should be noted however, that the mine has operated successfully for years without the benefit of these two processes and therefore if the Bolivar Mine elects to not proceed with tailings backfill or with pillar recovery, the mine can continue to operate, just as it does today.

The processing plant and its related tailings storage areas have been in operation for many years. The operations staff at the plant understand the mineralogy of the Bolivar Mine and the plant has demonstrated its success with the cost-effective generation of mineral concentrate. There are no indications that mill feed from any of the unmined mineralized zones in Bolivar are different metallurgically from the zones currently being mined. Therefore, processing and tailings storage risks are low.

Other

The mine is legally permitted for full mining operations, access, water, power, and land use. The mine conforms with all regulatory requirements and is recognized as a safe and efficient mining operation and is noted to be a good employer in the region. The risks associated with Permits, Social License and the Environment are all considered to be low.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 226
23 Adjacent Properties

SRK is not aware of any adjacent properties to the Bolivar Mine as defined under NI 43-101.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 227
24 Other Relevant Data and Information

There is no other relevant information or explanation necessary to make the Technical Report understandable and not misleading.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 228
25 Interpretation and Conclusions
25.1 Geology and Mineral Resources

SRK is of the opinion that the MRE has been conducted in a manner consistent with industry standards and that the data and information supporting the stated Mineral Resources are sufficient for declaration of Indicated and Inferred classifications of resources. SRK has not classified any of the resources in the Measured category due to some uncertainties regarding the data supporting the MRE.

General deficiencies related to the Geology and Mineral Resources of Bolivar include:

· No QA/QC program was conducted prior to 2016. This has been addressed by a limited resampling campaign of historical drill core and a more recent QA/QC program that was implemented in 2016. Continuation of the current QA/QC program will be required in order to achieve Measured Resources which generally are supported by high resolution drilling and sampling data that feature consistently implemented and monitored QA/QC.
· There is limited to no downhole deviation survey data for the historic drilling. The survey data obtained to date show significant deviations from planned orientations as well as local downhole deviations that influence the exact position of mineralized intervals.
· There is currently insufficient density sampling and analysis to adequately define this characteristic for the different lithological units and mineralization types in the various areas of the project. Correlation of density to mineralization characteristics is important for this type of deposit and therefore additional density sampling and analysis will be required for all future drilling.
· There is inadequate detailed structural geology data collection from drill core to support interpretation of local mineralization controls and geotechnical characteristics.
· A significant portion of the current sample database is missing gold analysis and therefore the current Mineral Resources and Reserves may not accurately reflect the true value of Bolivar mineralization locally.
· Bolivar currently does not have an adequate production reconciliation system to allow for robust comparison of mill production to mine forecasts.
25.2 Mineral Reserve Estimate

A Mineral Reserve has not been estimated for the project as part of this PEA.

25.3 Metallurgy and Processing

Sierra Metals operates a conventional concentration plant consisting of crushing, grinding, flotation, thickening and filtration of the final concentrate. Flotation tails are disposed of in a conventional TSF. Mineralized material feed during year 2019 reached a total of 1,269,697 tonnes, equivalent to an average of 105,000 t/m, or 3,500 tpd. There has been a steady increase in the production rate, and daily production rates in the latter part of 2019 frequently exceeded 4,000 tpd. As described in Section 16, the mine has made significant improvements to the on-site management team and increased its engineering resources in 2019, and the mine has greatly improved the mechanical availability of its underground mining fleet and production in early 2020 has exceeded 4,000 tpd numerous times.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 229

During 2019, production of copper concentrate consistently ranged between approximately 2,370 t/m and 3,850 t/m, equivalent to roughly a 2.9% mass pull. The monthly average concentrate consistently reached commercial quality with copper grade averaging 24.1% Cu and credit metals content in concentrate averaging 531.6 g/t silver and 5.57 g/t gold.

Piedras Verdes expenditure allocation and cost structure needs revision to ensure that the minimum possible number of items fall within the "Other" category. Currently the "Other" category is the largest one in the Piedras Verdes cost structure at 23% and should be no larger than 5%.

