NSL Consolidated Limited updated the market regarding the progress of its Phase Two Wet Beneficiation Plant. Further to previous wet plant commissioning updates, a number of key miles tones have been achieved during the past three weeks: Ball mill run times have increased according to the commissioning schedule, with 6-8 hour single shift tests occurring; Classifier commissioning complete; Recirculation and fresh water feed pumps installed and commissioned; Vacuum disc filters commissioning complete; High intensity magnetic separation commissioning complete; and All equipment commissioning complete. The Company has now transitioned from equipment commissioning to complete plant process flow optimisation and commencement of production ramp up. In a major safety milestone, and testament to the onsite teams safety focus the phase two wet beneficiation plant project has reached 250,000 hours without a lost time injury (LTI).