    KEY POINTS:

    TIRIS PROJECT (Mauritania)

      * Tiris Definitive Feasibility Study (DFS) recommenced in all project aspects
      * Resource definition work underway
      * Environmental Study commenced
      * Water search geophysics and testing underway
      * Metallurgical test work planning advanced
      * Appointments of key project people undertaken
      * Preparation of documents for the Mining Lease Application
      * Two additional Exploration Permits were granted to Aura

    TASIAST SOUTH GOLD PROJECT (Mauritania)

      * Planning continued for exploration of Aura's gold tenements
      * Excellent drill results report on adjacent Algold Resources (TSX) tenements

    AMARE LITHIUM AND SODA ASH PROJECT (Mauritania)

      * Sampling of the Amare lithium and soda ash prospect was undertaken

    HÄGGÅN PROJECT (Sweden)

      * Preparation for a diamond drilling program to commence in February 2017
      * Work continues establishing a brief for the Community Liaison program

    CORPORATE

      * Meetings with Mines Minister and other officials in Mauritania

    Quarterly Overview

    Following Aura Energy's successful London Stock Exchange (AIM) listing and
    significant funding in September 2016 the company recommenced its key task of
    completing the Tiris Definitive Feasibility Study (DFS). With positive
    sentiment returning to the uranium price and equities, Aura's ability to get
    Tiris into production is the main near-term driver of shareholder returns.

    As such, a major activity for the December quarter was the recommencement of
    the Tiris DFS. This involved the re-establishment of the project team, planning
    of the DFS activities and significant work on the ground in Mauritania.

    Aura also continued to evaluate the best approach for exploration on its
    significant Tasiast South gold prospects and noted the significant results on
    the adjacent of Algold Resources (TSX) which justifies Aura's conviction that
    our gold strategy has considerable strength.

    The Sabkha adjacent to Aura's uranium projects was sampled for lithium and soda
    ash for the first time and the company will continue to review opportunities in
    this area as they arise.

    Planning of community engagement for the Häggån Project in Sweden has
    continued.

    The commodity backdrop in uranium has become more buoyant improving sentiment
    in the sector and the company remains in a well-funded position.

    Tiris Project, MAURITANIA (Aura 100%)

    Tiris Project Overview

    Aura is conducting a feasibility study on its 100% owned 49 million pound U?O?
    calcrete project in Mauritania (See Figure 1). The project has low operating
    costs and low development capital with strong financial returns under long-term
    pricing scenarios.

    To view this release as a .pdf complete with referenced images please click the
                                    following link:                                

             http://www.auraenergy.com.au/investor/ASX%20Announcements/2017/       
         Quarterly%20Report%20December%202016%20and%20Appendix%205B%20%20.pdf      

             Figure 1: Location of Aura's Tiris Project Uranium Resources          

    Tiris Project Studies

    The Tiris DFS recommenced across many critical areas of the project during the
    period. In general terms, the main areas remaining in the study are resource
    upgrade and validation, leaching test work and process design, environmental
    and social impact study and infrastructure.

    In the period the main aspects of work were;

      * Recruitment of a Study Manager who has developed projects in the relevant
        regions of Africa
      * Permanent appointment of Dr Will Goodall as Principal Metallurgist for Aura
        Energy
      * Completion of a downhole logging survey as part of the resource validation
        assessment
      * Ultra-detailed ground radiometric surveying over the key resource zones to
        establish more precisely the outlines of, and zonation within,
        mineralisation across the major resources
      * This ground radiometric survey work was continued over the Hippolyte South
        prospect, currently under application, which hosts extensive and strong
        radiometric anomalies south of the main Hippolyte resource. This will
        define drill targets for future resource drilling on this very prospective
        target
      * Planning for continuation of previous metallurgical studies for leaching
        and beneficiation
      * Environmental and social impact assessment field work was undertaken with
        consultants on all resource sites.  Associated meetings with relevant
        government officials have also taken place and are continuing
      * The Terms of Reference for the Environmental and Social Impact Statement
        was submitted to the government
      * Water search consultants have commenced work which involves an initial
        program of ground geophysics to select drill targets prior to drill testing
        of these sites. The study will focus principally on the basal sedimentary
        units of the Taoudeni Basin to the south of the project area. These are
        known to host substantial water supplies elsewhere in the region. A few
        favourable sites on Reguibat Shield rocks closer to the project site will
        also be tested in this program
      * Preparation of documents for the Mining Lease Application
      * Two additional Exploration Permits were granted to Aura. One, Oum Ferkik
        South, covers the extension to the south of the mineralised zone that
        contains Aura's Ferkik Resource.  The other, Aguelet, contains an Inferred
        Resource of 0.7 million lbs U3O8 at 240 ppm U3O8