There is a high level of month-to-month variability for both tonnes and head grade. Better integration between geology, mine planning and processing can significantly reduce the variability. Additional work is also needed in the processing facilities to stabilize the operation. Improvements include the implementation of a preventive maintenance program and training programs to improve operators' skill, with the ultimate objective of improving metal recovery and lowering operating cost, while maintaining or improving concentrate quality.

Regarding the recovery of magnetite from both newly produced tailings from the run-of-mine ore and from the old (legacy) tailings, a 70% recovery figure is deemed to be reasonable based on the preliminary testwork done to date. The following conclusions are made regarding the recovery of magnetite:

1. Preliminary testwork shows that a minimum of 3 recovery stages may be necessary to achieve acceptable magnetite concentrate recovery.
2. The process would likely benefit from the installation of a regrinding mill in advance of the magnetic concentration plant. Further testwork is required to identify the optimal grinding target P80, but the data suggest that 100 micrometers is a potentially suitable value in order to ensure good recovery and concentrate quality (low impurities).
3. The magnetite recovery plant should conduct further tests on the variability of the head grade for both the old tailings and for fresh the newly produced tailings from run-of-mine ore, under a standard flowsheet as described in points #1 and #2.
25.4 Environmental, Permitting and Social

Based on communications with representatives from Sierra Metals, it does not appear that there are currently any known environmental issues that could materially impact the extraction and beneficiation of Mineral Resources or Reserves at Bolivar Mine.

More recent geochemical characterization data suggest that some of the more recent material from the underground mine may be potentially acid generating. Additional investigation of the current materials being deposited into the tailings impoundment may be warranted; however, given the dryness of the Chihuahuan Desert, this may not be a material issue for the project.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 230

The required permits for continued operation at the Bolivar Mine, including exploration of the site, have been obtained, based on information provided to SRK by Sierra Metals. Currently, SRK is not aware of any outstanding permits or any non-compliance at the project or nearby exploration sites.

SRK's scope of work did not include an assessment of the veracity of the closure cost estimate completed in 2017 by Treviño Asociados Consultores; however, based on projects of similar nature and size within México, the estimate appears low in comparison. SRK recommends that Sierra Metals conduct an outside review of this estimate, with an emphasis on benchmarking against other projects in northern México.

25.5 Economic Analysis

The economic summary presented in section 25.5.1 does not include any of the estimated revenue and costs for the magnetite recovery project. The magnetite recovery project was evaluated as an incremental addition to the Bolivar mine project and a summary of the economic analysis including the magnetite recovery project is provided in Section 25.5.2.

25.5.1 Economic Analysis (Not Including the Magnetite Recovery Project)

Sierra Metals makes the following interpretations and conclusions:

The PEA considered seven different production rates for the Bolivar Mine:

· 5,000 tpd (base case)
· 7,000 tpd in 2024
· 10,000 tpd in 2024
· 10,000 tpd in 2026
· 12,000 tpd in 2024
· 12,000 tpd in 2026
· 15,000 tpd in 2024

As shown in Section 22, the production rate option of 15,000 tpd (2024) has the highest incremental NPV with respect to the other options and both the 10,000 tpd (2024) and 12,000 tpd (2024) options have better returns than their 2026 counterparts. It was also found that the incremental benefit generated by increasing the production rate from 5,000 tpd to 10,000 tpd is very significant with an incremental post tax NPV of $57.4 M and an incremental post tax IRR of 28%.

However, the incremental benefit generated by increasing the production rate to 12,000 tpd or 15,000 tpd is far less significant and given that trebling the production rate could potentially present significant operational challenges, Sierra Metals therefore selected the 10,000 tpd (2024) production rate as the preferred option.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 231

The 10,000 tpd (2024) proposed mine plan requires a capital requirement (initial and sustaining) of US$ 317 M over the life of mine; efficiencies associated with higher throughputs are expected to drive a reduction in operating costs on a per tonne basis. This PEA indicates a post tax NPV (8%) at 10,000 tpd (in 2024) of US$ 283 M.

Total operating cost for the life of mine is US$ 827 M, equating to a total operating cost of US$ 19.77 per tonne milled and US$ 1.16 per pound copper equivalent. These estimated economic results do not include the proposed magnetite recovery project, and the proposed mine plan is conceptual in nature and would benefit from further, more definitive, investigation.

