Paragon Diamonds Limited / Index: AIM / Epic: PRG / Sector: Resources     

    15 September 2015

                 Paragon Diamonds Limited ('Paragon' or the 'Company')             

                Positive Technical Study for Mothae Kimberlite Project             

    Paragon Diamonds Limited, the AIM quoted diamond development company, is
    pleased to announce the results of two independent studies carried out by The
    MSA Group on the Mothae Kimberlite Project ('Mothae'), located in Lesotho, that
    Paragon is in the process of acquiring.

    The conclusions exceed management's initial expectations, as detailed in the
    announcement of 5 May 2015, that Mothae represents a low cost opportunity for
    Paragon to generate significant value for shareholders through the potential
    recovery of large high value diamonds.  Mothae is only 5 km from the world
    class Letšeng diamond mine in Lesotho which is located within a cluster of
    kimberlites, including Paragon's Lemphane Kimberlite Pipe Project ('Lemphane').

    These technical reports are intended as components of a future Preliminary
    Economic Assessment (PEA) and Pre-feasibility Study (PFS) and review multiple
    mining scenarios and simulated progressive cutting of processing costs, which
    will now be explored during final plant and open pit design work.

    Highlights of the studies include:

      * Potential to significantly increase Mothae's NPV from management's original
        estimates.
      * Improved strip ratio has been identified at <1:1 compared to <1.5:1
        previously assumed.
      * Potential for average diamond values up to US$2,000/ct..
      * Several Mining Scenarios exceeding 20Mt at US$40+/t ore value in a low
        operating cost mine exceeding 2Mt and 40,000 carats per year.

    These studies focussed on determining both the trade-off between maximum
    diamond value recovery against processing costs (using a range of bottom
    cut-off screen sizes-BCOS), as well as  optimum opencast mining scenarios at
    the Mothae Kimberlite based on the mining of the Main Pipe only, which
    comprises the South-West (SW), South-East (SE) and South-Central (SC) domains
    of the kimberlite.  The basis for both studies was the NI 43-101 Technical
    Report completed by Lucara Diamond Corporation in February 2013.

    Mothae Revised Diamond Revenue Models

    The revenue scenarios compiled by The MSA Group come from a sample of
    23,738 cts that were used to model the average diamond value per size class for
    each of the four kimberlite domains.  Average diamond values were calculated
    for three bottom cut-off screens (+2 mm; +3 mm; +4 mm) using three revenue
    models.  Key findings are summarised below:

      * The resource of Main Pipe (Southern Lobe) comprising SW+SC+SE Domains is
        estimated at 32.41 million tonnes at  an average diamond value of  US$1,352
        /ct and a grade of 2.2 cpht at a 3 mm bottom cut-off screen (BCOS).  The
        +20 ct diamond values were capped at US$6,492/ct for study purposes.
      * Upside potential of the planned mining area, SW+SC+SE Domains at US$1,971
        per carat and a grade of 2.2 cpht at 3 mm BCOS with +20 ct diamond value
        capped at US$11,057/ct, has been estimated.
      * A worst-case "Downside" model, which is based on modelled revenue of
        US$1,024/ct at 3 mm BCOS for SW+SC+SE, still yields US$22.53/t ore value,
        i.e. above anticipated break-even.  The "Downside" model at 3 mm BCOS also
        assumes overall diamond values circa 20% lower than those achieved in the
        actual 2012/13 valuation and sale of diamonds recovered during trial
        mining.
      * Modelled ore values at 3 mm BCOS of between US$29.75 and US$43.36/t would
        increase to US$32.77/t and US$48.07/t respectively by excluding the 6.8 Mt
        SE Domain.