    AMARE LITHIUM AND SODA ASH PROJECT (Mauritania)

    Aura recently announced that as part of a continual review of mineral
    opportunities in Mauritania, it has taken a position in 2 large Sabkhas (salt
    pans) in the region of its Tiris Uranium Project with a view to exploring them
    for soda ash and other minerals.

    Soda ash is the leach agent proposed for Tiris and if the source were confirmed
    it would provide significant benefits to the Tiris Project economics.

    The Sabkha's which are 165 km from Hippolyte are large on a relative basis
    covering an area of over 85 km2 (See Figure 2). Sabkha is an Arabic name for a
    salt-flat that has come into general use in sedimentology. They are also known
    as "Salars" in South America and generically as salt pans or flats. The
    valuable salts can occur in the Sabkha environment either in clays at or near
    surface or in brine reservoirs deeper in the lake sediments.

    The location of the Sabkha between Aura's Tiris Project East and West tenements
    provide a favourable location should a source of soda ash (Na2CO3) be
    identified.

    Initial sampling of the Amare lithium and soda ash prospect was undertaken
    during the period and assaying is underway.

    Aura will continue to review other opportunities for similar mineral
    occurrences throughout the local region given the favourable conditions for the
    numerous Sabkha's close to its project areas.

    To view this release as a .pdf complete with referenced images please click the
                                    following link:                                

             http://www.auraenergy.com.au/investor/ASX%20Announcements/2017/       
         Quarterly%20Report%20December%202016%20and%20Appendix%205B%20%20.pdf      

        Figure 2:  Location of the Sabkha targets relative to the Aura Uranium     
                                 Exploration Licences                              

    Tasiast South gold Project, MAURITANIA (Aura 100%)

    Aura Energy Limited announced in late 2016 that it has secured rights to
    acquire 175 km2 covering two under-explored mineralised greenstone belts in
    Mauritania (See Figure 3). The areas lie along strike from Kinross' giant
    Tasiast Gold Mine and from Algold's Tijirit gold deposits. The two areas are
    currently held under exploration permit applications and are expected to be
    granted in the near future.

    These highly prospective gold areas represent an excellent opportunity in
    lightly explored Archean greenstone belts and will leverage Aura's extensive
    operating experience in this part of the world. The project is favourably
    located 200 km from Aura's Nouakchott office, 60 km from the coast, and can be
    managed efficiently within the company's existing management resources without
    distraction from Aura's core uranium focus.

    To view this release as a .pdf complete with referenced images please click the
                                    following link:                                

             http://www.auraenergy.com.au/investor/ASX%20Announcements/2017/       
         Quarterly%20Report%20December%202016%20and%20Appendix%205B%20%20.pdf      

         Figure 3:  Location of Aura areas in relation to known mineralisation     

    Aura's Tasiast South project area has the following attributes;

      * Tenements over two lightly explored greenstone belts covering 175 km2 
      * The +20 Moz Tasiast gold deposit is nearby on the same greenstone belt and
        highlights the potential for major deposits in the region (See Figure 3)
      * $3m has been expended by the previous explorer on airborne geophysics,
        reverse circulation and air-core drilling, and sampling
      * Broad zones of gold mineralisation have been identified with strong
        similarities to the Tasiast Gold Mine mineralisation and alteration
      * No testing deeper than 150m with most previous holes less than 100m
      * High grade drill intersections have been reported by others in the district
        from both past and current programs, including one in progress with Algold
        Resources (TSX), which highlight the current interest and potential in
        these poorly tested belts

    During the period Aura continued to plan and assess the best approach to the
    exploration of these tenements.