The Piedras Verdes processing plant can be adapted to process 10,000 tpd and would require:

· Temporary shutdown to overhaul equipment;
· Purchase of mobile jaw and cone crushers; and
· Overhaul and reintroduction of idle equipment.

The availability of tailings storage capacity is a risk to the proposed mine plan, but it is noted that there is ample underground storage that could be utilized for the storage of tailings and the financial analysis has allowed for capital and operating costs for the operation of a tailings backfill plant.

25.5.2 Economic Analysis (Including the Magnetite Recovery Project)

The economic analysis of the Bolivar mine, including the incremental addition of the magnetite recovery project, indicates an after tax NPV of US$361 million (using a discount rate of 8%) at 10,000 tonnes/day (10,000 tpd in 2024).

Total operating cost for the life of mine is US$1,117 million, equating to a total operating cost of US$26.73 per tonne milled and US$1.56 per pound copper equivalent not including the revenue from magnetite, and US$1.32 per pound copper equivalent including the magnetite revenue.

Highlights of the economic analysis are provided in Table 25-1.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 232

Table 25-1: Economic analysis of project including the magnetite recovery project

Measure Unit Value
Net Present Value (After Tax 8% Discount Rate) US$ M 361
LOM Mill Feed (ROM ore) Tonnes (Mt) 41.8
LOM Mill Feed (tailings) Tonnes (Mt) 6.0
Mining Production Rate t/year 3,600,000
LOM Project Operating Period Years 14
Total Life of Mine (LoM) Capital Costs US$ M 345
Total Life of Mine (LoM) Operating Costs US$ M 1,117
Net After - Tax Cashflow US$ M 650
EBITDA US$ M 1,299
Total Operating Unit Costs US$/t 26.73
LOM Copper Production (Payable) Mt 0.25
LOM Gold Production (Payable) Moz 0.15
LOM Silver Production (Payable) Moz 12.9
LOM Iron Concentrate Production, 62% Fe (Payable) Mt 5.7

Source: Sierra Metals, 2021

The magnetite recovery project is also expected to provide additional benefits that have not been accounted for in the PEA report's economic evaluation:

1. Reduction of overall tailings management costs (less tailings to be handled and stored, reduced tailings storage development capital).
2. Reduction in future closure costs.
CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 233
26 Recommendations
26.1 Recommended Work Programs and Costs

SRK recommends the following action items for Bolivar:

26.1.1 Geology and Mineral Resources

SRK recommends the following action items for Bolivar:

· Complete downhole surveys for all exploration and delineation drill holes using a non-magnetic downhole survey instrument
· Continue to improve upon the current sample assay QA/QC program and monitor progress of the program over time to identify trends in the preparation and analytical phases of sample analysis.
· Complement the QA/QC protocol using additional controls including coarse blanks, twin samples, fine and coarse duplicates, and a second lab control using a certified laboratory to control de different phases of the preparation and chemical analysis process.
· Document the failures in the quality control protocol and the correction measurements taken.
· Implement a consistent density testing program including the representative selection of drill core from the different lithological units and mineralization types for the various areas of Bolivar and La Sidra. Multiple density samples should be collected from every drill hole so that local density fluctuations can be assessed.
· Density samples should be submitted for geochemical analysis to allow for correlation of density to mineralization type and extent.
· Density check samples (approximately 5 to 10% of total) should be submitted to a third-party independent laboratory such as ALS Minerals for testing using ASTM standards as part of the QA/QC program. These samples should also be analyzed using the current methods employed by Sierra and reviewed to ensure that the mine site analytical performance is reasonable.
· Drill core samples previously not analyzed for gold content should be re-analyzed for gold content. Current Mineral Resources and Reserves may not reflect the true value of the mineralization and metal content due to missing gold analysis. All future drill core samples should be submitted for the full suite of geochemical analyses.
· Delineation and infill drilling are recommended in areas of Inferred Mineral Resources to facilitate upgrading to higher confidence resource categories (i.e. Indicated or Measured Mineral Resource) to support life of mine planning activities. A drill hole spacing study should be completed to provide guidance on drill hole density requirements.
CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 234
26.1.2 Mining and Geotechnical
· Detailed structural geology data collection (i.e. oriented drill core) should be implemented for all future drill holes to allow for more detailed analysis of mineralization controls and geotechnical assessments to support mine design.
· Continue to develop a site wide litho-structural model to support exploration, Mineral Resource delineation and mine design activities.
· Undertake a study for the potential of extracting mining pillars to increase mineable inventory.
· SRK notes that the use of longhole mining methods in stopes with dip angles of less than 50 degrees can result in less effective ore recovery. Ore can get hung up on the relatively shallow footwall and thus be difficult to bring down to the mucking horizon. One potential solution is the creation of a false footwall developed at a steeper dip angle to promote better ore recovery. An examination of methods to improve ore recovery in these instances should be considered.
· Undertake a backfill study to determine the suitability of using tailings as backfill in stopes.
· Implement a production reconciliation system to allow for proper reconciliation of mill production to mine forecasts. This should include the development of a dynamic grade control model to support short- and long-term mine planning activities.
· Further study on the potential benefits of selling magnetite.
26.1.3 Tailings Management

