16 June 2022

onlyDevelopment Activities Continue at Lindi Jumbo as it advances towards Commissioning

Walkabout Resources Ltd (ASX:WKT, 'Walkabout' or the 'Company') is pleased to advise that construction activities are continuing at Lindi Jumbo, in addition to the nearing of completion of the manufacture and acquisition of major processing equipment in China. This is despite the delayed drawdown of the USD20 million project debt facility through CRDB Bank Plc (CRDB) announced on 6 June 2022.

useHIGHLIGHTS

  1. Established and trusted relationships with all major contractors have seen the continuation of works while the last condition precedent (CP) for debt drawdown is being finalised.

personal

o Development progress on the ground is more than 50% complete against the construction schedule.

o

Key milestones advancing commissioning include:

Manufacture and acquisition of major processing equipment complete by EPC contractor, Yantai

Jinpeng Mining Machinery (Jinpeng), with shipment of items not already on-site pending debt

drawdown.

Arrival of major equipment in the processing plant flow onsite and awaiting installation.

Completion of crushing, grinding, conveyors and thickener civils, enabling commencement of

steelwork and equipment erection.

Completion of pre-strip of the starter pit, with drilling underway in preparation of the first blast.

Continuation of tailings storage facility (TSF) groundworks with application of an impervious clay

base and all fill of the keys nearing completion.

For

o TANESCO, the Tanzanian Electrical Supply Company, has commenced connection of the Lindi Jumbo site

to the national grid and provided written confirmation of the planned sufficient supply of grid power for

the entire operation, expected to result in a significant reduction in operating costs.

o Offtake negotiations have continued with a focus on finalising the key commercial terms including pricing and off-take profile.

Walkabout Resources' CEO, Andrew Cunningham commented, "The support and trust from our major contractors has been overwhelming and is testament to our long-termrelationships, project viability and commitment to 'local first', with teams remaining mobilised and continuing development as scheduled despite temporary setbacks.

The processing plant, supporting infrastructure and mining area are now rapidly taking shape as we continue to advance Lindi Jumbo safely towards commissioning and achieve Tanzania's first sustainable graphite production under the new Administration."

DEBT DRAWDOWN

As announced on 6 June 2022, the Company is working towards securing the final conditions precedent ("CP") that needed to be fulfilled before drawdown of the USD20 million debt facility could commence. Progress is made on various fronts towards fulfilling this last CP and the market will be informed as soon as resolved. Lindi Jumbo continues to be supported by CRDB and various other parties as we work towards this.

only

MINE DEVELOPMENT ACTIVITIES

EARTHWORKS AND CIVILS

Si

ce the last update the project has not recorded any lost time injuries. More than 150 workers continue to

pr

gress earthworks and civils with processing plant civil works reaching 78% completion and strong headway

making up for some of the minor delays caused by the heavy rains since the beginning of the year.

Concrete works were aligned with the shipping schedule and various work fronts have been opened for simultaneous steelwork construction by the EPC team, Jinpeng. Since May, and further to the announcement on

30 April 2022, the following progress has been made:

use

o

Thickener civils complete

o

Conveyors civils complete

personalFor

o Fine Ore Bin civils complete

o

Crusher Civils complete

o

Screen civils complete

o Concentrator building and mill bases casted

o

TSF - 37% complete:

fill pre‐deposition of the embankments in progress

piping delivered and partially installed

lining in country

Figure 1: Oblique view from the south of the TSF. Clay filled cut-off keys around the TSF footprint are clearly visible (left). Excavation of the

stormwater cut off trench at the TSF (right).

Various samplers; Drum Scrubber; Graphite deglomerator; Various silos;
BGRIMM Attritioning mills; Crane beams and hoists; Dust collectors;
Various spiral conveyors;

only

Figure 2: Top view of the processing plant area. Numerous pieces of equipment visible including the floatation cells, filter presses, crushers,

use

screw classifiers, fine ore bin sections and laydown of the structural steel components.

ENGINEERING, PROCUREMENT AND CONSTRUCTION PROGRESS

personal

EPC Contractor, Jinpeng, has completed the manufacture and acquisition of the majority of the major equipment for the processing plant. While all previous shipments of equipment have been delivered to the Lindi Jumbo site, several batches of factory acceptance tested equipment are in storage in China and remain on standby for loading. Shipping of the equipment will commence upon drawdown of the project debt (see announcement on 6 June 2022).

The delay in despatch of these remaining shipments will impact the overall project schedule and as logistics become clearer this will be communicated to the market.

With the mechanical construction team on site since April, the erection of the steelwork had commenced focussing on the fine-ore bin, thickener, front-end (ROM Bin) and conveyor areas of the processing plant. The civils completed to date were prioritised to these areas.

Equipment awaiting despatch to Tanzania includes:

o o

o

Foro

o o o o

o Dryer;

o Concentrate bag packaging equipment;

o Steel Structures for various of the processing plant buildings; and

  1. Rotex screens manufactured and assembled in Melbourne, Australia (refer Figure 4).

For personal use only

Figure 3: Graphite concentrate bagging equipment undergoing factory testing in China.

Figure 4: Rotex Screens assembled at the workshop in Melbourne.

Figure 5: Steelwork construction on site using the Lindi Jumbo 55-ton crane (left) and transport of an assembled section of the fine-

ore bin for installation (right).

STARTER PIT

Earthworks, including the removal and stockpiling of the topsoil, the removal of the clay rich saprolitic material, and the exposure of the bedrock in preparation of drilling and blasting at the starter pit area is nearing completion the first blast planned for late June (refer Figure 6 and 7). The starter pit has been chosen to generate maximum waste rock and clay

rich material for the construction of the TSF retainer wall, while at the same time exposing and selected excavation of the high-grade graphitic material for the commissioning and start-up of the processing plant. Care was taken to avoid the highly visible super high-grade zones that will form the baseload of the run of mine stockpile.

The waste rock generation starter pit will potentially have a positive knock-on effect on the operating costs for the

initial period of the proposed mine plan with a higher ratio of ore to be produced. As with all of the construction areas,

care is taken to keep the operational footprint as small as possible in line with the Company's efforts to minimise the

useonly

environmental and carbon footprint.

Figure 6: Starter pit pre-strip. The area is approximately 700m to the west of the Processing Plant area. Approximately 0.30 to 1m

personal

of clay rich saprolitic waste material has been used in the construction of the TSF.

For

Figure 7: Drilling in preparation of the first blast.

SUPPLY OF GRID POWER TO LINDI JUMBO CONFIRMED

Lindi Jumbo has received confirmation from the Tanzanian Electrical Supply Company (TANESCO) of their commitment to extend the existing 33Kv line to the Lindi Jumbo site and that the power infrastructure can handle the expected load of 4.5MW for continuous plant operations. The supply of grid power to site is expected to:

1. Significantly, lower operational costs in comparison to the diesel generators scoped in the feasibility study. Previously, power related expenses represented the largest operating cost of the processing plant with grid power

a gamechanger at only a fraction of the cost;

This is an excerpt of the original content. To continue reading it, access the original document here.