    Nickel and Base Metal Potential

    Previous exploration for gold on these permit areas also located strongly
    anomalous nickel values in several areas, associated with ultramafic rocks (See
    Figure 4). In parts of the tenements high nickel values are associated with
    anomalous copper highlighting potential for nickel-copper sulphide
    mineralisation, as occurs also in the greenstone belts of Australia and Canada.
    At this stage, there has been no follow-up work carried out on these nickel
    targets.

    To view this release as a .pdf complete with referenced images please click the
                                    following link:                                

             http://www.auraenergy.com.au/investor/ASX%20Announcements/2017/       
         Quarterly%20Report%20December%202016%20and%20Appendix%205B%20%20.pdf      

        Figure 4:  Key nickel results in bedrock sampling by air-core drilling     

    Future Work Program and Other Opportunities

    Next steps envisaged at Tasiast South are;

      * Ground electrical geophysics to locate the strongest zones of disseminated
        sulphide development for drill targeting
      * Additional bedrock sampling by air-core or auger-drilling to better define
        the high nickel ultramafics and zones of copper/nickel for follow up
        drilling
      * Deep drill testing (RC and DD) of targets defined

    Aura's timing for this work is dependent on granting of the permits and on
    financing however some of the work described is relatively low cost and may be
    funded from existing resources. Aura will also explore other financing options
    to progress this work plan including joint ventures, royalties and
    work-for-equity funding.

    HÄGGÅN PROJECT, SWEDEN (AURA 100%)

    Häggån Development

    The Häggån Project has an Inferred Resource of 803 million pounds of U3O8(1).
    Scoping studies previously completed by Aura have indicated that the Häggån
    Project has the potential be a very large low cost uranium producer.

    Work continued regarding a community engagement for the Häggån Project.

    The key aspects of the community liaison program are twofold;

      * Recruitment of an appropriate representative
      * Further the education and understanding of Aura's project in those areas
      * Completion of an economic development study to outline the benefits of the
        project in terms of direct and indirect jobs, capital outlay and broader
        contribution to the local and regional economy

    Aura continues to press the Häggån project as a unique and strategic energy
    source in Europe which the European nuclear energy sector is beginning to
    realise can play an important role as a uranium source in the future.

    Aura believes Häggån is a 5-7 year proposition as a development project and is
    scoping its work program around that time frame.

    A program of 750m of diamond drilling in 3 holes is programmed for the first
    Quarter 2017 for geostatistical and resource upgrade purposes.

    URANIUM SECTOR AND PRICE

    The price of uranium has enjoyed improved sentiment and recovered from its
    recent lows in the face of producer cutbacks. The current price series is as
    follows:

      * Spot Price        - US$23.65/lb
      * Mid Term        - US$22.00/lb
      * Long Term       - US$30.00/lb

    Key points of interest to note from the uranium sector have been:

      * KazAtomProm stated it would cut output by 10%, equivalent to 2000t or 3% of
        global supply, because of low prices
      * The Trump presidency may result in a more pro-nuclear stance by the US and
        policy shifts in the US under a new administration are likely to play an
        important role in the nuclear industry over the next few years
      * Over the next 2-3 years, many of the long-term supply contracts will expire
        requiring renegotiation at prices unlikely to be done at current midterm or
        long-term pricing

    A key point worth repeating and highlighting is the lack of term contracting in
    2013 and 2014 as shown in Figure 5 below. This remains a key risk for utilities
    going forward and will need to be filled at some stage. This contracting phase
    will strongly impact the Long Term price as evidenced in Figure 5 between 2004
    and 2007.

    To view this release as a .pdf complete with referenced images please click the
                                    following link:                                

             http://www.auraenergy.com.au/investor/ASX%20Announcements/2017/       
         Quarterly%20Report%20December%202016%20and%20Appendix%205B%20%20.pdf      

                          Figure 5: Spot vs Long Term pricing                      

    CORPORATE

    Mauritanides Conference - Mauritania

    Aura Energy attended the Mauritanides conference in Nouakchott Mauritania in
    October 2017. The government sponsored bi-annual conference is the key
    resources conference in the country and is attended by the President, Prime
    Minister and Mines Minister.

