Press Release - 11 January 2016

Publication of the documents and opinions on the estimated cost of Cigéo

Andra, EDF and AREVA all wish to bring insights into the construction of the assessment of the costs of Cigéo as documents and opinions are disclosed today by the ASN on the project costing.

 

Following the sketch studies (2012-2014), Andra provided the French state with a costing report regarding Cigéo. The Ministry in charge of Energy has consulted with the Nuclear Safety Authority (ASN) and the nuclear operators involved, EDF, CEA and Areva - which will be the future users of the storage facility and will provide full funding - to gather their views on this report.

 

This assessment of the cost of Cigéo is released ahead of the submission by Andra of the safety options report to ASN in the course of 2016 and of the start of detailed design studies, which constitute key milestones for configuring the Cigéo project and for its costing.

 

The development and construction of the storage facility will take place gradually over its entire operating life and will also integrate optimizations and innovations compared to the sketch, some of which are already identified. Thus, there are different visions of the project costing, depending on anticipations of technological advances and optimizations that can be developed and valued in subsequent phases of the studies.

 

In order to converge, many technical discussions are currently taking place between Andra, project owner of the project and the nuclear operators concerned, EDF, AREVA and CEA. These discussions allow sharing a common storage concept, optimization leads to study and the related technical and economic issues. These optimizations are studied by Andra with the aim to implement them throughout the different phases of the storage facility construction, without reducing the level of safety and security.

 

During the recent visit of EDF's Chief Executive Officer at the underground Laboratory, the Managing Director of Andra and EDF's CEO expressed their commitment to strengthen their cooperation in 2016 to optimize the design of this major project. Andra and EDF also agreed to study how EDF will support Andra and how Andra can benefit from EDF's industrial experience in the project implementation phase.

 

 

 

About the Cigéo project

 

The Cigéo project is designed to ensure long-term management of the radioactive waste produced by nuclear facilities in France, in accordance with the Environmental Code. This waste is now packaged and stored by nuclear operators that produced them in specific and secure facilities, under their responsibility. Andra conducts research on storage in deep geological formations for over 20 years including at the underground laboratory Meuse / Haute-Marne. The project is now coming to the end of the phase of preliminary design. Studies of detailed design will be conducted in 2016-2017 to develop the creation authorization application. Subject to authorization, the construction of the storage facility could start in 2020.

 

The costing reports cover:

- First, studies, technology trials, investments for the construction and operation of the facility for the pilot industrial phase of Cigéo spread over twenty years.

- Then, spread over a hundred years, future expenses related to the construction and the current operating phase of Cigéo. These costs will cover the construction of new disposal cells as and when new waste is managed, the monitoring, maintenance and periodic renewal of industrial equipments, operation and closure of the storage facility, fiscal charges and taxes.

 

 

Financing of Cigéo

 

Financing of Cigéo is supported in full by nuclear operators (EDF, CEA and Areva).

According to the Code de l'environnement (environmental legislative and regulatory framework), the financing is secured in their accounts by provisions backed by dedicated assets, under the control of the Ministry of Energy. The reference cost of the Cigéo storage considered at present by EDF, AREVA and CEA results of the assessment of a working group led in 2005 by the Ministry in charge of energy and that included Andra, EDF, AREVA, the CEA and ASN. It is the responsibility of the Minister in charge of energy to decide, in light of available evidence and the progress of the project, whether to set a new reference estimated cost of storage.

 

The Court of Auditors (Cour des comptes) estimated that the cost of storage is in the order of 1 to 2% of the total cost of electricity generation throughout the operating life of a reactor. The different costing assumptions for the Cigéo project do not impact significantly the cost of electricity for French consumers.

 

 

EDF Contacts:

Press: +33 1 40 42 46 37

Analysts & investors: +33 1 40 42 40 38

About EDF Group

A key player in energy transition, the EDF Group is an integrated electricity company, active in all areas of the business: generation, transmission, distribution, energy supply and trading, energy services. A global leader in low-carbon energies, the Group has developed a diversified generation mix based on nuclear power, hydropower, new renewable energies and thermal energy. The Group is involved in supplying energy and services to approximately 37.8 million customers, of which 28.3 million in France. The Group generated consolidated sales of €72.9 billion in 2014, of which 45.2% outside of France. EDF is listed on the Paris Stock Exchange.

 

Contacts AREVA:
Press office: 01 34 96 12 15
Investor relations: 01 34 96 11 53

About AREVA
AREVA is a world leader in nuclear power. The group proposes an offer to utilities covering every stage of the fuel cycle, the design and construction of nuclear reactors, as well as services for their exploitation. Its expertise and unwavering insistence on safety makes it a key player in the sector. AREVA is also investing in renewable energy in order to develop solutions in partnership with high technological content. Thanks to the complementary nuclear and renewable, the 45,000 AREVA employees are helping to build the energy model of the future: to provide the largest number ever safer energy with less CO2.

Contact Andra
Press office: 01 46 11 83 01

About Andra
The National Agency for Radioactive Waste Management (Andra) is a public industrial and commercial entity established by the law of 30 December 1991. Its missions were completed by the Planning Act of 28 June 2006 on the sustainable management radioactive materials and waste. Independent of radioactive waste producers, Andra is under the supervision of the Ministries in charge of energy, environment and research.
Andra puts its expertise at the state service to find, implement and ensure safe management solutions for all French radioactive waste in order to protect present and future generations of the risk posed by these wastes.

 


PR CIGEO ANDRA:
http://hugin.info/143450/R/1978158/724411.pdf



This announcement is distributed by NASDAQ OMX Corporate Solutions on behalf of NASDAQ OMX Corporate Solutions clients.
The issuer of this announcement warrants that they are solely responsible for the content, accuracy and originality of the information contained therein.
Source: EDF via Globenewswire

HUG#1978158