The existing tailings storage facility (TSF) is comprised of several sub-sections identified as TSF1 through TSF5. Expansion beyond TSF5 will consist of the construction of a New TSF, located to the west of the existing TSF. As part of the overall tailings management plan, Bolivar is moving to filtered tailings and in the latter part of 2020, dry-stack tailings will begin to be placed in the New TSF.

All permits are in place for TSF1 through TSF5, and for the New TSF. Sierra Metals allocated US$1 million in 2018 and US$3 million in 2019 for the TSF expansion civil works.

This PEA contemplates the use of underground storage of tailings as backfill although no studies have yet been conducted. SRK recommends that an analysis of utilizing tailings as backfill in the underground mine should be carried out, and a trade-off study completed. The underground storage of plant tailings would serve to significantly reduce the TSF volume required for surface storage and could enable a mine pillar recovery plan.

26.1.4 Environmental, Permitting and Social or Community Impact

SRK has the following recommendations regarding environment, permitting, and social or community impact at Bolivar:

· Surface road fugitive dust emissions should be continually managed in order to avoid jeopardizing the mine's social license and incurring a compliance violation from the regulatory authorities.
CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 235
· SRK recommends that Sierra Metals contract an independent, outside review of the closure cost estimate, with an emphasis on benchmarking against other projects in northern Mexico. This may require a site investigation and the preparation of a more comprehensive and detailed closure and reclamation plan before a closure specialist evaluates the overall closure approach and costs.
· Based on the 2016 geochemical characterization data, a more robust and comprehensive closure program for the tailings should be undertaken with an emphasis on closure of the existing facilities in such a manner as to not pose a risk to local groundwater resources.

Permits of underground water extraction and surface water utilization were not found. New permits for wastewater discharge were obtained in December 2019.

26.1.5 Costs

Table 26-1 lists the estimated cost for the recommended work described in Section 26.

Table 26-1: Summary of Costs for Recommended Work

Category Work Cost US$
Geology and Resources Drilling* 1,627,500
Mining Mine ventilation survey and whole-of-mine plan 100,000
Mining Pillar extraction study (includes review of use of tailings as backfill) 350,000
Environmental & Social Closure cost estimate and benchmarking exercise 50,000
Environmental & Social Development of tailings closure plan 25,000
Total $2,152,500

Source: Sierra Metals, 2020

Note: * Drilling costs assume ~15,500 meters @ US$105/m drilling costs.

Scope of drilling is difficult to assess without understanding the density of drilling required to support Mineral Resource delineation.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 236
27 References

Burō Hidrōlogico Consultoría (2016). Geological Survey of the Current Tailings Facility at Piedras Verdes, Chihuahua. (Reconocimiento Geológico en el Actual Depósito de Jales en Piedras Verdes, Chihuahua). Ing. Rubén Martínez Guerra, Ing. Yolanda Dolores Inez and Ing. Alejandra B. Mayo Vera. May, 2016, 6pp.

Burō Hidrōlogico Consultoría (2016). Final Report of the New Tailings Facility at Piedras Verdes, Chihuahua. (Informe Final del Nuevo Deposito de Jales en Piedras Verdes, Chihuahua). June 2016, 62pp.