    Key points of the conference and trip was;

      * Excellent company meetings with the Mines Minister demonstrating strong
        support for Aura's activities in the country
      * The depth of resource industry involvement in the country including
        significant Oil and Gas activity
      * Recent success of Algold's gold exploration and its significance to Aura's
        gold properties

    Aura Energy Directory

    ASX Code:          AEE            
                                      
    AIM Code:          AURA           
                                      
    Shares on issue:   719,715,374    
                                      
    Options on issue:  185,443,076    
                                      
    Warrants on issue: 6,578,699      

    Board of Directors:

    Peter Reeve        Executive Chairman        
                                                 
    Bob Beeson         Non-Executive Board Member
                                                 
    Brett Fraser       Non-Executive Board Member
                                                 
    Jules Perkins      Non-Executive Board Member

    Website:                     www.auraenergy.com.au  

    For further information contact:

    Aura Energy Limited                   Telephone: +61 (3) 9516 6500      
    Peter Reeve (Executive Chairman and   Email: info@auraenergy.com.au     
    CEO)                                                                    
                                                                            
    WH Ireland Limited                    Telephone: +44 (0) 207 220 1666   
    Adrian Hadden                                                           
    Katy Mitchell                                                           
    James Bavister                                                          
                                                                            
    Yellow Jersey PR Limited              Telephone:                        
    Felicity Winkles                      +44 (0) 7748 843 871              
    Joe Burgess                           +44 (0) 7769 325 254              

    Competent Persons

    The Competent Person for the Tiris Metallurgical Testwork is Dr Will Goodall.

    The information in the report to which this statement is attached that relates
    to the testwork is based on information compiled by Dr Will Goodall.  Dr
    Goodall has sufficient experience that is relevant to the testwork program and
    to the activity which he is undertaking.  This qualifies Dr Goodall as a
    Competent Personas defined in the 2012 edition of the 'Australasian Code for
    Reporting of Exploration Results, Mineral Resources and Ore Reserves'.  Dr
    Goodall is a Member of The Australasian Institute of Mining and Metallurgy
    (AusIMM).  Dr Goodall consents to the inclusion in the report of the matters
    based on his information in the form and context in which it appears.

    The Competent Person for the Tiris and Häggån Resources is Mr Neil Clifford.

    The information in the report to which this statement is attached that relates
    to the resource is based on information compiled by Mr Neil Clifford.  Mr
    Clifford has sufficient experience that is relevant to the style of
    mineralisation and type of deposit under consideration and to the activity
    which he is undertaking.  This qualifies Mr Clifford as a Competent Person as
    defined in the 2012 edition of the 'Australasian Code for Reporting of
    Exploration Results, Mineral Resources and Ore Reserves'. Mr Clifford is a
    Member of the Australasian Institute of Mining and Metallurgy (AusIMM). Mr
    Clifford consents to the inclusion in the report of the matters based on his
    information in the form and context in which it appears.

    Top 20 Shareholders                                                    27 January 2017
                                                                                          
    Rank Name                                                        Units       % of     
                                                                                 Units    
                                                                                          
