Currently, the physical progress of civil works is 91.2%, electromechanical supply is 87.9% and electromechanical assembly is 37.1%. The consolidated advance as of December is 83.4%, being the deviation of the river already fully accomplished. The implementation of the Project is in accordance with the schedule initially established.
EESM is a partnership, in the proportion of 1/3 (one third), among EDP, China Three Gorges Brasil Energia Ltda. and Furnas Centrais Elétrica S.A.
Miguel Nuno Simões Nunes Ferreira SetasCEO and IR Director
IR Tea m
Marilia Barbosa Nogueira Maria Rodrigues Amanda C. Pecorari +55 (11) 2185-5907ri@edpbr.com.br www.edp.com.br/ri