Lian Hwa Foods Corporation announced the construction of new factory The contract amount of this project is TWD 2,573,424,000 (tax included). Start and end dates of the contract: Completion in 946 calendar days from the date of construction, Wastewater treatment equipment purchase and installation works with contract amount of this project is TWD 40,110,000 (tax included). Start and end dates of the contract:It will be completed of 180 working days from the completion of construction works in the wastewater treatment area and the date of supply of water and electricity and Mechanical and electrical engineering of new factory The contract amount of this project is TWD 816,000,000 (tax included).

Start and end dates of the contract: In line with the construction progress, it will be completed within 946 days from the date of construction.