July 21, 2021
Electric Power Development Co., Ltd. (J-POWER)
J-POWER carry out "Esashi wind power project (tentative name)"as
a joint project
J-Wind Co., Ltd., a wholly subsidiary of J-POWER, established Esashi Green Energy Co., Ltd. as a wholly owned subsidiary on June 7, 2021.
After completing the necessary procedures based on the Electricity Business Act and other related laws and regulations, we will accept the investment of SymEnergy Inc., and this project will be carried out by J-POWER Group and SymEnergy Inc.
----- | |||
1. Overview of the project | |||
Name | Esashi Windfarm | ||
Location | Esashi-town, Hokkaido, Japan | ||
Capacity | 21,000kW (General Electric 4,200kW turbine x 5) | ||
Schedule | FY2021 | Commencement of construction (planned) | |
December | |||
2022 | Commencement of commercial Operations (planned) |
2. Project scheme (planned)
3. Location map
Attachments
- Original document
- Permalink
Disclaimer
EPDC - Electric Power Development Co. Ltd. published this content on 21 July 2021 and is solely responsible for the information contained therein. Distributed by Public, unedited and unaltered, on 21 July 2021 07:24:38 UTC.