    1.   COMPUTERSHARE CLEARING PTY LTD                 255,974,288 35.57    
                                                                                          
    2.   BNP PARIBAS NOMINEES PTY LTD     59,599,268  8.28     
                                                                                          
    3.   HSBC CUSTODY NOMINEES (AUSTRALIA) LIMITED                   37,675,274  5.23     
                                                                                          
    4.   PRE-EMPTIVE TRADING PTY LTD                                 35,700,000  4.96     
                                                                                          
    5.   ABN AMRO CLEARING SYDNEY NOMINEES PTY LTD    16,077,504  2.23     
                                                                                          
    6.   SAMBOLD PTY LTD                    13,764,895  1.91     
                                                                                          
    7.   PASAGEAN PTY LIMITED                                        12,313,946  1.71     
                                                                                          
    8.   MR PETER DESMOND REEVE                                      9,718,304   1.35     
                                                                                          
    9.   J P MORGAN NOMINEES AUSTRALIA LIMITED                       6,566,696   0.91     
                                                                                          
    10.  MR MICHAEL BUSHELL                                          5,474,903   0.76     
                                                                                          
    11.  MR PIETER HOEKSTRA + MRS RUTH HOEKSTRA                                                                              
                                                                                          
    12.  YARANDI INVESTMENTS PTY LTD       4,754,793   0.66     
                                                                                          
    13.  MS MICHELLE ANNE PAINE                                      4,500,000   0.63     
                                                                                          
    14.  MRS KERRYN PATRICIA DELEN                                   4,333,840   0.60     
                                                                                          
    15.  MS CHUI YING CHAN                                           3,459,000   0.48     
                                                                                          
    16.  M & K KORKIDAS PTY LTD         3,400,000   0.47     
                                                                                          
    17.  MRS LINDA YE + MR DAVID XIAO DONG YE                        3,160,000   0.44     
                                                                                          
    18.  DR ROBERT BEESON                                            3,129,071   0.43     
                                                                                          
    19.  MRS JENNY LEE BUSHELL                                       3,091,182   0.43     
                                                                                          
    20.  MR SCOTT ANDREW ROBERTS                                     3,001,001   0.42     
                                                                                          
         Total Top 20 Shareholders                                   490,993,965 68.22    
                                                                                          
         Remaining Shareholders                                      228,721,409 31.78    
                                                                                          
         GRAND TOTAL                                                 719,715,374 100.00   

       

    Top 20 Shareholders                                                    28 October 2016
                                                                                          
    Rank Name                                                       Units         % of    
                                                                                  Units   
                                                                                          
    1.   COMPUTERSHARE CLEARING PTY LTD                263,692,309   36.81   
                                                                                          
    2.   BNP PARIBAS NOMINEES PTY LTD    59,514,268    8.31    
                                                                                          
    3.   HSBC CUSTODY NOMINEES (AUSTRALIA) LIMITED                  58,785,060    8.21    
                                                                                          
    4.   PRE-EMPTIVE TRADING PTY LTD                                35,900,000    5.01    
                                                                                          
    5.   ABN AMRO CLEARING SYDNEY NOMINEES PTY LTD   14,063,092    1.96    
                                                                                          
    6.   SAMBOLD PTY LTD                   13,764,895    1.92    
                                                                                          
    7.   PASAGEAN PTY LIMITED                                       12,313,946    1.72    
                                                                                          
    8.   MR PETER DESMOND REEVE                                     9,718,304     1.36    
                                                                                          
    9.   MR MICHAEL BUSHELL                                         5,474,903     0.76    
                                                                                          
    10.  CITICORP NOMINEES PTY LIMITED                              5,296,852     0.74    
                                                                                          
    11.  MR PIETER HOEKSTRA + MRS RUTH HOEKSTRA                                                                         
                                                                                          
    12.  YARANDI INVESTMENTS PTY LTD      4,754,793     0.66    
                                                                                          
    13.  MS MICHELLE ANNE PAINE                                     4,150,000     0.58    
                                                                                          
    14.  MRS KERRYN PATRICIA DELEN                                  3,333,840     0.47    
                                                                                          
    15.  MRS LINDA YE + MR DAVID XIAO DONG YE                       3,160,000     0.44    
                                                                                          
    16.  DR ROBERT BEESON                                           3,129,071     0.44    
                                                                                          
    17.  MRS JENNY LEE BUSHELL                                      3,091,182     0.43    
                                                                                          
    18.  MR PETER ROBERT OTTON + MRS CAROLE ANNE OTTON                                                                         
                                                                                          
    19.  MR HENDRIK JACOBUS DELEN + MRS KERRYN PATRICIA DELEN       2,914,492     0.41    
                                                              
                                                                                          
    20.  MR JULIAN CHRISTOPHER PERKINS + MS MARGARET SU-PING FONG   2,861,990     0.40    
                                                                     
                                                                                          
         Total Top 20 Shareholders                                  513,718,997   71.71   
                                                                                          
         Remaining Shareholders                                     202,682,574   28.29   
                                                                                          
         GRAND  TOTAL                                               716,401,571   100.00  

    About Aura Energy's Projects

    Tiris Project, MAURITANIA (Aura 100%)

    The Tiris Uranium Project is based on a major greenfields uranium discovery in
    Mauritania, with 49 Mlb U3O8 in current resources(1) from 66 million tonnes @
    334 ppm U3O8. The project has several natural attributes which result in low
    capital and operating costs. These attributes are:

      * Shallow flat-lying surface mineralisation (only 1-5 metres deep) within
        unconsolidated gravels
      * Low cost mining with no blasting and negligible overburden
      * Uranium ore can be simply (wash and screen) upgraded by up to 700%; from
        335 ppm to 2500ppm
      * Leads to a very small plant, small footprint and minimal supporting
        infrastructure
      * Leach feed grade 2,000-2,500 ppm U3O8 with 94% leaching recovery in 4 hours

    The conceptual 1 Mtpa mine and plant project described in the Scoping Study(2)
    was designed to take full advantage of these unusual characteristics, whilst
    providing a low capital cost and rapid project development and construction.
    Significantly, a water study by Golders has indicated that potential sources of
    water in the immediate vicinity will satisfy the demands of the project.