    Summary of Indicated/Inferred Resource Tonnes and Average Grades & Values

       Bottom     Domain     Ind & Inf.                     Cumulative                
      Cut-off                                                                         
                                                                                      
                             Mt      cpht     Mt   cpht  US$/ct     US$/ct    US$/ct  
                                                          High       Med.       Low   
                                                                                      
       @ +2mm       SW        21.18     2.5  21.18  2.5    $1,887     $1,185      $895
                                                                                      
                   +SE         4.44     4.4  25.62  2.8    $1,777     $1,142      $864
                                                                                      
                   +SC         6.79     2.6  32.41  2.8    $1,640     $1,069      $812
                                                                                      
                    +N         6.55     2.4  38.96  2.7    $1,638     $1,076      $817
                                                                                      
                  Total       38.96     2.7                                           
                                                                                      
       @ +3mm       SW        21.18     2.0  21.18  2.0    $2,162     $1,469    $1,106
                                                                                      
                   +SE         4.44     3.5  25.62  2.3    $2,090     $1,425    $1,075
                                                                                      
                   +SC         6.79     1.9  32.41  2.2    $1,971     $1,352    $1,024
                                                                                      
                    +N         6.55     1.9  38.96  2.1    $1,991     $1,359    $1,028
                                                                                      
                  Total       38.96     2.1                                           
                                                                                      
       @ +4mm       SW        21.18     1.4  21.18  1.4    $3,016     $2,033    $1,519
                                                                                      
                   +SE         4.44     2.3  25.62  1.6    $2,946     $1,991    $1,490
                                                                                      
                   +SC         6.79     1.2  32.41  1.5    $2,833     $1,924    $1,443
                                                                                      
                    +N         6.55     1.3  38.96  1.5    $2,850     $1,932    $1,450
                                                                                      
                  Totals      38.96     1.5                                           

    Source:  The MSA Group J3105 report

    Mothae Opencast Mining Scenario Conclusions

    A sequence of eleven Whittle pit optimization scenarios were undertaken by The
    MSA Group, using 2 mm, 3 mm & 4 mm BCOS?with plant operating costs reduced by
    -5% to -20% in some scenarios (to reflect the coarser BCOS) and to include
    various elements of the geological domains.  Highlights are:

      * Optimum scenarios for mining the combined SW+SC+SE domains at a waste:ore
        ratio of 1:1 and either 3 mm or 4 mm BCOS yield a 12 year initial open pit
        life.
      * A typical scenario (SW+SC+SE @ 3 mm BCOS and -5% on processing costs)
        yields a provisional discounted pit value based on industry standard
        assumptions for Lesotho mining costs of US$ 190M at 10% discount on a
        resource of 22.6 Mt producing ~42,000 carats per annum over a 12 year open
        pit life.  Capital expenditure, financing, taxation etc. were not included
        in the analysis.
      * The possibility to increase pit depth to in excess of 300 m at a waste:ore
        ratio of under 1.5:1 and to incorporate additional kimberlite domains into
        the mine plan subject to ongoing resource development work.
      * Note, the potential differences in processing related to different amounts
        of plant throughput due to increased bottom cut-off screen sizes were
        simulated by progressively cutting processing costs.  This expediency is
        broadly indicative of the expected cost-savings (both capital and
        operating) that would be associated with the different plant
        configurations.  Paragon will conduct a PEA or a PFS to more accurately
        quantify the potential cost savings associated with larger bottom screen
        cut-off sizes and to determine overall longer-term project viability.

    Dr Stephen Grimmer, Managing Director, said:

    "The reports compiled by The MSA Group confirm and exceed Paragon Diamonds'
    initial internal projections of the resource being acquired at Mothae.  It is
    clear that the combined SW+SC domains in particular represent a higher-value,
    relatively higher-grade resource, exceeding 25 Mt in total, with the potential
    for a significant percentage of carats present in large diamonds.  At 3 mm the
    grade is 2.3 cpht and US$1,425/ct ("Best Estimate") with potential upside for
    US$2,090/ct (the "Upside").

    "It is important to note that in the "Best Estimate" case, the report caps all
    diamonds above 20 cts at US$6,492/ct value - even in the "Upside Scenario" all
    diamonds above 20 cts are still capped at US$11,057/ct.  Large Lesotho diamonds
    range up to US$70,000/ct and Mothae itself has historically achieved US$50,000+
    /ct for a large diamond in December 2011.  At a 4 mm BCOS the entire ~5 Ha and
    32 Mt Southern Lobe (SW+SC+SE) has a grade of 1.5 cpht and a "Best Estimate" of
    US$1,924/ct (~US$2,800/ct with "Upside").  This is comparable in potential
    grade and average diamond value to the ~4 Ha Letšeng Satellite pipe, only 5 km
    distant, and the mainstay of production at that mine.