Burō Hidrōlogico Consultoría (2016). Report on Technical Visit to Monitor Work Progress at Piedras Verdes, Chihuahua (Visita Técnica de Seguimiento de los Trabajos en Piedras Verdes, Chihuahua). Ing. Rubén Martínez Guerra, Samuel Colín López, Alejandro Rodríguez Pérez. September 2016, 15pp.

CIM (2014). Canadian Institute of Mining, Metallurgy and Petroleum Standards on Mineral Resources and Reserves: Definitions and Guidelines, May 10, 2014.

Sierra, (2016, 2017). Multiple unpublished reports, tables, maps, and figures. Provided by Sierra Metals and its subsidiaries.

Gustavson, (2013). NI 43-101 Technical Report Bolivar Mine, Chihuahua State, Mexico. Prepared for Sierra Metals Inc., by Gustavson Associates, Donald E. Hulse, Zachary Black, Karl D. Gurr, and Deepak Malhotra, Lakewood, Colorado, USA, May 31, 2013, 188pp.

Lunder, P.J., and Pakalnis, R., 1997, "Determining the strength of hard rock mine pillars," Bull. Can. Inst. Min. Metall., Vol. 90.

Meinert L.D., (2007). Unpublished internal company reports. Prepared by Lawrence D. Meinert, Department of Geology, Smith College, Northampton, MA, January 2007.

Ray, G.E., and Webster, I.C.L., (1991). An Overview of Skarn Deposits, in McMillan, W.J. and others, eds., Ore Deposits, Tectonics, and Metallogeny in the Canadian Cordillera: British Columbia Ministry of Energy, Mines, and Petroleum Resources paper 1991-4, p.213-252.

REDCO, 2018. Bolivar_NI43-101_MiningReserveReport_REDCO_rev4.docx

Reynolds M, (2008). Stratigraphy, Mineralogy and Geochemistry of The Bolivar Cu-Zn Skarn Deposit, Chihuahua, Mexico. Thesis submitted to the Department of Geology, Smith College. May 2008. 115pp.

Sierra Metals, (2010). Management Discussion and Analysis for the year ended December 31, 2009. Retrieved from http://www.sierrametals.com/investors/financial-information/financial-reports/default.aspx.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 237

Sierra Metals, (2011). Management Discussion and Analysis for the year ended December 31, 2010. Retrieved from http://www.sierrametals.com/investors/financial-information/financial-reports/default.aspx.

Sierra Metals, (2011). Press Release: Sierra Reports Another Record Production and Financial Results in the Third Quarter 2011 and Declares Commercial Production at Bolivar Mine. Retrieved from http://www.sierrametals.com/investors/news-releases/2011/default.aspx.

Sierra Metals, (2016). Condensed Interim Consolidated Financial Statements for the three and nine months ended September 30, 2016. Retrieved from http://www.sierrametals.com/investors/financial-information/financial-reports/default.aspx.

Sierra Metals, (2016). Management Discussion and Analysis for the three and nine months ended September 30, 2016. Retrieved from http://www.sierrametals.com/investors/financial-information/financial-reports/default.aspx.

SNL Financial LC, (2017). Bolivar area claim map. Retrieved from https://www.snl.com.

SRK, (2016). NI 43-101 Technical Report on Resources and Reserves, Bolivar Mine, Mexico, Effective Date: June 30, 2016, Report Date: September 9, 2016

SRK, (2017). NI 43-101 Technical Report on Resources and Reserves, Bolivar Mine, Mexico, Effective Date: October 31, 2017, Report Date: June 28, 2018

SRK, (2017). Preliminary Economic Assessment (PEA) for the Bolivar Mine, Mexico, Effective Date: October 31, 2017, Report Date: August 21, 2018

SRK, (2020). NI 43-101 Technical Report on Resources and Reserves, Bolivar Mine, Mexico, Effective Date: December 31, 2019, Report Date: May 8, 2020

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 238
28 Glossary

The Mineral Resources have been classified according to CIM (CIM, 2014). Accordingly, the Resources have been classified as Measured, Indicated or Inferred, as defined below.

A Mineral Reserve was not estimated for this PEA report.

