Presentation of
RESULTS
for the six months ended 31 December 2024
Niël Pretorius
Chief Executive Officer
Riaan Davel
Chief Financial Officer
Results for the six months ended 31 December 2024 / Page 3
CONTENTS
1 | Our purpose and Vision 28 | Slide 5 | 4 | Sustainable development performance | Slide 22 | |
Setting up for the next phase | Slide 6 | Environmental performance | Slide 23 | |||
Solar plant completion | Slide 7 | Social performance | Slide 24 | |||
Capital infrastructure | Slide 8 | Governance | Slide 25 | |||
2 | Operating performance | Slide 10 | 5 | Looking ahead | Slide 26 | |
Ergo operating trends | Slide 11 | Outlook | Slide 27 | |||
FWGR operating trends | Slide 12 | Delivering on our purpose | Slide 28 | |||
Group operating trends | Slide 13 | Contact us | Slide 29 | |||
3 | Financial performance | Slide 14 | ||||
Ergo financial results | Slide 15 | |||||
FWGR financial results | Slide 16 | |||||
Group financial results | Slide 17 | |||||
Financial review: P&L | Slide 18 | |||||
Financial review: SFP | Slide 19 | |||||
Financial review:SCF | Slide 20 | |||||
Share price | Slide 21 | |||||
Results for the six months ended 31 December 2024 / Page 4
PERFORMANCE AT A GLANCE
as at 31 December 2024
18th consecutive financial year of dividends: lnterim cash dividend of 30 cps
Financial
Operational
Sustainable development
Revenue | Operating profit |
R3 802.3m | R1 578.7m |
28% increase | 74% increase |
26% | Headline |
earnings | |
increase | |
R970.1m | |
in the average Rand | |
gold price received to | 65% increase |
R1 478 663/kg | |
Capital expenditure | |
R947.6m | |
(HY1 FY2024: R1 074.7m) |
Production
2 564kg
1% increase
Throughput
12.9Mt
16% increase
Cash operating costs of
R866 221/kg
6% increase
All-in sustaining costs margin
of 35%
Average yield
0.199g/t
(HY1 FY2024: 0.228g/t)
Rand per tonne (R/t)
R172
9% decrease
Solar plant and battery energy storage system practically commissioned
Electricity | Potable water |
consumption | consumption |
141 333MWh | 551 MI |
16% decrease | 3% increase |
Hectares | Dust exceedances |
vegetated | increased |
28ha | to 3.7% |
(HY1 FY2024: 15ha) | of total number of |
measurements |
No fatalities
Section 1
Our purpose and Vision 28
Results for the six months ended 31 December 2024 / Page 6
Positioning for the next phase: Vision 28
Vision 28: capital infrastructure | 3mtpm | 6tpa |
development designed for | ||
FY2028 and beyond | Tonnage throughput | Gold production |
fund Ergo 2.0 | 1.650mtpm |
Depleted Ergo sites replaced to | |
Interim throughput capacity |
FWGR Phase II expansion underway
0.6mtpm to 1.2mtpm
To make this a reality, we are pursuing our aggressive capital reinvestment programme to create the capacity infrastructure to
realise our Vision for FY2028 and beyond
Results for the six months ended 31 December 2024 / Page 7
PRACTICAL COMPLETION OF OUR SOLAR PLANT AT ERGO
A milestone in sustainable energy
Advancing circularity, optimising costs and strengthening energy security
2020 | 2021 | 2022 | 2023 | 2024 |
Conceptualisation | Feasibility study and | Completion of | ||
and planning | regulations | feasibility study and | ||
commencement | ||||
• Exploring solar | • | Regulatory | • | Definitive feasibility |
power as a backup | approval | study completed | ||
amid ongoing | • | Ongoing definitive | • | Commencement of |
energy crises and | feasibility study | Phase 1 of the solar | ||
disruptions | project at Ergo | |||
• | Installation of | |||
medium voltage grid | ||||
connection |
Continuous capital | Enhancing operational efficiency, sustainability | |||
investment and | and reducing electricity costs | |||
approval of Phase 2 | ||||
• | Phase 2 60MW | • | Solar plant and BESS | • To contribute |
solar project | practically | approximately half of | ||
approved | commissioned | Ergo's energy | ||
• | Battery energy | • | Formal grid | consumption in FY2025, |
storage system | connection certificate | reducing Ergo's electricity | ||
(BESS) of 160MWh | received | costs by R9-R15/t |
approved
Results for the six months ended 31 December 2024 / Page 8
CAPITAL INFRASTRUCTURE DEVELOPMENTS TO REALISE VISION 2028
Enabling production capacity growth and operational resilience
WITHOK TSF RECOMMISSIONING AT ERGO
First public consultation for the recommissioning of the Withok TSF completed in December 2024.
Scoping documents in support of environmental authorisations to the DMRE submitted and commenced a water use license application to the DWS.
July 2025 - submission of all required final documents.
Results for the six months ended 31 December 2024 / Page 9
CAPITAL INFRASTRUCTURE DEVELOPMENTS TO REALISE VISION 2028 continued
Enabling production capacity growth and operational resilience
PHASE II PROJECT AT FWGR
Regional Tailings Storage Facility (RTSF)
Construction of the RTSF progressing well since work started.
2 million m3 of ground moved to date.
To commence installation of the liner for the facility.
Extensive Pipeline Infrastructure
Approximately 13km of residue pipelines and water pipelines installed.
Driefontein 2 Plant expansion
Civil works on the expansion of Driefontein 2 Pant progressing well and majority of earthworks have been completed.
Contractor appointed to commence with Structural, Mechanical Installation, Plate work and Piping (SMPP) on site.
Section 2
Operating performance
Attention: This is an excerpt of the original content. To continue reading it, access the original document here. |