    "The favorable ~1:1 waste:ore ratio (compared to initial in-house estimates as
    high as 1.5:1) should result in operating cost savings of up to US$1-2/t based
    on industry-standard mining contractor costs of  ZAR25-30/t plus fuel and as
    provided in the MSA Report.  Further cost reductions could result from using
    extensive X-ray transmission recovery (XRT) technology to reduce water and
    power consumption and waste generation and at the same time more reliable
    recovery of large diamonds with reduced breakage."

    Funding Update

    The Company is in advanced negotiations with several funding providers as it
    looks to complete the acquisition of a 75% interest in, and operatorship of,
    Mothae from Lucara Diamond Corporation ('Lucara'), a TSX quoted mining company
    (the 'Acquisition").  Subsequent to the conclusion of these negotiations, the
    Board will select and announce what it deems to be the best funding package
    available.  The proposed funding package from International Triangle General
    Trading LLC ('ITGT') for the Company's existing Lemphane Project, as set out in
    the announcements dated 28 January 2015 and 5 May 2015 respectively, also
    remains subject to final negotiation and contract.  As such, the Board may
    agree a funding package for both Mothae, and the Lemphane project with a party
    other than ITGT and on terms that differ from those which have previously been
    announced, but which may prove to be more commercially attractive to
    shareholders overall.

    The Board remains confident that the selected funding package for both Mothae
    and Lemphane will be agreed in order to meet the terms of the Acquisition or
    any revisions thereto.

    Mr. Simon Retter, Finance Director said:

    "Subsequent to the new and positive confirmations provided by The MSA Group
    reports on Mothae, the Board has been intensively and positively refining the
    Company's funding options with potential financing partners from an enhanced
    commercial position.  Several funding options are in advanced stage
    negotiations, with due diligence now complete, and as previously announced it
    is possible that the Company may seek ITGT to fund the downstream diamond
    operations in Dubai, with an alternative funder providing capital to initiate
    and accelerate mining at both Mothae and Lemphane.  We look forward to updating
    shareholders further later this month."

                                       **ENDS**                                    

    For further information please visit www.paragondiamonds.com or contact:

    Philip Falzon Sant             Paragon Diamonds             +44 (0) 20 7182 1920      
    Manduca                  Limited                                                      
                                                                                          
    Simon Retter                   Paragon Diamonds             +44 (0) 20 7182 1920      
                             Limited                                                      
                                                                                          
    David Hignell                  Northland Capital Partners   +44 (0) 20 7382 1100      
    Gerry Beaney             Limited                                                      
                                   (Nominated Adviser)                                    
                                                                                          
    John Howes                     Northland Capital Partners   +44 (0) 20 7382 1100      
    Mark Treharne            Limited                                                      
                                   (Sales and broking)                                    
                                                                                          
    Felicity Winkles               St Brides Partners Limited   +44 (0) 20 7236 1177      
                                                                                          
    Frank Buhagiar                 St Brides Partners Limited   +44 (0) 20 7236 1177      

    Notes

    Paragon Diamonds has an 80% interest in the Lemphane Kimberlite Pipe project in
    Lesotho, located close to the world class Letšeng mine, Lesotho's largest
    diamond mine.  Lemphane is the last known kimberlite to be developed in
    Lesotho.  The first of a two stage production programme is expected to commence
    in 2015 which will further define the resource at Lemphane. As increased
    tonnages of kimberlite are processed the proportion of larger diamonds
    recovered will improve, increasing the average value of diamonds recovered at
    the project, as was the case at Letšeng. In addition to Lemphane, Paragon
    Diamonds has signed a Memorandum of Understanding with Lucara Diamond
    Corporation, a TSX quoted mining company, to acquire a 75% interest in and
    operate the defined Mothae Kimberlite Resource, which is located only 5 km from
    the world class Let?eng le Terai diamond mine in Lesotho.

    In accordance with the AIM Rules for Companies, the information in this
    announcement has been reviewed by Dr Stephen Grimmer PhD., Msc., a qualified
    geologist with over 25 years diamond exploration experience.