ASX Announcement

29 January 2019

Gruyere Project Update

CONTACT DETAILSGold Road Resources Ltd Level 2, 26 Colin St

Highlights

West Perth WA 6005www.goldroad.com.auperth@goldroad.com.au

T +61 8 9200 1600

Successful introduction of material through Primary Crusher to Coarse Ore

ASX Code GOR

Stockpile

First ore mined as scheduled

Gold Fields

Level 5, 50 Colin St

First gold production remains on target for June 2019 quarter

West Perth WA 6005

www.goldfields.com

Construction is 91% complete and remains on schedule and on budget

T +61 8 9211 9203

JSE:GFI NYSE: GFI

Gold Road Resources Limited (Gold Road) and Gruyere Mining Company Pty Ltd, a member of the Gold Fields Limited group (Gold Fields), provide an update on construction and commissioning progress for the Gruyere Gold Project (Project), which is being developed as a 50:50 Joint Venture approximately 200 kilometres east of Laverton in Western Australia.

Project Progress

First ore was mined on schedule in January 2019 as Downer commenced double‐shift operations as part of the mining production ramp‐up. To de‐risk the Project start‐up a significant amount of ore is forecast to be stockpiled in advance of first gold production.

Construction of the Gruyere process plant and infrastructure continues to progress with overall construction at 91.2% as at 18 January 2019.

Photos clockwise from top: primary crusher to coarse ore stockpile circuit, CV02 delivering material to the coarse ore stockpile,

CV01 transfer station to CV02

Page 1 of 2

Construction works in the primary crusher area are substantially complete, with ore commissioning of the primary crusher to coarse ore stockpile circuit in progress.

The remaining process plant construction works are concentrated in the milling, CIL and elution areas and include piping, electrical and instrumentation installations and progressive commissioning of systems and equipment through these areas.

The Project remains on schedule for first gold production in the June 2019 quarter and within previously announced forecast total cost estimates.

Photos clockwise from top: Aerial Gruyere process plant, conveyor to pebble crusher and Gruyere pit

For further information, please visitwww.goldroad.com.auor contact:

Gold Road Resources

Media Enquiries - Cannings Purple

Duncan Hughes

Warrick Hazeldine or Peter Klinger

Manager - Business Development &

whazeldine@canningspurple.com.au

Investor Relations

pklinger@canningspurple.com.au

Tel: +61 8 9200 1600

Tel: +61 417 944 616 or +61 411 251 540

Page 2 of 2

Attachments

  • Original document
  • Permalink

Disclaimer

Gold Road Resources Limited published this content on 29 January 2019 and is solely responsible for the information contained herein. Distributed by Public, unedited and unaltered, on 29 January 2019 04:58:08 UTC