In Disclosure and Barring Service v
Background
In
The project faced significant delays and issues, leading to claims and counterclaims between the parties for delay damages and losses caused by alleged software defects. TCS raised a claim against DBS for breach of contract valued at Ł110.2 million, and a claim of Ł14.3 million for underpayment. DBS counterclaimed for delay and defect losses totalling Ł108.7 million.
On interpretation of a liability clause, the Technology and Construction Court ("TCC") found that TCS's liability was capped at Ł10 million, and that a separate condition precedent applied to the entitlement of both parties. TCS was awarded Ł4.8 million after set-off. DBS was subsequently granted leave to appeal on the existence of the condition precedent at clause 6.1, which it claimed prevented DBS from being able to recover Delay Payments (akin to liquidated damages).
Conditions precedent
A condition precedent is a contractual term that requires a specific event or action to occur before a party's obligation or right is enforceable. The condition precedent was whether DBS's right to claim Delay Payments under clause 6.2 was contingent upon its compliance with clause 6.1, which required the prompt issuance of a Non-conformance Report ("NCR") following failure to meet an acceptance test or milestone due to TCS's default:
"6.1If a Deliverable does not satisfy the Acceptance Test Success Criteria and/or a Milestone is not Achieved due to the CONTRACTOR's Default, the AUTHORITY shall promptly issue a Non-conformance Report to the CONTRACTOR categorising the Test Issues as described in the Testing Procedures or setting out in detail the non-conformities of the Deliverable where no Testing has taken place, including any other reasons for the relevant Milestone not being Achieved and the consequential impact on any other Milestones. The AUTHORITY will then have the options set out in clause 6.2."
The Court of Appeal agreed with the TCC's ruling that clause 6.1 was a condition precedent. DBS's failure to fulfil the condition precedent (by failing to provide the NCR) meant that the remedies contained within clause 6.2, including the right to claim Delay Payments, were not available to DBS.
The appeal judgment addressed the question of how to identify and interpret conditions precedent clauses. The main arguments can be categorised as follows:
1. The language of clause 6.1
DBS complained that:
- the language of clause 6.1 was not clear enough to suggest that, without an NCR, clause 6.2 did not apply;
- clause 6.1 did not contain the words, 'condition precedent'; and
- the TCC ruling relied too heavily on the 'if-then' phrase.
In his judgment,
With regard to DBS's 'if-then' argument, DBS relied upon the two stages at clause 6.1, the first being the failure to satisfy the "Acceptance Test Success Criteria" or reach a "Milestone" date, and the second being to issue an NCR. DBS argued that only the first stage was provisional on an NCR being issued. DBS also argued that the use of the first comma in clause 6.1 meant that although an NCR was mandatory, it was not a condition precedent.
2. Lack of clarity
DBS also argued that the TCC gave too much weight to the use of the word "shall".
3. Inconsistent language
Key takeaways
-
While the
- The court will give effect to the words that are "actually used", and it is therefore imperative that conditionality is apparent, regardless of precise timescales or consistency across the contract. There is no requirement to include the words "condition precedent" in a clause, but the use of these words would assist if the clause is intended to be a condition precedent.
- Requiring something to be done 'promptly' will not undermine a condition precedent clause, but having a precise deadline will always aid clarity.
- The ruling also highlights the importance of adhering to contractual provisions, so as to avoid losing an entitlement.
The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.
Mr
1 Exchange Crescent,
EH3 8UL
Tel: 131228 9900
Fax: 131228 1222
E-mail: paulina.barela@shepwedd.com
URL: www.shepwedd.com
© Mondaq Ltd, 2025 - Tel. +44 (0)20 8544 8300 - http://www.mondaq.com, source