On March 20, 2019, Newater Technology Inc. delivered the system for China Everbright Group’s landfill leachate treatment project located in Jinan, Shandong Province after the two parties signed the contract on March 4, 2019. The total leachate volume for the project is over 1.5 million tons and Newater was entrusted to manufacture and deliver a system with a 1,100-ton-per-day capacity within 20 days. Regarding that a DTRO system with such size typically requires a manufacture time of 2 to 3 months, Newater crashed the schedule by leveraging its experience in leachate projects, as well as its fully-automated production line, modular design concept, and build-to-stock inventory models, and delivered the system in just 16 days, setting a new record in the leachate treatment industry.