28.1 Mineral Resources

A Mineral Resource is a concentration or occurrence of solid material of economic interest in or on the Earth's crust in such form, grade or quality and quantity that there are reasonable prospects for eventual economic extraction. The location, quantity, grade or quality, continuity and other geological characteristics of a Mineral Resource are known, estimated or interpreted from specific geological evidence and knowledge, including sampling.

An Inferred Mineral Resource is that part of a Mineral Resource for which quantity and grade or quality are estimated on the basis of limited geological evidence and sampling. Geological evidence is sufficient to imply but not verify geological and grade or quality continuity. An Inferred Mineral Resource has a lower level of confidence than that applying to an Indicated Mineral Resource and must not be converted to a Mineral Reserve. It is reasonably expected that the majority of Inferred Mineral Resources could be upgraded to Indicated Mineral Resources with continued exploration.

An Indicated Mineral Resource is that part of a Mineral Resource for which quantity, grade or quality, densities, shape and physical characteristics are estimated with sufficient confidence to allow the application of Modifying Factors in sufficient detail to support mine planning and evaluation of the economic viability of the deposit. Geological evidence is derived from adequately detailed and reliable exploration, sampling and testing and is sufficient to assume geological and grade or quality continuity between points of observation. An Indicated Mineral Resource has a lower level of confidence than that applying to a Measured Mineral Resource and may only be converted to a Probable Mineral Reserve.

A Measured Mineral Resource is that part of a Mineral Resource for which quantity, grade or quality, densities, shape, and physical characteristics are estimated with confidence sufficient to allow the application of Modifying Factors to support detailed mine planning and final evaluation of the economic viability of the deposit. Geological evidence is derived from detailed and reliable exploration, sampling and testing and is sufficient to confirm geological and grade or quality continuity between points of observation. A Measured Mineral Resource has a higher level of confidence than that applying to either an Indicated Mineral Resource or an Inferred Mineral Resource. It may be converted to a Proven Mineral Reserve or to a Probable Mineral Reserve.

28.2 Mineral Reserves

A Mineral Reserve is the economically mineable part of a Measured and/or Indicated Mineral Resource. It includes diluting materials and allowances for losses, which may occur when the material is mined or extracted and is defined by studies at Pre-Feasibility or Feasibility level as appropriate that include application of Modifying Factors. Such studies demonstrate that, at the time of reporting, extraction could reasonably be justified.

CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 239

A Mineral Reserve was not estimated for this PEA report.

Table 28-1: Definition of Terms

Term Definition
Assay The chemical analysis of mineral samples to determine the metal content.
Capital Expenditure All other expenditures not classified as operating costs.
Composite Combining more than one sample result to give an average result over a larger distance.
Concentrate A metal-rich product resulting from a mineral enrichment process such as gravity concentration or flotation, in which most of the desired mineral has been separated from the waste material in the ore.
Crushing Initial process of reducing ore particle size to render it more amenable for further processing.
Cut-off Grade (CoG) The grade of mineralized rock, which determines as to whether or not it is economic to recover its gold content by further concentration.
Dilution Waste, which is unavoidably mined with ore.
Dip Angle of inclination of a geological feature/rock from the horizontal.
Fault The surface of a fracture along which movement has occurred.
Footwall The underlying side of an orebody or stope.
Gangue Non-valuable components of the ore.
Grade The measure of concentration of gold within mineralized rock.
Hangingwall The overlying side of an orebody or slope.
Haulage A horizontal underground excavation which is used to transport mined ore.
Hydrocyclone A process whereby material is graded according to size by exploiting centrifugal forces of particulate materials.
Igneous Primary crystalline rock formed by the solidification of magma.
Kriging An interpolation method of assigning values from samples to blocks that minimizes the estimation error.
Level Horizontal tunnel the primary purpose is the transportation of personnel and materials.
Lithological Geological description pertaining to different rock types.
LoM Plans Life-of-Mine plans.
LRP Long Range Plan.
Material Properties Mine properties.
Milling A general term used to describe the process in which the ore is crushed and ground and subjected to physical or chemical treatment to extract the valuable metals to a concentrate or finished product.
Mineral/Mining Lease A lease area for which mineral rights are held.
Mining Assets The Material Properties and Significant Exploration Properties.
Ongoing Capital Capital estimates of a routine nature, which is necessary for sustaining operations.
Ore Reserve See Mineral Reserve.
Pillar Rock left behind to help support the excavations in an underground mine.
RoM Run-of-Mine.
Sedimentary Pertaining to rocks formed by the accumulation of sediments, formed by the erosion of other rocks.
Shaft An opening cut downwards from the surface for transporting personnel, equipment, supplies, ore and waste.
Sill A thin, tabular, horizontal to sub-horizontal body of igneous rock formed by the injection of magma into planar zones of weakness.
Smelting A high temperature pyrometallurgical operation conducted in a furnace, in which the valuable metal is collected to a molten matte or doré phase and separated from the gangue components that accumulate in a less dense molten slag phase.
Stope Underground void created by mining.
Stratigraphy The study of stratified rocks in terms of time and space.
Strike Direction of line formed by the intersection of strata surfaces with the horizontal plane, always perpendicular to the dip direction.
Sulfide A sulfur bearing mineral.
Tailings Finely ground waste rock from which valuable minerals or metals have been extracted.
Thickening The process of concentrating solid particles in suspension.
Total Expenditure All expenditures including those of an operating and capital nature.
Variogram A statistical representation of the characteristics (usually grade).
CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 240
28.3 Abbreviations