    The Study, which indicates 11 million pounds of uranium will be produced over
    an initial mine life of 15 years, only utilises 20% of the known Global Mineral
    Resource resulted in the following outputs;

      * Low capital cost - US$45 million
      * Low operating cost - A$30/lb
      * Easily scalable
      * Mining at ~120 tph (1.0 Mtpa)
      * Small 25 tph leach facility
      * Mined grade >420ppm U3O8 for 15 years
      * Produce 0.7-1.1 Mlbs U3O8 per year
      * Expand project from cashflow

    HÄGGÅN PROJECT, SWEDEN (AURA 100%)

    Häggån is located in central Sweden and is one of the largest undeveloped
    uranium projects in the world. The project has a resource of 803 million pounds
    (3) uranium with significant base metal by-products.

    Sweden remains a nuclear friendly jurisdiction with 10 operating nuclear power
    reactors. In 2013, Sweden generated 152.5 TWh, of which 65.8 TWh (43%) was from
    nuclear and 61.3 TWh (40%) from hydro. Sweden imports most of its nuclear fuel,
    including all enrichment. It is one of the few countries that has the
    opportunity, within its sovereign borders, to be vertically integrated from
    nuclear power generation down to the U3O8 fuel source. Public opinion polls in
    the last few years had shown steady majority (over two-thirds) support for
    nuclear power(4).

    The Häggån project is located in a sparsely populated area of swamp and forest
    used mainly for commercial forestry. Sweden's has a current and active mining
    industry, with a clear regulatory position and a well-established path from
    exploration to production.

    A Scoping Study(5) suggests that the Häggån Project has excellent potential to
    become a major, low cost producer of uranium, with by-product nickel and other
    metals. Aura's discovery that the mineralisation is ideally suited to bioleach
    metal extraction was the major breakthrough to creating a robust and economic
    project. Bioleaching, including bioheap leaching, is a proven technology widely
    used in copper and gold industries with some application to the uranium
    industry.

    The Häggån Inferred Resource contains 2.35 billion tonnes at the grades shown
    in the table below. Metal content is also shown.

     Metal    Grade   Content 
              (ppm)    (Mlbs) 
                              
      U3O8     155      803   
                              
       Ni      316      1640  
                              
       Zn      431      2230  
                              
       Mo      207      1070  
                              
       V       1519     7870  

    The project contemplated in the Scoping Study was a large scale heap leach with
    recovery of base metals as separate and high purity sulphide precipitates. The
    Scoping Study outcomes were as follows;

      * Capital cost - US$540 million
       
      * Low operating cost - A$13.50/lb U3O8
       
      * Mining rate 30 Mtpa
       
      * Mined grade 160 ppm U3O8 for 30 years
       
      * Production 7.8 Mlbs U3O8 per year
       
        NOTES TO PROJECT DESCRIPTIONS
       
    (1) There is a low level of geological confidence associated with inferred and
    measured mineral resource and there is no certainty that further exploration
    work will result in the determination of indicated measured resource or that
    the production target will be realised.

    (2) The Company released to the ASX the Tiris Project Scoping Study on 16 July
    2014 and the Company believes that no material change to forecast capital and
    operating costs and forecast production rates have occurred since the release.

    (3) There is a low level of geological confidence associated with inferred
    mineral resource and there is no certainty that further exploration work will
    result in the determination of indicated measured resource or that the
    production target will be realised.

    (4) http://www.world-nuclear.org/info/Country-Profiles/Countries-O-S/Sweden

    (5) The Company released to the ASX the Haggan Project Scoping Study on 7
    February 2012 and an updated study on 29 May 2014. The Company believes no
    material change to forecast capital and operating costs and forecast production
    rates have occurred since the releases.