Cathay Real Estate Development Co.,Ltd. announced change of the construction contract of 13 lands located at No.588th,Lot Dongqiao,Hsinchu City. The contract amount is about TWD 1.43 billion(before-tax)™. The contract starts from the date signed and was expected to be completed in August 2020.

Reason for change and its main content: The contract amount increase in TWD 4,745,199 (before-tax) was incurred from change in design changes. As such, the contract amount increase to TWD 1.44 billion (before-tax)™ . The contract ending date was changed to October 2020.