The following abbreviations may be used in this report.

Table 28-2: Abbreviations

Abbreviation Unit or Term
AA atomic absorption
Ag silver
Au gold
AuEq gold equivalent grade
bhp brake horsepower
°C degrees Centigrade
CoG cut-off grade
cm centimeter
cm2 square centimeter
cm3 cubic centimeter
cfm cubic feet per minute
CV Coefficient of variation
° degree (degrees)
dia. diameter
EIS Environmental Impact Statement
EMP Environmental Management Plan
g gram
gal gallon
g/L gram per liter
g-mol gram-mole
gpm gallons per minute
g/t grams per tonne
ha hectares
HDPE Height Density Polyethylene
hp horsepower
ICP inductively coupled plasma
ID2 inverse-distance squared
ID3 inverse-distance cubed
kg kilogram
km kilometer
km2 square kilometer
koz thousand troy ounce
kt thousand tonnes
ktpd thousand tonnes per day
kt/y thousand tonnes per year
kV kilovolt
kW kilowatt
kWh kilowatt-hour
kWh/t kilowatt-hour per metric tonne
L liter
L/sec liters per second
L/sec/m liters per second per meter
lb pound
m meter
CK/JJ September 2021

SRK Consulting

2US043.005 Sierra Metals Inc.

Bolivar_Technical_Report_PEA_Update

Page 241
Abbreviation Unit or Term
m2 square meter
m3 cubic meter
masl meters above sea level
mg/L milligrams/liter
mm millimeter
mm2 square millimeter
mm3 cubic millimeter
Moz million troy ounces
Mt million tonnes
MW million watts
m.y. million years
NI 43-101 Canadian National Instrument 43-101
OSC Ontario Securities Commission
oz troy ounce
% percent
ppb parts per billion
ppm parts per million
QA/QC Quality Assurance/Quality Control
RC rotary circulation drilling
RoM run of mine
RQD Rock Quality Designation
SEC U.S. Securities & Exchange Commission
sec second
t tonne (metric ton) (2,204.6 pounds)
t/h tonnes per hour
t/d and tpd tonnes per day
t/m and tpm Tonnes per month
t/y tonnes per year
TSF tailings storage facility
µm micron or microns
V volts
W watt
XRD x-ray diffraction
y year
CK/JJ September 2021

SRK Consulting (Canada) Inc.

Suite 2200 - 1066 West Hastings Street

Vancouver, BC V6E 3X2

T: +1.604.681.4196

F: +1.604.687.5532

vancouver@srk.com

www.srk.com

Local Offices: Group Offices:
Saskatoon Africa
Sudbury Asia
Toronto Australia
Vancouver Europe
Yellowknife North America
South America

Attachments

  • Original document
  • Permalink

Disclaimer

Sierra Metals Inc. published this content on 29 September 2021 and is solely responsible for the information contained therein. Distributed by Public, unedited and unaltered, on 29 September 2021 21:11:07 UTC.