Fortescue Ltd (Fortescue, ASX: FMG) is pleased to announce it is accelerating delivery of the world's first industrial and fully integrated green energy grid dedicated to eliminating fossil fuels from large-scale industry, at a scale comparable to a city.

Fortescue intends to replicate and commercialise this technology wherever it is invited.

The Company is targeting diesel elimination in particular - a fuel that is 100 per cent imported and subject to extreme price volatility, unreliability and hardship - that also costs the taxpayer billions in subsidies.

Unlike other large renewable hubs, which feed intermittently into national or other power systems, Fortescue's off-grid system will be the largest of its kind dedicated to decarbonising major industry, around the clock.

By early next year, the Company expects to complete 290MW of installed renewable capacity to meet the fixed energy requirements of its ore processing facilities, enabling daytime 'green processing' across its Pilbara operations. Later that year, the system will power all of Fortescue's operations for 24-hour periods without fossil fuels.

This is well ahead of previously announced Real Zero plans, targeting December 2030.

Fortescue is expecting full completion of its Pilbara green grid by the end of 2028, in line with Real Zero. This includes 1.2GW of solar capacity, more than 600MW of wind generation, and 4-5GWh of battery energy storage.

As global energy supply chains become increasingly unstable and the massive risks of fossil fuel dependence are exposed, Fortescue is moving faster - proving industry can power itself with green energy, control its costs, and take back control of its largest risk - energy.

Deployment underway

The deployment of Fortescue's green grid infrastructure has commenced within its approved decarbonisation budget (not adjusted for inflation) and on an accelerated timetable.

By the completion of Fortescue's profitable decarbonisation program, it is targeting approximately 2GW of generation capacity.

This system incorporates

Large-scale battery infrastructure (approximately 4-5GWh)

Proprietary AI-driven optimisation systems

Fortescue-developed in-house technologies and know how.

The deployment will support the replacement and electrification of: Fixed plant operations, including Fortescue's port infrastructure

All of Fortescue's large-scale iron ore processing facilities

End-to-end processing and logistics infrastructure

On-site accommodation and services supporting a workforce of approximately 10,000 personnel.

The Company expects implementation to ramp up within two years, subject to delivery schedules and commissioning.

Fortescue also confirms it expects to save US$100 million in fossil fuel costs by next year, and at the completion of its decarbonisation program, expects to see a further reduction in C1 unit costs of at least US$2 - US$4/wet metric tonne. This demonstrates that eliminating fossil fuels is not only achievable, but economically superior.

This deployment shows that a fully integrated renewable energy system can be built at speed and scale, delivering immediate benefits in cost, certainty and energy security. Fortescue will make these systems available via a license or as a provided service to major energy users.

Project scale

Following the successful development of its profitable decarbonisation program, Fortescue sees a clear pathway to expand its green energy system by a further approximately 2GW of power generation capacity, firmed with 4GWh of advanced batteries. This would be enabled by Fortescue's proprietary know-how, patented technologies and exclusively developed AI, and is expected to be delivered for less than US$2.5 billion.

The Company anticipates this capacity could be progressively delivered over an approximately 18-month timeframe (subject to final investment decisions). This represents a breakthrough in terms of delivering firmed energy generation in speed to market, capital costs and operating costs

World-first integrated green grid

Upon completion, Fortescue expects this economic project will represent the first fully integrated industrial green grid of its scale globally, supporting an entire mining ecosystem including: Processing facilities

Rail infrastructure

Ports and logistics

Mobile and fixed equipment.

Fortescue has improved the speed of deployment of renewables, lowering the capital intensity, improving operating cost profile and making it highly competitive with traditional fossil fuel-based generation systems.

Scalability and replication

Fortescue intends to replicate this green grid model globally and believes that: Delivery timelines may be further accelerated for future projects

Costs will reduce as scale increases and deployment experience grows

Contact:

Email: media@fortescue.com

Tel: 1800 134 442

Email: investors@fortescue.com

Tel: +61 8 9230 1647

(C) 2026 Electronic News Publishing, source ENP Newswire