Trans-Siberian Gold plc reported production results at Asacha plant for the month and year to date ended May 2013. Trans-Siberian Gold plc provided an update on mining and production at Asacha in the first five months of 2013 at the company's Annual General Meeting. Mine development in April and May 2013 comprised 564 metres, while ore extraction (including ore from stoping and mine development) amounted to 32,410 mt. In the same period, an average 12,120 mt per month was processed through the Asacha plant. The plant produced gold refined of 2,748 oz and silver refined of 3,245 oz.

For the year to date, the plant produced gold refined of 11,159 oz and silver refined of 14,216 oz compared to gold refined of 10,199 oz and silver refined of 11,857 oz a year ago.

The company expects production of 33,800 oz gold and 62,000 oz silver for the fiscal 2013.